Professional Documents
Culture Documents
Final Note
Final Note
I. LIST OF DATES
Date Particulars
February 27, 2012 NTPC Limited (‘Appellant Employer’) issued Letter of Award for site levelling and infrastructure works package for Kudgi Super Thermal
Power Plant Stage-I (3x800MW) in favour of Sri Avantika Contractors (India) Limited (‘Respondent Contractor’) for a value of Rs.154 Crores.
April to September 2012 The Appellant Employer issued letters for progressive handing over of various sites. In all these letters, the Respondent Contractor highlights
the absence of unhindered physical access to execute the said Project. (Refer Annexure-A4)
February 2013 Respondent Contractor shared the entire set of Initial Levels/ OGL records with Appellant Employer
June 15, 2013 The Appellant Employer issued a letter disputing the OGL records of the Respondent Contractor. Pertinently, the letter mentioned that
Appellant was itself maintaining the initial levels records which they stored in the system in presence of engineer of Appellant Employer and
Respondent Contractor, and subsequently, these records were downloaded and self-certified by the 2 officers of Appellant Employer. It is
pertinent to note the OGL records maintained by Appellant did not bear any signature of the Respondent Contractor (which is violative of
Clause 2.9 of Technical Specifications)
June 21, 2013 The Respondent Contractor alleged violation on the part of Appellant Employer inasmuch as the records of spot levels or initial levels
indicated in letter dated June 21, 2013 were not jointly signed by the authorised representative of both the parties. It further shared jointly
signed records of spot levels maintained and asked the Appellant Employer to verify the same.
August 5, 2013 The NGT vide its Order banned the mining or removal of sand from river beds across the country without a specific licence or order of
(NGT sand-mining Ban) environmental clearance from Ministry of Environment and Forestry (‘MoEF’). This severely impacted the progress of said Project.
November 9, 2013 Appellant vide its letter dated November 9, 2013, extended the completion period for a further period of 6 months’ time till Feb 2015.
(6 months Extension)
February 19, 2014 The Appellant Employer issued drawings for construction (excavation) of raw water reservoirs (plans and sections).The Appellant Employer
also issued a separate letter alleging delays on the part of Respondent Contractor.
February 27, 2014 The Appellant Employer issued 7 day’s show cause notice under Clause 51.3.1(a) of the GCC alleging delays in execution of said Project and
(7 Day Show Cause directing the Respondent Contractor to mobilise men and machinery and re-start the work.
Notice)
February 28, 2014 The Appellant Employer issued Amendment No. 2 to the LoA whereby it increased the contract value from Rs.154 Crores to Rs.189 Crores on
account of extra-works undertaken and substitutions made by Appellant Employer.
March 4, 2014 The Respondent Contractor issued a reply letter to the Appellant Employer’s 7days’s show cause notice dated February 27, 2014 summarising
(1st reply to Show cause) the reasons for delay in execution of said Project.
March 6, 2014 Respondent Contractor raised R.A. Bill No. 15 for an amount of Rs 47.15 Crores. The quantification of work done was based on OGL’s.
(RA Bill 15)
March 13, 2014 The National Green Tribunal (‘NGT’) passed an Order in the matter of M.P. Patil v. UoI & Ors. (including the Appellant Employer). The NGT
vide its Order set aside the environmental clearance granted by MoEF for the said Project, and remanded the issue back to MoEF for fresh
Palit & Co | August 28, 2020| Revised Note
consideration. It further issued orders for status quo till further orders by the MoEF.
March 13, 2014 The Respondent Contractor issued another letter in reply to the Appellant Employer’s 7days’s show cause notice dated February 27, 2014
nd
(2 reply to Show cause) summarising the reasons for delay in execution of said Project.
March 14, 2014 The Appellant Employer issued letter to all its contractors, including the Respondent Contractor, intimating the order of status quo issued by
NGT. Apropos the said order, the Appellant Employer in its letter directed the Respondent Contractor to temporarily halt the construction
activities.
March 24, 2014 The Appellant Employer issued a letter terminating the contract for said Project, i.e. LOA, executed with Respondent Contractor. The
Appellant Employer in its letter attributed the delays in execution of said Project to Respondent Contractor.
March 25, 2014 The Supreme Court of India vide its Order in an appeal filed by Appellant Employer stayed the operation of NGT’s Order dated March 13,
2014.
July 20, 2014 16th & Final Bill was raised by the Respondent Contractor.
(16th & Final Bill)
November 30, 2015 and The Respondent Contractor invoked the arbitration agreement and the Arbitral Tribunal was entered upon reference.
January 16, 2016
July 7, 2017 The Arbitral Tribunal passed Arbitral Award whereby a sum of Rs.47 Crores was awarded to the Respondent Contractor along with post
(ARBITRAL AWARD) award interest of 8.9%.
August 27, 2017 NTPC filed a complaint before the Anti-Corruption Branch, CBI, Bangalore, alleging collusion and foul play between Respondent Contractor’s
(CBI F.I.R) representatives and NTPC representatives and forgery of initial levels / OGLs. FIR No. R.C.15(A)/2017 was registered under Section 420, 468
of Indian Penal Code, 1860 and Section 13 of Prevention of Corruption Act, 1988.
October 26, 2017 The Appellant Employer filed a petition challenging the Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996
(‘Arbitration Act’). The Ld. Single Judge was pleased to stay the Arbitral Award subject to deposit of 50 per cent. of the awarded amount. The
aforesaid amount was deposited on November 16, 2017.
*Along with the Section 34 petition, The Appellant Employer had filed an interlocutory application being I A No. 11990 of 2017, praying for
taking cognizance of FIR dated 27.08.2017 registered by the CBI, however the application was not pressed by the Appellant Employer and
was directed to be ‘dismissed as withdrawn’ with a liberty to file afresh if required.
February 9, 2018 The Respondent Contractor preferred an application under Section 9 of the Arbitration Act being OMP(I) (COMM) 75 of 2018, seeking release
of the deposited sum.
April 18, 2018 The Ld. Single Judge in Section 9 petition was pleased to release the deposited sum subject to furnishing of bank guarantee.
(RELEASE OF DESPOSIT)
May 7, 2018 The Appellant Employer preferred an appeal being FAO(OS) 94 of 2018 against the Order of Ld. Single Judge in Section 9 petition directing
(STAY ON RELEASE) release of deposited sum. The Ld. Division Bench vide its Order stayed the release of deposited sum.
March 3, 2019 The Ld. Division Bench disposed of the appeal i.e. FAO(OS) 94 of 2018, considering that the Section 34 challenge petition was at the stage of
final arguments and therefore, directed the continuance of the interim stay order till the conclusion of the Section 34 petition and
further directed that the orders in relation to release of deposited amount will be passed at the time of final disposal of the said challenge
petition.
Palit & Co | August 28, 2020| Revised Note
June 8, 2020 The Ld. Single Judge of the Delhi High Court passed Impugned Judgment in the petition challenging the Arbitral Award, upholding the same in
(IMPUGNED JUDGMENT) respect of all issues, except insofar as the award of claim for loss of profit is concerned.
No directions in relation to the release of the deposited sum was contained in the Judgment, as directed of the Ld. Division Bench in FAO(OS)
94 of 2018 in its aforesaid Order dated March 3, 2019.
July 3, 2020 Respondent Contractor filed Execution Petition seeking enforcement of Judgment dated June 8, 2020 along with an application for release of
deposited sum in in terms of Ld. Division Bench’s Order dated March 3, 2019. Notice was issued to the Appellant Employer. Ld Senior Counsel
appearing for Appellant Employer expressed that they are contemplating to file an appeal against Impugned Judgment and therefore
opposed the prayer for release of deposited sum. Accordingly, the Ld. Judge was pleased to defer the hearing to August 6, 2020.
Claims filed by Respondent Contractor/ Claimant - 36 claims for a total amount of INR 139.14 crores (Pg. 1000)
Counter claims filed by Appellant Employer - 16 counter claims for a total amount of INR 185,82 crores (Pg. 1001)
Issues framed by AT (Pg. 1002)
A. Issue No. 1 – Whether the Respondent is liable for the various delays as set out in the Statement of Claims and if so, to what extent?
B. Issue No. 2 – Whether the Claimant is liable for various delays as set out in the Statement of Defence/ Counter Claims and if so, to what extent?
C. Issue No. 3 – Whether the termination of the Contract by the Respondent at the risk and cost of the Claimant is contractually and legally sustainable?
D. Issue No. 4 – Whether the issue of measurements fall within the jurisdiction of the Arbitral Tribunal to adjudicate?
Palit & Co | August 28, 2020| Revised Note
E. Issue No. 5 – Whether the Claimant is entitled to the claims from Claim-1 to Claim- 36 as set out in the Statement of Claim and if so, to what amounts?
F. Issue No. 6 – Whether the Respondent is entitled to its counter-claims from Counter-Claim-1 to Counter-Claim- 16 as set out in the Statement of Counter
Claims and if so, to what amounts?
Award – AT awarded a total amount of INR 50,21,54,497/- towards the Claims No. 2, 4, 5, 6 and 24 and rejected the other claims of the Respondent Contractor.
(Ref: Pg No. 1127, Para 328) Further AT awarded a total sum of INR 2,67,23,699/- to Appellant Employer towards Counter Claims No. 3, 4, 5 and 6. (Ref: Pg No.
1150, Para 413). After set off- an award of INR 47, 54,30,798/- in favour of Respondent Contractor along with an future interest @ 8.9% simple interest (Ref: Pg
No. 1151, Para 415)
Claim Awarded to Respondent Contractor Amount claimed Amount awarded by Total awarded amount
by Appellant/ Arbitral Tribunal including pre-award interest at
Contractor the rate of 14% per annum
CLAIM NO. 2 3,08,69,089/- 3,08,69,089/- 4,48,05,003/-
Refund of Performance Bank amount illegally encashed by the Respondent
(Pg No. 1072, Para 182 to Pg No. 1073, Para 186)
CLAIM NO. 4 5,94,98,878/- 5,94,98,878/- 8,63,59,769/-
Refund of retention money withheld at 10% of the Gross Running Account
Bills
(Pg No. 1076, Para 193 to Pg No. 1077, Para 197)
CLAIM NO. 5 1,08,74,198/- 1,08,74,198/- 1,57,83,377/-
Refund of Mobilization Advance Recovered from R.A. Bill
(Pg No. 1077, Para 198 to Pg No. 1079, Para 203)
CLAIM NO. 6 57,01,01,198/- 13,17,67,675/- 19,12,54,463/-
Payment of Total Work Done Bills
(Pg No. 1079, Para 204 to Pg No. 1101, Para 241)
CLAIM NO. 24 11,89,52,804/- 11,29,57,149/- 16,39,51,886/-
Payment towards overheads and profits
Pg No. 1114, Para 286 to Pg No. 1121, Para 307)
V. JUDGMENT DATED 8TH JUNE 2020 IN OMP (COMM) 370 of 2017 (‘IMPUGNED JUDGMENT’)
The Ld. Single Judge has partly allowed the Section 34 petition while upholding the claims awarded in favour of the Appellant Contractor by AT under Claim No. 2, 4,
5, 6 and further only allowing Claim No. 24 to the extent of ‘overheads’ awarded however, setting aside the claim awarded to towards ‘Loss of Profit’ Appellant
Contractor, holding that no proof for loss suffered was provided to sustain the claim.
Palit & Co | August 28, 2020| Revised Note
AT had awarded an amount of Rs 11,14,21,440/- (i.e. principal amount of Rs 7, 68,00,000/- plus simple interest of Rs 3,46,21,440/- @ 14%) towards ‘Loss of Profit’.
Pursuant to the Impugned Judgment dated 8 th June 2020, upon deducting the amount of Rs 11,14,21,440/- awarded by AT towards ‘Loss of Profit’, the Respondent
is entitled to receive an amount of Rs 36,40,09,358/- along with post Award simple interest @ 8.9 %, from the date of the Award i.e. 07.07.2017 till payment.
Our Submissions: The findings and conclusions of the AT are based on detailed appreciation and appraisement of the evidence on record and the interpretation of the
contractual provisions. It is settled law that the arbitrator is the sole judge of the quantity and quality of evidence and the Hon’ble Court doesn’t possess the power to re-
appreciate the evidence once the arbitrator has provided its reasons in relation to arriving at its conclusions. In the present case, the conclusions of AT are unanimous
and supported with facts and reasons. The decision on issues are plausible views which could not be interfered by the Hon’ble court as the Ld. Single Judge has rightly
observed in the Impugned Judgment. The scope of appeal under Section 37 of the 1996 Act is even more narrow than Section 34 where a Court is not permitted to
interfere in an award unless the award is so perverse that it shocks the conscience of the Court. It is also equally settled that a Court cannot act as a court of appeal qua
an arbitral award challenged before it. In fact, it has also been held by various Courts including the Hon’ble Supreme Court of India that even errors of facts cannot be
corrected under Section 34 of the 1996 Act, which the Ld. Single Judge has correctly appreciated. Therefore, none of the grounds raised by the Petitioner fall within the
Palit & Co | August 28, 2020| Revised Note
ambit of Section 37 and therefore the present appeal is not maintainable. The Appellant Employer is solely attempting to have a re-trial of the disputes and issues which
have already dealt with in elaborate detail by the Arbitral Tribunal and conclusions given, which are upheld by the Ld. Single Judge. The same cannot be interfered with
by this Hon’ble Court under the Section 37 of the Act.
(Reliance is placed on Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India (NHAI), 2019 SCC OnLine SC 677; Associate Builders v
Delhi Development Authority, (2015) 3 SCC 49; Madhya Pradesh Power Generation Company & Anr vs Ansaldo Energia SPA & Anr, (2018) 16 SCC 661; Municipal
Corporation of Delhi vs Jagan Nath Ashok Kumar & Anr, (1987) 4 SCC 497; Sudarshan Trading Co. vs State of Kerela & Anr, (1989) 2 SCC 38)
2. Issue of excepted 1. OGL forms part of the measurements ISSUE NO. 4 (EXCEPTED MATTER) (Ref. Paragraph 164 1. The Tribunal had conspicuously
matter- Whether which falls within the list of excepted to 174 of the Award) observed that in respect initial levels
issue of matters as per Clause 37.6 of the GCC. not only the quantity, but also the
measurements 1. Appellant Employer relied on Clause 37.6 (i.e. signatures of authorised representative
fall within the 2. Single judge merely states that the Measurements) contending the initial levels/OGL’s are of the Respondent on the records
jurisdiction of AT issue is technical and falls within the form of measurements and therefore, is excepted furnished by Petitioner, were in
(Issue 4) domain of arbitrator. matter which is outside the jurisdiction of AT. dispute. Accordingly, Harsha
Construction was distinguishable on
AND 3. Claim No. 6 dealt with total work 2. AT ruled that dispute is in relation to authenticity of facts;
done till the date of termination and records of initial levels/ OGL’s and not measurements.
Claim for total had nothing to do with OGLs. AT observed that the Clause 37.6 being relied by NTPC 2. The Tribunal further drew a
works done relates to measurements and not initial levels and distinction between measurements
(Claim No. 6) 4. Judgment in the case of Madnani therefore, the dispute doesn’t fall within the scope of outside the purview in terms of Clause
Construction cannot be relied was Clause 37.6. AT observed: “..taking initial levels is a 37.6 and initial levels, and held that
peculiar to the facts involved as the preliminary task for measurement and cannot be initial levels did not qualify as excepted
procedure involving excepted matter construed as measurement of quantity as matter. It held that determination of
was not scrupulously followed. contemplated under Clause 37..” initial levels was preliminary task
undertaken prior to commencement of
5. Clause 2.9.0 of Technical 3. The Arbitral Tribunal derives authority from works, the measurement of which
Specifications merely provides detailed Arbitration Clause (i.e. Clause 7 of the GCC), which is qualifies as excepted matter under
procedure for taking measurements, worded in widest manner and gives authority to AT to Clause 37.6;
which is an excepted matter under adjudicate ‘any dispute and difference’ without any
Clause 37.6 of GCC. Thus, Clause 37.6 exceptions. Further Arbitration Clause 7 provides for a 3. The Tribunal (comprising of
was applicable on OGLs. three-tier dispute resolution system, which allows the technical experts) arrived at above
AT to have jurisdiction on all matters which could not findings based on interpretation of
6. Heavy reliance placed upon be resolved by DRB. The instant issue was in fact contractual clauses as well as technical
judgement in the case of Harsha referred to DRB where it could not be resolved. interpretations of initial levels, used in
Constructions. field of construction contracts. These
4. AT ruled that the reliance of Appellant on the case of findings are not open to Court under
Palit & Co | August 28, 2020| Revised Note
7. Respondent Contractor never claimed Harsha Contractors is incorrect since arbitration clause Section 34, and Tribunal is master of
that 15th and 16th RA bill represented in the said case expressly provided for the matters quality and quantity of evidence.
total works done. The AT erred in which shall not be within the AT’s jurisdiction. Reliance was placed upon Madnani
reopening the entire computation. Construction (pp. 65 to 66) and Country
In view of the above, AT ruled that the dispute Club India Limited, 2016 SCC OnLine
8. Claim No. 6 is subject matter of FIR regarding the initial levels falls within the AR’s Bom 8993 (pp. 67);
whereunder the OGLs furnished by jurisdiction to arbitrate.
Respondent Contractor and signature 4. The Tribunal has applied
appended thereto are subject matter of CLAIM NO. 6 (CLAIM FOR TOTAL WORKS DONE) (Ref. Simpson’s formula to quantify the total
investigation by the CBI. Accordingly, Paragraph 204 to 241 of the Award) works done. It is completely a domain
the grant of claim computed on the of the arbitrator. Reliance was placed
basis of such OGLs unjustly enriches the1. AT found the correct provision in the contract for upon McDermott International, (2006)
Respondent Contractor. recording initial levels was Clause 2.9 of Section II Part 11 SCC 181 (SC) (pp. 68 and 69);
B, Detailed Technical Specifications, (2.0.0 Technical
9. The Arbitral Tribunal completely Specification for Excavation and Filling for Site 5. The Tribunal examined facts
overlooked the set of OGLs furnished by Levelling Works) (Extracted in Pg 90, Para 208 of and based on that gave findings on the
Appellant Employer basis frivolous Award). The provision provided that spot levels (i.e. issue of relevant measurements and
ground that Augustine was not initial level & final level) shall be signed jointly by both whether Mr. Augustine was authorised
authorised person. Notably, Augustine contractor and EIC of Appellant. As per Clause 2.9, final representative. The Tribunal has
was part of the survey team and had measurement of the volume of the total excavation undertaken in-depth study of the issue
been deployed at site since the and filling for site levelling works was to be conducted and observed that initial levels were to
beginning. for the purpose of payment for work. be jointly recorded. The examination of
initial records revealed discrepancies as
10. The AT observed that Respondent 2. AT observed that initial levels/OGL’s form the datum records did not bear the signature of
Contractor had excavated 15 lakhs cum for all excavations and therefore in engineering authorised person of the SACIL /
during October 2013 to March 2014. practice all excavation works have to have joint Respondent. The Appellant / Petitioner
Notable that prior to that the signatures of both contractor and EIC to avoid dispute in his letter dated June 15, 2013 also
Respondent Contractor had excavated at a later date, since OGL’s become non-susceptible claimed that initial level records were
46 lakh cum in 18 months. Given the and non-existent physical form after excavation and self-certified without signatures of
resources deployed were poor, the can’t be remeasured (Para 212, Pg 92 of Award). Respondent. This could have been
Respondent Contractor could not have shared initially, and there was
3. Now in the present case, there was no dispute on
excavated any more than 2 lakh cum. requirement to produce them only at a
the final levels reached on the date of termination of
The Single Judge completely ignored the later stage;
contract, however the dispute was with respect to
same.
initial levels. Both parties had produced a different set
6. Calculation was done on the
of OGL’s which they were relying for calculation and
11. If the set of OGLs furnished by basis of time-tested Simpson’s.
disputing the other party’s set of OGL’s. AT examined
Respondent Contractor were recorded Formula. Volume of RRB was deducted
Palit & Co | August 28, 2020| Revised Note
in 2012, why were they furnished only in the OGL records of both parties (Para 212 to 216 Pg from the volume of excavation so
February 2013. 93 to 97 of Award) and concluded that the calculated. The amount which had been
12. Judgment in the case of McDermott Respondent Contractors OGL records were genuine paid to the Respondent against RA Bills
is an authority on use of established and set produced by Appellant cannot be relied upon. 1 to 14 was also deducted and then the
methods wherein damages cannot be AT conclusion was based on the following broad final Award was made;
computed. Its use for justifying use of observations:
Simpsons rule for determination of total The issue is completely beyond the
works done is erroneous. I. NTPC OGL’s signed by unauthorised representative domain of examination under Section
34 of Arbitration and Conciliation Act,
OGL records produced by both parties were signed by
1996, and as such no infirmity can be
Mr Praveen on behalf of Appellant Employer.
found in the award. The Court cannot
However, for the Respondent Contractor, NTPC’s
intervene unless it patently illegal or
records contained signature of one, Mr Augustine who
shocks the conscience of the Court.
was a lower level member of the Respondent’s survey
Reliance placed upon Associate
team, who had no authorisation to sign. On the other
Builders, (2015) 3 SCC 49.
hand, records produced by Respondent was signed by
Mr Prashant Konda Reddy, in whose favour the
Respondent produced authorisation (Pg 98-99, Paras
217 to 219 of Award).
Our Submissions:
Clause 37.6 and 2.9.0 are two separate and distinct clauses. While Clause 37.6 provides for joint measurements on daily basis in Measurements Book, Clause 2.9.0
provides for recording of spot levels only twice, i.e. initial level/OGL (i.e. recorded before start of work) and final levels (i.e. recorded once work is done to finished levels
as per engg. drawings). These initial levels are recorded on the Field Book.
Clause 37.6 is a provision under which volume of daily work is recorded in Measurement Book, basis which RA bills raised and paid. Clause 37.6 is indeed a excepted
matter, so as to avoid disputes in relation to daily volume of calculation, which potentially can lead to unnecessary delays in execution. Whereas Clause 2.9.0 is the
provision under which final payment of total work is calculated based on OGLs/ initial levels (recorded jointly in field book) and final levels to be achieved. Since, the
dispute is in relation to initial levels recordings, which is provided under Clause 2.9 of Section II Part B, Detailed Technical Specifications, (2.0.0 Technical Specification for
Excavation and Filling for Site Levelling Works) and not Clause 37.6 of GCC (Measurements), the same was held to be not an excepted matter and therefore, a subject
matter which could be adjudicated by AT. Further, the arbitration clause is a separate agreement which is crafted in widest manner to include jurisdiction over all
disputes and differences, including dispute pertaining to ‘initial levels/ OGL recordings’, which is not an excepted matter.
Further, the Single Judge also observed that Clause 37.6 was not scrupulously followed (based on statements of NTPC in its Letter dated 15.06.2013- self certification of
records) . Hence, the Single Judge held Madnani Construction to be applicable which held that the procedure laid out under the excepted matter clause is required to be
scrupulously adhered to, in order to take advantage of the same.
Further, the question which is set of OGL records is genuine is a pure question of fact to be determined basis examination of evidence, therefore under the sole domain
Palit & Co | August 28, 2020| Revised Note
of arbitrators. The determination of total works done is a technical exercise, which the Arbitral Tribunal comprising of three senior technical experts undertook based on
the evidence, site records etc. The appraisement and appreciation of the evidence is within the sole domain of arbitrator and cannot be interfered with by court under
Section 34 as correctly held by the Single Judge, far less in Section 37 appeal proceedings.
3 Loss of overheads 1. The Respondent Contractor has not 1. The overheads cost is a time related cost which is 1. Arbitral Tribunal had made a detailed
(Claim-24) led any evidence to prove the loss of incurred independent of the progress achieved. consideration of the overheads.
overheads. (para. ttt at pg. 149) Manner of computation completely
2. Consequential to the delay in execution of project. falls in the domain of Arbitral Tribunal.
2. The AT has adopted 6 per cent. as the
rate for loss of overheads. In toto, the 3. Calculated in following manner: 2. Arbitral Tribunal awarded overheads
AT allowed 16 per cent. toward loss of (i) Compute 6 per cent. of Rs.154 Crores to compute cost relying upon its findings on Issue 1
overheads and loss of profit. As per total overheads cost attributable to said Project; and Issue 2. No legal infirmity.
CPWD guidelines, maximum 15 per cent. (ii) Compute proportionate overheads cost for the
can be allowed towards loss of contract period of 30 months. Deduct proportionate
overheads and profit in building overheads cost for 5 months (representing the period
construction works in plain areas. (para. post termination of contract) from total overheads
www pg. 151) cost.
(iii) Deducting 6 per cent. of the RA bills raised from
3. The overhead costs saved by the aforesaid value.
Respondent Contractor by delaying
mobilisation till December 2012 were
not reckoned. (para. yyy at pg. 152)
Our Submissions:
The cost of overheads (indirect cost) continuously borne by a contractor. The contractor whilst bidding for the project attributes certain part of the overhead cost in the
contract value. When a contract is wrongfully terminated by the employer, the contractor should be entitled to recover the overhead cost proportionate the period
during which contract subsisted, provided the same could not be recovered in the RA bills.
This overheads cost is generally expressed as specified percentage points of contract value, say 6 per cent. The Arbitral Tribunal comprised of 3 arbitrators who were
experts in the field, which had unanimously adopted rate of 6 per cent. to compute the cost of overheads. The manner of computation is a technical issue which falls
completely within the domain of AT.
VII. SUBMISSIONS FOR RELEASE OF DEPOSITED SUM VIS A VIS NTPC’s CONTENTION OF PENDENCY OF CRIMINAL PROCEEDINGS UNDER CBI FIR DATED AUGUST 27, 2017
1. Order dated 26.10.2017 in OMP(COMM) 370 of 2017 i.e. Section 34 Stay on operation of the arbitral award was granted subject to deposit of 50% of the
challenge petition filed by NTPC) awarded amount i.e. 23.77 crores by NTPC with the Registrar General of HC.
Palit & Co | August 28, 2020| Revised Note
2 Order dated 18.04.2018 in OMP (I) (COMM) 75 of 2018 (i.e. Section Ld. Single Judge allowed the release of INR 23.77 Crores to Respondent Contractor subject to
9 petition filed by Sri Avantika/client seeking release of money deposit of bank guarantee.
deposit)
3 Order dated 07.05.2018 in FAO(OS) 94 of 2018 (i.e. Appeal filed by Ld. Division Bench stayed the Order of release of money.
NTPC against the aforesaid order dated 18.04.2018)
4 Order dated 26.03.2019 in FAO(OS) 94 of 2018 Ld. Division Bench disposed of the appeal, considering that the Section 34 challenge petition
was at the stage of final arguments and therefore, directed the continuance of the interim
stay order till the conclusion of the Section 34 petition and further directed that the orders in
relation to release of deposited amount will be passed at the time of final disposal of the said
challenge petition.
SUBMISSIONS
I. Application seeking cognizance of CBI FIR was not pressed and was ‘dismissed as withdrawn’ vide Order dated October, 26 2017 in OMP (COMM) 370 of 2017 [i.e.
Section 34 petition]
Appellant Employer along with the petition had filed an Interlocutory Application (IA No. 11990/ 2017) praying for taking cognizance of FIR dated 27.08.2017 registered
by the CBI, however Appellant Employer did not press the application and sought to withdraw it. Application was directed to be ‘dismissed as withdrawn’ with a liberty
to file afresh if required. The Appellant Employer has never preferred any application seeking cognizance of the FIR subsequently.
II. Ld. Division Bench vide its Order dated March 26, 2019 in FAO (OS) (COMM) 94 of 2018 directed the Section 34 Court to pass orders in relation to release of
deposited sum at time to disposal of Section 34 challenge petition.
Vide Order dated October 26, 2017, Appellant Employer was directed to deposit 50% of Award Money i.e. INR 23, 77 Crores with HC registry.
Respondent Contractor filed Section 9 Arbitration Petition [i.e. OMP (I) (COMM) 75 of 2018) seeking release of the deposited sum which was allowed by the Single
Judge vide Order dated April 18, 2018.
NTPC filed appeal [i.e. FAO (OS) (COMM) 94 of 2018] against the said order before the Ld. Division Bench wherein an interim stay order was passed against the release
of deposited sum vide Order dated May 7, 2018.
Vide Order dated March 26, 2019, considering that the Section 34 challenge petition was at the stage of final arguments, the Ld. Division Bench was pleased to dispose
of the appeal without going into merits of the matter, while directing the continuance of the interim stay order till the conclusion of the Section 34 petition and further
directing the Section 34 court to necessary pass orders in relation to release of deposited amount at the time of final disposal of the Section 34 challenge petition (NTPC
also agrees and admits to this understanding of the Order dated in the Appeal (Pg 50, para xlxii of the Amended Appeal) .
Palit & Co | August 28, 2020| Revised Note
Ld. Single Judge in the Impugned Judgment has not passed the necessary directions in relation to the deposited sum in its Judgment, thus failing to give effect the
directions of the Ld. Division Bench given in the March 3, 2019 Order.
III. FIR was filed merely based on an afterthought as a counterblast to the Arbitral Award, which held Respondent Contractor’s OGL’s to be the genuine set of records
The OGL records relied upon by the Respondent Contractor were available with Appellant Employer since February 2013, when the Respondent shared the same for the
records of Appellant. This is evident from Appellant’s Letter dated 15.06.2013, wherein Appellant raised allegations and disputed the genuineness of Respondent’s set
of OGL records. (Ref: Pg 220 of Award) However, the Respondent neither shared their set of OGL records with Respondent nor initiated any criminal action seeking
enquiry into the allegations, during the duration of contract or the arbitral proceedings. Only when the Arbitral Tribunal in its Award dated 7 th July 2017 after due
consideration of both sets of OGL’s concluded the Respondent’s OGL set to be genuine, the Respondent as an afterthought filed the complaint to CBI alleging collusion
and forgery of OGL records, pursuant to which FIR was registered on August 27, 2017. This action was merely to derail the Arbitral Award where threadbare assessment
of the issue was undertaken.
FIR was registered on August 27, 2017. It’s been 3 years and no charge sheet has been filed. (FIR at Pg No. 1152 of Appeal Documents)
V. Arbitral Tribunal has concluded appellant’s OGL records to be unreliable after conducting a detailed analysis of evidence, which has been upheld by the Single Judge
in the Impugned Judgment