Professional Documents
Culture Documents
1 Chapter 5 a Spoilage, Rework & Scrap
1 Chapter 5 a Spoilage, Rework & Scrap
Spoilage (Defective): are units of production whether fully or partially complete that don’t meet
the standard required by customers for good units and that are discounted or sold for reduced
price. Example: defective shirts, shoes, electronic devices.
Reworks: are units of production that don’t meet the standard required by customers for finished
units that are subsequently repaired and sold as acceptable finished unit.
Scrap (By product): are materials left over when making a product. They have low sale value
compared with the sale value of the main products.
Example: short lengths from wood working operations, frayed cloth etc.
Types of Spoilage
Normal spoilage: is spoilage inherent in a particular production process that arises even under
efficient operating condition. Depending on the production process, management decides the
spoilage it considers normal.
Cost of normal spoilage is typically included as a component of cost of good unit’s manufactured
because good units can be made without also making some units that are spoiled. Normal
spoilage is inventor able costs. The managements are tolerating small amount of spoilage as
normal.
Abnormal spoilage: is spoilage that would not arise under efficient operation condition. It is not
inherent in a particular production process. It arises because of machine breakdown and
operator’s error. Abnormal spoilage is usually avoidable or controllable. Abnormal spoilage cost
is recorded separately and treated as loss of the current year. Costs of abnormal spoilage are not
considered as inventor able costs and are written off as costs of the period in which detection
occurs.
Two Approaches of Treating Normal Spoilage
Approach A: counting spoiled units when computing out put in equivalent units
Approach B: not counting spoiled units when computing output in equivalent unit Approach
A better than approach B because
In approach B, WIP ending is changed for spoilage twice
Approach A high lights cost of normal spoilage, this will help management take action to
minimize normal spoilage
Example 1: Counting and not Counting Spoiled Unit
Chipmakers, incorporation manufactures computer chip for TV set, all direct material is added
at the beginning of the production process. In May 2003, $270,000 direct material was
introduced in to the production process. Production data for may indicate 10,000 units were
started, 5,000 units were completed and 1,000 units were spoiled (all normal spoilage). No
beginning WIP. Ending WIP was 4,000 units, each unit 100% complete as to direct material
cost. Spoilage is detected up on completion of the process.
Requirement: Assign direct material cost to completed units and units in WIP ending using
approach A&B. Solution
Approach A Approach B
1. Costs to account for $270,000 $270,000
2. Equivalent Units
- Completed & T.O ……………... 5,000 5,000
- Ending WIP …………………... 4,000 4,000
- Normal Spoilage ……………… 1,000 -----
- EU of Work done to date 10,000 9,000
When assigning costs, job costing system generally distinguishes between normal spoilage
attributable to a specific job and normal spoilage common to all jobs.
Normal spoilage attributable to specific job is assigned to that job.
Example 3: In the JK machine shop 5 aircraft parts out of a job a lot of 50 aircraft parts are
spoiled. Costs assigned prior to the inspection point are $2,000 per part. JK calculates these costs
on the basis of it inventory costing assumption WA&FIFO. We do not however emphasize cost
flow assumptions in our presentation here or in subsequent sections. The current disposal price
of the spoiled parts is estimated to be $600 per part. When the spoilage is detected, the spoiled
goods are inventoried at $600per part.
- When normal spoilage occurs because of the specifications of a particular job, that job bears the
cost of the spoilage reduced by the current disposal value of that spoilage
DM-ctrl (spoiled goods at current disposal value): 5*$600…………………3000
WIP-ctrl (specific job):5*$600………………………………………………3000
- Total normal spoilage (5*$2,000per part) 10,000
- Less spoiled goods at current disposal value (5*$600) 3,000
-Net normal spoilage (10,000-3,000) 7,000
-Total cost of 45(50-5) good units (45*$2,000) 90,000
-add net normal spoilage +7,000
Total cost of good units 97,000
Normal spoilage common to all jobs; in some cases, spoilage inherent in production only
confidentially occurs when a specific job is being worked on. The spoilage then is not
attributable and hence is not changed; to the specific job instead it is cosseted as manufacturing
overhead. The journal entry is.
DM ctrl. (Spoiled goods at current disposal value) 5*$600……………………3,000
MOH-ctrl. (Normal spoilage)(10,000-3,000)……………………………………7,000
WIP-ctrl (specific job) 5*$2,000 …………………………………………………..10,000
Abnormal Spoilage: if the spoilage is abnormal, the net loss is highlighted and always charged to
an abnormal loss account. Unlike normal spoilage costs, abnormal spoilage costs are not included
as part of the cost of good units produced the total cost of the 45 (50-5) good units is 90,000
(45units X $2,000
DM ctrl. (Spoiled goods at current disposal value) 5*$600……………………3,000
Loss from.(abnormal spoilage)(10,000-3,000)……………………………………7,000
WIP-ctrl (specific job) 5*$2,000 …………………………………………………..10,000
Even though, for external reporting purposes, abnormal spoilage costs are written off in the
period and are not liked to specific jobs or units, often identify the specific reasons for abnormal
spoilage and where appropriate, link abnormal spoilage with specific jobs or units for cost
management purposes