Professional Documents
Culture Documents
HSE Permit Templates
HSE Permit Templates
Personal Protective Equipment: Hard Hat, Safety Shoes & Reflective Vest is Mandatory and Job Specific PPE’s to be worn as per
requirement.
Name of the Permit Holder: Designation: Signature:
To be filled by the Permit Issuer: (Any specific precautionary measures proposed while carrying out activity)
Comments:
SIGNED: DATE:
Procedure:
1. A separate permit has to be completed for each and every height work activity.
2. Maximum approval period is one day / one shift.
Note: - A copy of this work permit must be posted at the work place adjacent where the work is being conducted.
This completed Hot Work Permit is to be hanging adjacent to the work being conducted and a copy attached to the relevant SWMS.
Project Name: Project's Name Location of Hot Work:
Permit No.: Date & Time:
Task to be Completed:
Heat generating equipment used:
Fire protection equipment required:
Personal protective equipment required:
Prior to issuing this permit, the following questions must be considered and answered:
The precautions ticked below must be fully observed. Yes NA
1. Have all combustible materials been removed from the work area or made safe? (Within 15 metres)
2. Are appropriate fire extinguishers located within 2 metres of ignition source?
3. Is ventilation, Illumination adequate?
4. Will sparks be contained completely; are flash screens available to be used?
5. Have welding machine/gas cylinders been inspected, including for spark arrestors?
6. Is the welding machine earthed directly to the equipment, has supply amperage been checked?
7. Pipe work or other vessels decommissioned and vapours flushed?
8. Trolley is being used for the Gas cylinders?
9. Have all drains, pits and depressions been checked, isolated and sealed?
10. Is the body of the welding machine is connected with earthing?
11. Is the area cordoned off with the Caution Tape & with HOT WORK Signage
12. Is Personal protective equipment available and being used?
List special conditions that must be complied with? (Refer SWMS)
TASK COMPLETED: Works have been completed and area checked for smoking embers.
Note: The work cannot be allowed, if the permit is not signed from Authorised person and is valid for one shift, i.e. 8 hrs. If the work extends beyond the shift,
another permit required to be generated.
To Date: Time:
Have the following been considered: Access and egress, site security, exclusion zones and spotters, noisy works permits from local authority?
Electrical Representative:
Company:
Mechanical Representative:
Company:
Hydraulic Representative:
Company:
Demolition Representative:
Company:
Additional Comments:
TASK COMPLETED:
Note: The work cannot be allowed if the permit is not signed from all authorised representatives, and is valid for one shift (i.e. 8 hours). If the
work extends beyond the shift, another permit is required to be generated.
To Date: Time:
Prior to any penetration work, the following must be considered and signed off:
All Isolations or Disconnections must be completed as per company SWMS.
Yes NA
1. Has a structural and electrical slab scan been completed?
The structural and electrcial slab scan report to be attached to this document.
Contractor involved:
Company:
Contractor to provide evidence that an engineer has signed off on the penetration to proceed.
Contractor involved:
Company:
Electrical Representative:
Company:
Contractor involved:
Company:
6. Has all equipment been tested and tagged, and the Electrical Register been completed?
JLL Authorised Representative:
Additional Comments:
TASK COMPLETED:
Note: The work cannot be allowed if the permit is not signed from all authorised representatives, and is valid for one shift (i.e. 8 hours). If the
work extends beyond the shift, another permit is required to be generated.
THE WHOLE OF THE REMAINING DETAIL OF THIS PERMIT MUST BE 7. USE OF CHEMICAL AGENTS (Details to be completed)
AUTHORISED BEFORE WORK IS TO PROCEED AND ONLY WORK No chemical agents other than those listed below may be taken into the
LISTED MAY BE DONE. confined space:
(a)
3. ISOLATION OF CONFINED SPACE (b)
(a) Pipelines (Water, Steam, Gas etc.) (c)
(b) Mechanical/Electrical drives (d)
(c) Sludges/Deposits/Waste
(d) Harmful materials Signed by Competent Person (sub-contractor)
(e) Electrical services 8. HOT WORK
(f) Warning notices, locks or tags have been Hot work permitted – Yes / No
fixed to means of isolation
If hot work is authorised to be carried out within the confined space, a
Signed by Competent Person (sub-contractor) separate Hot Works Permit is required.
4. ATMOSPHERIC TEST REQUIREMENTS Signed by Competent Person (sub-contractor)
The atmosphere has been tested to ensure no oxygen 9. STANDBY PERSONNEL AND RESCUE ARRANGEMENTS
deficiency or excess and for the following contaminants. (Fill in
details and results of tests) (a) Standby persons are: (identity)
(a) (Oxygen)
(b) ( )
(c) ( ) (b) Rescue and emergency procedures are understood and all
equipment is in place.
(d) ( )
Continuing monitoring of the atmosphere is/is not required
(Delete as appropriate) Signed by Competent Person (sub-contractor)
The conditions are safe for entry under the conditions ticked
below:
(i) With a supplied-air respiratory protective device.
(ii) With an air purifying (non-air-supplied) respiratory
protective device.
(iii) Without a respiratory protective device.
Competent Person Time & Date Signed by Site Management (principal contractor)
Valid Until Time & Date
Reference Material – Subcontractors are advised to obtain a copy of the <LOCAL REGULATION/CODE> regarding ‘Safe Working in a Confined Space’ to assist them in
their risk assessment, developing their procedures (including SWMS) and completing this form.
A. Activity details
B. Permit Validity
To Date: Time:
3. Are the explosives and cartridges selected for use the correct size?
6. Are sockets in the blasted area flushed with air and water, and plugged?
7. Have the bore holes been cleared of all the debris before explosives are inserted?
8. Have all the excessive cartridges been removed from the work spot?
Have all persons involved in the operation come out of the spot after loading and
9.
been counted?
Have the environmental conditions been considered?
10.
(Rain / Sunny / Wind / Thunders / Lightning)
11. Are Electronic Items / Radios, mobile phones & pagers prohibited in the location?
12. Is the danger zone suitably cordoned with flagmen posted at important points?
Has a proper signaling system been established to prevent trespassers entering the
16.
blasting zone, siren or hooter and made available?
17. Are all the drillers provided with Ear Plugs, Helmets, Goggles & Gum Boots?
I have checked the above points & found conditions suitable to undertake the blast.
Signature:
The precautions & safe conditions mentioned above have been verified & blast can be done.
People shall be evacuated from danger zone & warning sirens shall be blown before the blast.
1.
Has the “All clear” siren been blown? If yes, specify the time of the “All clear” siren.
2.
Time:
Signature:
To be filled by the Issuing Authority: (Specific Precautionary Measures proposed while carrying out the activity if Any)
Project's Name
A copy of work permit to be displayed at job location with relevement attachments.
Project Name: Date:
Contractor Name: Trade:
Supervisor's Name: 2nd:
Excavation work details:
Permit Valid from: am/pm
Permit Valid to: am/pm
Nearby loose rocks or any other materials that may roll or fall into excavation.
Spoils, materials, and equipment set back at least 1.5mtr away from edge of excavation.
Does excavation area is barricaded.
Flagman provided to control unauthorised movement in that area.
Does underground utilities are identified and marked.
Protection from overhead utilities such as power lines, pipes etc are in place.
Does area is having any harmful / contamination / combustible exposure.
Oxygen level checked
Safe Work Method Statement (SWMS) is reviewed and available.
Slop / Shoring / Benching / is marked on the drawing and available at work location
Plant and Equipment's inspected & verified for the job and are in good condition.
Does the work involve any of the following? Yes / No - (Use appropriate permits in addition)
Hot Work Work at height Isolation (LOTO) Confined Space
In case of any emergency, call (Phone): __________________________
PERMIT HOLDER - ( Site Eng. / Supervisor)
I have read and fully understand the precautions listed in the SWMS attached to this permit,
PERMIT ISSUER -
I have checked and verified the above and permitting to carry out the work :