You are on page 1of 6

Service delivery

Sewerage

20 Melbourne Water Annual Report 2011–12


Key Achievements
>> Completed the Northern >> Completed the Western >> Developed an alternative
Sewerage Project six Treatment Plant (WTP) wet strategy to building an
months ahead of schedule weather capacity upgrade expensive new sewer
and under budget to reduce and used this during several at Ringwood South to
sewage overflows to Merri rainfall events improve the health of
and Moonee Ponds creeks >> A major upgrade of the Dandenong Creek
>> Completed the Melbourne Eastern Treatment Plant (ETP), >> Completed a Biosolids
Main Sewer Replacement on which will benefit the marine Strategy and identified
time and under budget environment at Boags Rocks commercial/research
>> Met all compliance and increase opportunities proposals for the beneficial
obligations for effluent for recycled water, is on track use of biosolids
discharged from our sewage to be completed by the end
treatment plants of 2012

Disappointments Challenges
>> Failed odour complaints target >> Managing a significant number
of wet weather sewage overflows
>> Delayed completion of new aeration
tanks at ETP (to meet population-based >> Rehabilitating the Eastern Drop Structure
load growth and support ammonia on Hobsons Bay Main Sewer in a ‘live’
reduction) due to substantial defects sewer environment to facilitate the
requiring rectification construction of an air treatment facility
>> Reviewing our Odour and Corrosion
Strategy to account for issues including
the impacts of reduced sewer flows
on odour-causing compounds
>> Ensuring we are positioned to take
advantage of new markets for resources
produced from sewage and biosolids

Melbourne Water Annual Report 2011–12 21


Service delivery

Sewerage

Melbourne Water’s Recycling Schemes

YARRA VALLEY WATER

CITY WEST WATER

HOBSONS BAY
MAIN

Western Treatment Plant


Mordialloc No.2 PS
Mordialloc No.1 PS
Bondi Rd PS Eastern Treatment Plant
SOUTH EAST WATER
Port Phillip Bay

Melbourne Water
Western Port sewerage pipeline
LL
FA
UT

Retail Water Business boundary


O
N
ER

French
ST

Melbourne Water
EA

Island
H

sewerage pump station


UT
SO

Sewerage system outlet


Bass Strait
Phillip Sewer Treatment Plant
Island

Our sewerage system Eastern Treatment Plant Powering the plant


Melbourne Water’s sewerage system A major upgrade of ETP in Melbourne’s The introduction of tertiary treatment at
consists of: south-east is nearing completion. Built in ETP requires additional power at the site to
1975, the plant will be transformed into complement on-site generation from biogas
>> 402 kilometres of sewers one of the most sophisticated large-scale harvesting. A second high-voltage feeder
>> 9 sewage pumping stations sewage treatment facilities in the world. was constructed and commissioned in 2011
to supply this power. The second feeder also
>> ETP at Bangholme and WTP at The project will deliver significant provides an important backup to ensure that
Werribee environmental benefits by improving the critical plant operations can continue if the
quality of the treated effluent discharged supply from one feeder is lost.
>> 9 air treatment facilities.
at Boags Rocks and raising the standard of
Melbourne Water treated a total of recycled water produced at the plant. Treating waste solids and
320,067 million litres of sewage at ETP renewable energy
and WTP in 2011–12. This was similar to Once completed, the plant will treat more
2010–11 flows (325,308 million litres) due than 100 billion litres of wastewater to Suspended solids in raw sewage entering ETP
primarily to ongoing above average rainfall. Class A recycled water standard each are allowed to settle in large tanks to form
year using advanced tertiary treatment a layer of primary sludge in a process called
About 44% of this sewage was treated processes including biological media sedimentation. The sewage then undergoes
at ETP and 56% was treated at WTP. filtration, and disinfection using ozone, secondary treatment involving a biological
ultraviolet light and chlorine. process to break down organic material and
remove nutrients. Waste-activated sludge
The project is being delivered by the is generated from this process.
Eastern Tertiary Alliance – a partnership
between Baulderstone, UGL Infrastructure,
Black & Veatch, KBR and Melbourne Water.
Commissioning will occur in the second
half of 2012, and the project remains on
track to be fully operational by the end
of the year.

22 Melbourne Water Annual Report 2011–12


A major upgrade of ETP
in Melbourne’s south-east
is nearing completion.
Built in 1975, the plant will
be transformed into one
of the most sophisticated
large-scale sewage treatment
facilities in the world.

The primary sludge and the thickened for completion by September 2013. The Renewable energy
waste-activated sludge are pumped to increased costs and time delays are being
eight large tanks (8 million litres each) addressed with the project manager, Lagoon covers are being progressively
called digesters where around 45% of designer and constructor. replaced at WTP to capture more biogas
the solids are converted into biogas for the generation of renewable energy
(predominantly methane). The biogas is Reliability program and to help reduce odour. The 115 East
used on site to generate renewable energy. Lagoon cover reached the end of its service
A targeted reliability program is underway life and was removed in early 2012. This
Increases in Melbourne’s population at ETP. This program identifies repetitive work also included dredging of a significant
have resulted in higher levels of solids failures with mechanical and electrical amount of surface sludge that had
requiring treatment in the digesters and equipment and then undertakes root accumulated under the covers.
a need for increased digestion capacity. cause analysis. The root cause analysis
A primary sludge thickening facility was provides an action plan that reduces Works to replace and double the existing
commissioned in late 2011 which has future breakdowns. This program reduces area covered across the 55 East Lagoon
freed up volume in the digesters equivalent maintenance costs and ensures the plant’s have started with two segments of the
to an additional two digesters. ongoing reliability. new cover installed. The new cover will
be four times the size of the MCG and
Aeration tank works Western Treatment Plant is expected to be completed in 2013. It
forms part of an overall plan to increase
A contract was awarded for the construction Wet weather capacity upgrade biogas capture and production of
of four additional aeration tanks in February renewable energy at the plant.
2007 to support the successful conversion Major sewage channel duplication work
of existing aeration tanks to an ammonia to accommodate increases in peak sewage These works will enable the plant to be
reduction process, and provide for ongoing flows following significant rainfall events nearly self-sufficient in its power needs
population-based load growth to ETP. was completed at WTP in late 2011. and to export any excess electricity to
other Melbourne Water sites, reducing
A number of defects relating to the The increased sewage inflow capacity system-wide power costs and greenhouse
construction of the concrete aeration has been used on several occasions since gas emissions.
tanks are now evident. The rectification completion, with peak flows reaching
of these defects has caused delays to the 1,773 million litres a day.
project. Construction of the four additional
aeration tanks was due to be completed by The wet weather treatment capacity has
January 2009. The project is now scheduled increased to 2,500 million litres a day.

Melbourne Water Annual Report 2011–12 23


Service delivery

Sewerage

Recycled water pump station Delivered jointly by Melbourne Water Large pump assessments
and pipeline (Stage one) and Yarra Valley Water (Stage
two), the new sewers provide additional Melbourne Water relies on large pumps
Construction of a new recycled water capacity for Melbourne’s fast-growing to successfully transfer sewage and water
pump station and pipeline was completed northern suburbs including Epping around its extensive distribution network.
in 2012. The project improves reliability and Craigieburn and will protect the
in the delivery of both Class A and Class C Due to the critical nature of sewerage
downstream health of the Yarra River system pumps at Hoppers Crossing,
recycled water to customers. and Port Phillip Bay from sewer overflows Brooklyn and ETP, and water pumps at
following rainfall events. Yering Gorge, a condition assessment
Transfer system strategy was implemented to maximise
The 8 kilometre long deep-tunnelled sewer
Sewerage transfer capacity has been on Stage one connects into the existing the life of the assets.
improved by the recently completed sewerage system near the Merri Creek at It was concluded these assets are robust
Melbourne Main Sewer Replacement and Coburg and the Moonee Ponds Creek in and can have an extremely long operational
the Northern Sewerage Project which will Pascoe Vale. life with minimal changes to existing
help reduce sewage spills into waterways
The 4.5 kilometre long, deep-tunnelled maintenance regimes. Nominal operating
during wet weather.
sewer on Stage two runs from Carr Street, life of the pumps, based on empirical
Melbourne Main Sewer Replacement Coburg North to L.E. Cotchin Reserve in evidence drawn from analysis of other
Reservoir, receiving sewage flows from the similar large assets, was 100 years.
The replacement of a section of a century- existing sewerage system in Fawkner. A $5.5M capital investment is expected
old sewer main from Port Melbourne to to be required to address renewals over
Docklands was completed in June 2012, Ringwood Sewer Strategy to a period of 10 years across all four sites.
on time and under budget. improve Dandenong Creek
Managing corrosion and odour
Marking the culmination of four years of An alternative strategy is being
tunnelling and construction, the new sewer implemented for the Ringwood South Melbourne Water received 14 odour
main replaces a 2.3 kilometre section of Sewer site at Dandenong Creek to provide complaints related to the sewerage transfer
Melbourne’s original brick-lined sewer built a more cost-effective approach for system this year. This was two less than in
in the 1890s. The new Melbourne Main improving the local environment and to 2010–11, but more than our target of 10.
Sewer will triple sewerage capacity and cater avoid building an expensive new sewer. These odour complaints were due to a
for inner-city growth for the next century.
Given that a new sewer would cost an range of reasons, predominantly manhole
A 100-metre long boring machine was estimated $100M, other options to covers being dislodged by traffic or
used to construct the tunnel under the improve the overall health of Dandenong grass cutting activities as well as normal
CBD and build the new main up to 12 metres Creek were examined. discharge of sewer gases from vent stacks
underground. A major component of the or ventilation associated with works being
project was a 140 metre pipeline under the An ecological health study conducted in undertaken in the sewer network.
Yarra River that took specialist divers and consultation with EPA Victoria, South East
Water and Yarra Valley Water revealed wet An enhanced proactive maintenance
engineers two years to build.
weather sewage overflows did not have a program and implementation of
An additional 1.9 kilometres of smaller significant impact on the creek’s health but improvement actions from our Odour
branch and reticulation sewers were also other sources of pollution, such as runoff and Corrosion Strategy will reduce the
constructed, connecting Port Melbourne from industrial areas, did have an impact. likelihood of future odour complaints.
residents into the new system. These pollutants will be the focus of a Works to address sewer corrosion and
program to improve the health odour from the Eastern Drop Structure
Northern Sewerage Project of the waterway. (EDS) manhole on the Hobsons Bay Main
The Northern Sewerage Project was Several environmental improvements were Sewer are continuing. The EDS allows
completed in November 2011, six months also identified to offset any impacts on the sewage from the city fringe and bayside
ahead of schedule and under budget. creek of further overflows from the sewer areas to drop down and flow beneath the
system during high rainfall events. Yarra River. The EDS handles about 175
The project involved the construction of million litres of sewage a day and is the
12.5 kilometres of new sewer tunnels in Up to $12M has been set aside for capital main crossing point for sewage on the way
Melbourne’s densely-populated northern works to deliver pollution abatement and to WTP.
suburbs. Commencing in August 2007, amenity and ecology improvements for
works took place 24 hours a day, six days Dandenong Creek as part of the first stage To address odour complaints from
per week. of the strategy. neighbouring development, the ventilation
fan used to extract foul air from the EDS
The project has been formalised in was turned off for 12 hours a day in 2002.
a Memorandum of Understanding This reduction in ventilation resulted in
between EPA Victoria and Melbourne significant corrosion impacts within the
Water and will result in a better financial drop structure.
and environmental outcome than the
traditional ‘big sewer’ approach.

24 Melbourne Water Annual Report 2011–12


The replacement of a
section of a century-old
sewer main from Port
Melbourne to Docklands
was completed in June
2012, on time and
under budget.

From 2007, projects have been Two private sector proponents have been Sewer mining
progressively implemented to rehabilitate identified as potential beneficial users
the EDS. These works, on a live sewer, of biosolids from ETP. These proponents In 2009, the Melbourne Metropolitan
are very challenging and have to be will commence feasibility studies in Sewerage Review identified the need for
undertaken in stages to ensure they are early 2012–13. Melbourne Water aims to a modelling tool capable of analysing the
completed safely. achieve annual beneficial use of 28,000 dry system-wide effects (energy consumption,
tonnes of biosolids (approximately 100% greenhouse gas emissions, nutrient and
About $8M has been spent on restoring of ETP annual production) by 2018. water flows) of sewer mining and localised
the EDS to date. Works are nearing sewage treatment.
completion to remove corroded elements, The strategy also recommends continued
install an overflow weir to reduce the research into the impacts of stockpiling at Since 2009, Melbourne Water has updated
release of corrosive gases, and fit an access WTP and continued support for emerging its hydraulic model to include recent urban
platform for penstock maintenance. Other biosolids beneficial use technologies. growth and sewage quality analysis.
planned works include provision of an Air During 2011–12, these initiatives were
Treatment Facility at an estimated cost of Biosolids reuse target
consolidated into the Strategic Sewerage
$20M, followed by rehabilitation of other Melbourne Water has a target to reuse Assessment Tool. This tool will be used to
civil structures within the EDS, costing 90,000 tonnes of ‘clay rich’ biosolids from support the development of integrated
about $3M. ETP by 2013. Due to the clay composition water cycle strategies in Melbourne.
of these biosolids, they are particularly
Managing biosolids suited for use as a structural fill material.
Melbourne Water updated its Biosolids Although there was no reuse of these
Strategy in 2011–12. The strategy biosolids in 2011–12, Melbourne Water
recommends identifying beneficial uses is continuing to work with Victorian
for biosolids from ETP given the significant Government agencies and private sector
impacts of continued stockpiling at that site. construction companies to identify
opportunities for the use of this material.

Melbourne Water Annual Report 2011–12 25

You might also like