FW FORMWORK
FW01 Formwork to footings 2 CARPENTERS, 1 HELPER 1.2 12
FW06 Formwork to high level tie beams D>0.45M 2 CARPENTERS, 1 HELPER 1.2 12
FW19 Formwork to slab decking (>10ft) hourdi D/S beams 2 CARPENTERS, 1 HELPER 1.2 12
D DEPTH
U. GR. UNDERGROUND
D/S DECK - SLAB Page 1 of 9
> GREATER THAN
< LESS THAN
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
Page 2 of 9
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
M MASONARY WORKS
MBW 01 Hollow Blockwork (100, 150 & 200 mm) 1 MASON, 1 HELPER 12 Nos 120 NR
MBW 02 Hollow Blockwork (large panels) 1 MASON, 1 HELPER 14 Nos. 140 NR
MBW 03 Solid blockwork 1 MASON, 1 HELPER 9,5 95 NR
MBW 04 Solid Blockwork as Raft forms 1 MASON, 1 HELPER 11 110 NR
MPL PLASTER WORKS 1.2
MPL 01 Plaster (internal), walls final coat 1 MASON, 1 HELPER 1.6 16 SM
MPL 02 Plaster (internal), walls rush coat 2 HELPER 1.4 150 SM
MPL 03 Plaster (internal), walls mesh 1 HELPER 1.8 100 SM
MPL 04 Plaster (internal), walls hacking 1 HELPER 1 100 SM
MPL 05 Plaster (internal), walls guide point 1 MASON, 1 HELPER 1.2 100 SM
MPL 06 Plaster (internal), walls corner beads 1 MASON, 1 HELPER 10 SM 100 SM
MPL 07 Plaster (external), walls with grooves 1 MASON, 1 HELPER 10 SM 10 SM
MPL 08 Plaster (external), walls without grooves 1 MASON, 1 HELPER 1,2 12 SM
MPL 09 Plaster (external), walls rush coat 2 HELPER 15 SM 150 SM
MPL 10 Plaster (external), walls mesh 1 HELPER 10 SM 100 SM
MPL 11 Plaster (external), walls hacking 1 HELPER 10 SM 100 SM
MPL 12 Plaster (external), walls guide points 1 MASON, 1 HELPER 10 SM 100 SM
MPL 13 Plaster (external), walls corner beads 1 MASON, 1 HELPER 10 SM 100 SM
MPL 14 Plastering of Arches/Mullians 1 MASON, 1 HELPER 0.8 80
MPL 15 Floor screed 50mm thick 1 MASON, 1 HELPER 2 20
MPL 16 Roof screed 100 mm thick 1 MASON, 1 HELPER 1.5 15
MPL 17 Mosiac floor Tiles fixing 1 MASON, 1 HELPER 1.6 1.5
MPL 18 Floor Screed 25mm thick 1 Mason + 1 Helper 0,6 6
MCR CERAMIC WORKS
MCR 01 Ceramic tiles to walls by mortar 1 MASON, 1 HELPER 1.2 8 SM
MCR 02 Ceramic tiles to walls, mortar to corridors 1 MASON, 1 HELPER 1 9 SM
MCR 03 Ceramic tiles to walls, cut pieces 1 MASON 2 20 SM
MCR 04 Ceramic tiles to walls grouting 1 HELPER 5 50 SM
MCR 05 Ceramic tiles to walls, by glue 1 MASON, 1 HELPER 1,2 12 SM
MCR 06 Ceramic tiles to walls, corridors, by glue 1 MASON, 1 HELPER 1,3 13 SM
MCR 07 Ceramic tiles to walls, by glue, cut pieces 1 MASON 2 20 SM
MCR 08 Ceramic tiles to walls, by glue, grouting 1HELPER 5 50 SM
MCR 09 Ceramic tiles to floors 1 MASON, 1 HELPER 1 10 SM
MCR 10 Ceramic tiles to floors in halls 1 MASON, 1 HELPER 1,2 12 SM
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60
Page 3 of 9
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
MKP01 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 METRE
Page 4 0f 9
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
MLW11 Hourdi block shifting and fixing to slab 2 HELPER 20 200 NOS
Page 5 0f 9
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
CPW04 Concrete to slabs / beams by crane 1 MASON, 6 HELPERS, 0.5 OPERATOR 8,10 27 CM
CPW12 Concrete footings & pile caps 1 MASON + 4 HELPER 12.00 120
GLW02 Loading reinforcement to slab (With Crane) 4 HELPERS (Flat Bed Truck loads) 40 Nos. 2 Nos
GLW03 Loading blockwork to site (with Wheel Burrow) 1 HELPER 400 Nos.
GLW06 Site mixing of ready mix for distribution Hand mix 3M3
Page 6 of 9
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
Page 7 of 9
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
RF REINFORCEMENT
RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 25 250
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 20 200
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 38 380
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 35 350 > 16M
RFC 01 Steel cutting and bending 18.25 mm 1 STEEL FIXER 50.00 500
EX EXCAVATION
EX 1 Manual Excavation 1 HELPER 3M3
EX 2 Backfill + levelling 1HELPER 5 M3
EX 3 Shaping of sloped earth for blinding for bases including compaction 1 MASON + 2 HELPER 6 LM/Day
Page 8 of 9
PRODUCTIVITY RATES FOR ALL PROJECT WORKS
Productivity Rates for Tilling
Page 9 of 9