Palakkad Block Panchayath 2012-13 Improvements
Name of Work:
to Alikkapparambu Road in Keralassery Grama Panchayath
Detailed Estimate
Sl Breadt Depth/
Particulars No Length Quantity Rate Amount
No h Height
Collection and supply of
60/36mm graded metal (7:3) in
1 standard heaps for
measurement including all
charges etc complete
For patch 10 1203
Say 10m3@ Rs 1203/1m3 12030
Collection and supply of 36mm
metal in standard heaps for
2
measurement including all
charges etc complete
1 110.00 3.00 0.10 33.00 1311
Say 33m @ Rs 1311/1m
3 3
43263
Collection and supply of good
gravelly red earth for blinding
3 in standard heaps for
measurement including all
charges etc complete
1 10/0.1 0.02 2.00
1 110 3.00 0.015 4.95
6.95 447
Say 7m @ Rs 447/1m
3 3
3129
Supplying and filling quarry
4 rubbish including all charges
etc complete
1 100.00 0.50 0.30 15.00 1130
Say 15m3@ Rs 1130/1m3 16950
Metalling the road way 100mm
spread thickness and
5 compacted to 75mm as per
specification by using Dept.
graded metal
100.00 841
Say 100m @ Rs 841/10m
2 2
8410
Metalling the road way 100mm
spread thickness and
6 compacted to 75mm as per
specification by using Dept.
36mm metal
1 110.00 3.00 330.00 841
Say 330m @ Rs 841/10m
2 2
27753
Collection and supply of 12mm
broken stone in standard heaps
7
for measurement including all
charges etc complete
1 110.00 3.00 0.027 8.91 1815
Say 9m3@ Rs 1815/1m3 16335
Collection and supply of 6mm
broken stone in standard heaps
8
for measurement including all
charges etc complete
1 110.00 3.00 0.009 2.97 1474
Say 3m @ Rs 1474/1m
3 3
4422
Providing 20mm premixed
9 chipping carpet over WBM
surface including all charges
1 110.00 3.00 330.00 19991
Say 330m2@Rs19991/100m2 65970
10 Cement concrete 1:4:8
10 Unfore seen items if any 101738
Total 300000
(Rupees Three Lakhs only)