Construction of Greenfield Port at Mulapeta on EPC Basis
PROGRAM VS PROGRESS CONSTRUCTION ACTIVITIES
PROJECT : Construction of Greenfield Port at Mulapeta on EPC Basis DURATION: 900.00 FINISH:
Client : Andhra Pradesh Maritime Board (APMB)
Dec'23
UID BOQ ITEM DESCRIPTION UM RATE EXPECTED SCOPE
PLANNED Amount
BOQ Ref. Approximate
Group 1 Schedule-1 Breakwaters & Shore Protection
2 3&4 Casting of Indopods (for SBW&NBW)
2.1 3.24-3.36 Casting of 4 Cum Indopod No's 25,905.19 31,437.00 4,832.00 125,173,855.62
2.2 3.24-3.36 Casting of 6 Cum Indopod No's 38,857.78 21,183.00 1,958.00 76,083,529.38
Southern Breakwaters Construction (2.470
3 3 KMs) -
3.1-3.10&
3.1 Filter layer 303,358,718.09
3.11-3.19
MT 1,040.84 1,483,094.00 291,457.00
3.2 " Core (0-500Kg) -
Northern Breakwaters Construction (0.580
4 4 KM) -
4.1 4.1-4.4 Filter layer 54,059,812.29
MT 1,048.12 155,019.00 51,578.00
4.2 " Core (0-500Kg) -
General Cargo Berths (3 No's) & One Coal
Group 3 Schedule-3 Berth (1 No.) -
A Multipurpose Berth Construction (3 Nos.) -
1 A General Cargo Berth (GSB -1) -
Piling
4 1.2-1.14 No's 2,227,141.36 168.00 193.00 429,838,282.92
Total Amount for the Day = 988,514,198.30
Construction of Greenfield Port at Mulapeta on EPC Basis
PROGRAM VS PROGRESS CONSTRUCTION ACTIVITIES
PROJECT : Construction of Greenfield Port at Mulapeta on EPC Basis DURATION: 900.00 FINISH: 10/30/2025 DPR Date:
Client : Andhra Pradesh Maritime Board (APMB)
Dec'23
UID BOQ ITEM DESCRIPTION UM RATE EXPECTED SCOPE
FOR THE DAY FOR THE DAY Cumiulative Amount
PLANNED Amount PROGRESS PROGRESS Quantity PROGRESS Amount
BOQ Ref. Approximate
Group 1 Schedule-1 Breakwaters & Shore Protection
2 3&4 Casting of Indopods (for SBW&NBW)
2.1 3.24-3.36 Casting of 4 Cum Indopod No's 25,905.19 31,437.00 4,832.00 125,173,855.62 131.00 4.00 103,620.74 3,393,579.28
2.2 3.24-3.36 Casting of 6 Cum Indopod No's 38,857.78 21,183.00 1,958.00 76,083,529.38 50.00 19.00 738,297.78 1,942,888.90
Southern Breakwaters Construction (2.470
3 3 KMs) -
3.1-3.10&
3.1 Filter layer 303,358,718.09
3.11-3.19
MT 1,040.84 1,483,094.00 291,457.00 6,009.32 2,058.36 2,142,413.64 6,254,712.06
3.2 " Core (0-500Kg) -
Northern Breakwaters Construction (0.580
4 4 KM) -
4.1 4.1-4.4 Filter layer 54,059,812.29
MT 1,048.12 155,019.00 51,578.00 528.58 98.22 102,946.12 554,014.03
4.2 " Core (0-500Kg) -
General Cargo Berths (3 No's) & One Coal
Group 3 Schedule-3 Berth (1 No.) -
A Multipurpose Berth Construction (3 Nos.) -
1 A General Cargo Berth (GSB -1) -
Piling
4 1.2-1.14 No's 2,227,141.36 168.00 193.00 429,838,282.92 6.00 - 13,362,848.17
Total Amount for the Day = 988,514,198.30 3,087,278.28 25,508,042.44