Professional Documents
Culture Documents
ATTACHMENT "A"
D.O. No. 197
Series of 2016
890.00
DESCRIPTION
Contract Duration:
m.
QUANTITY
UNIT
ITEM NO.
(1)
(2)
(3)
(4)
ESTIMATED
DIRECT COST
(5)
MARK-UPS
IN PERCENT
OCM[1]
PROFIT
(6)
(7)
TOTAL MARK-UP
MOB.\ DEMOB.[2] %
(8)
VALUE
(9)
(10)
PART A
A.1.1.(6)
5.80
mos.
142,888.80
A-1.2(5) :
5.80
mos.
384,907.72
B.5
PROJECT BILLBOARDS/SIGNBOARD
2.00
each
12,455.28
8.00%
8.00%
B.7
5.80
mos
335,798.32
8.00%
8.00%
B.9
MOBILIZATION/DEMOBILIZATION
1.00
ls
203,392.00
0.00%
PART B
8.00%
8.00%
P
P
11,431.10
-
VAT[3]
TOTAL
INDIRECT
COST
TOTAL COST
UNIT COST
(11)
(12)
(13)
(14)
7,716.00 P
19,245.39 P
996.42 P
26,863.87
19,147.10 P
162,035.88
27,937.22
19,245.39
404,153.11
69,681.57
566,188.98
672.59 P
1,669.01 P
14,124.32
7,062.16
18,133.11 P
44,996.97 P
380,795.30
65,654.36
10,169.60 P
10,169.60 P
213,561.60
213,561.60
608,481.22
TOTAL PART B
PART F
BRIDGE CONSTRUCTION
404 (1) a
6700.40
kgs.
303,580.42
12.00%
8.00%
20.00%
60,716.08 P
18,214.83 P
405(1) a3
222.50
cu.m.
1,138,908.21
12.00%
8.00%
20.00%
227,781.64 P
68,334.49 P
78,930.91 P
296,116.13
TOTAL PART F
PART J
174 cd
382,525.71
57.09
1,435,024.88
6,449.55
1,817,550.59
STRUCTURE EXCAVATION
2670.00
cu.m.
612,583.44
12.00%
8.00%
20.00%
122,516.69 P
36,755.01 P
159,271.69 P
771,843.60
289.08
1704(1)
EMBANKMENT
4147.40
cu.m.
987,651.25
12.00%
8.00%
20.00%
197,530.25 P
59,259.07 P
256,789.32 P
1,244,427.37
300.05
GABION
5340.00
cu.m.
12,781,626.42
12.00%
8.00%
20.00%
P 2,556,325.28 P
3,015.89
1714(3)
1717(2)a
FILTER CLOTH
SHEET PILES - STEEL (Slope Protection)
3560.00
6675.00
sq.m.
l.m.
1,728,408.48
19,808,317.82
12.00%
12.00%
8.00%
8.00%
20.00%
20.00%
P 345,681.70 P 103,704.51 P
449,386.20 P 2,177,794.68 P
P 3,961,663.56 P 1,188,499.07 P 5,150,162.63 P 24,958,480.45 P
611.74
3,739.10
TOTAL PART J
P 45,257,395.40
TOTAL
P 48,249,616.18
Forty Eight Million Two Hundred Forty Nine Thousand Six Hundred Sixteen & 18/100 Pesos Only
PREPARED/SUBMITTED BY:
JONATHAN T. BOBITA
ENGINEER II
APPROVED:
CHOPIN P. BACARRA
ENGINEER II
RONALDO O SAPONGEN
ENGINEER II
ERNESTO B. BELMES
ENGINEER II
LORETO B. DACOROON
Assistant District Engineer
(Caretaker)
STRUCTURE COMPONENT
VOLUME
CONCRETE
(CU.M.)
0.5
width=
MARK
SIZE
Main Bars
Stirrups
0.5
10
10
STATION
UNIT
WEIGHT
(Kg/m.)
0.617
0.617
SPACING
0 TO
LENGTH=
890
890
REINFORCEMENT
LENGTH
PER BAR
(m.)
DIMENSION
SHAPE
a
AS
200
b
3,560
350
c
400
3.56
1.64
70
QTY.
INPLACED
QUANTITY
(kgs)
1000.00
4451.00
2,196.52
4,503.88
GRADE 40=
6,700.40
222.5
Total
Length(m.)
SHEET PILES
Width=
0.40
Length=
No. of pcs.=
ITEM NO.
DESCRIPTION:
UNIT:
STRUCTURE
COMPONENT
REVETMENT
ITEM NO.
DESCRIPTION:
UNIT:
STRUCTURE
COMPONENT
1714(3)
FILTER CLOTH
sq.m.
MARK
LENGTH
(m)
WIDTH
(m)
DEPTH
(m)
1st LAYER
890
MARK
LENGTH WIDTH
(m)
(m)
AREA
(sq.m.)
REVETMENT
1ST LAYER
2nd LAYER
3rd LAYER
1704(1)
EMBANKMENT
cu.m.
MARK
LENGTH
(m)
WIDTH
(m)
DEPTH
(m)
1st LAYER
2nd LAYER
3rd LAYER
890
890
890
1
1.6
2
1
1
1
ITEM NO.
QUANTITY:
890
890
890
1.5
1.5
1
1,335.00
1,335.00
890.00
3,560.00
QUANTITY:
2,670.00
QUANTITY:
4,147.40
1714(1)
GABION
3,560.00 DESCRIPTION:
UNIT:
STRUCTURE
COMPONENT
REVETMENT
6,675
2,225
1702(1)a
STRUCTURE EXCAVATION
cu.m.
ITEM NO.
DESCRIPTION:
UNIT:
STRUCTURE
COMPONENT
REVETMENT
3.00
cu.m.
QUANTITY:
NO. OF PCS. NO. OF PCS.
LENGHTWISE CROSSWISE
5,340.00
MARK
LENGTH
(m)
WIDTH
(m)
TOTAL
NO. OF PCS.
1st LAYER
2nd LAYER
890
890
3
2
445
445
3
2
1335
890
3rd LAYER
890
445
445
2670
VOLUME
(cu.m.)
2,670.0
2,670.00
VOLUME
(cu.m.)
943.4
1,424.0
1,780.0
4,147.40
VOLUME
(cu.m.)
2,670.0
1,780.0
890.0
5,340.00
Location
ITEM A.1.1.(6) - Provision of Combined Field Office, Laboratory and Living Quarters Building for the Engineers
Quantity =
5.80
Designation
1. Labor :
Laborer
For the maintenance of the rented Field Office,
Laboratory and Living Quarters
mos.
No. of
Person
No. of Hours
1,392
No. of
Units
Units
Unit Cost
Unit
Quantity
Unit Cost
mos.
5.80
Hourly Rate
P
40.15
15,000.00
8%
5%
Location
ITEM A.1.2
A-1.2(5) :
Operation and Maintenance of 4x4 Pick up Type Service Vehicle for the Engin
Quantity =
5.80
mos.
Designation
1. Labor :
Driver
No. of
Person
No. of Hours
1,392
No. of
Units
Units
5.80
mos.
Unit
Unit Cost
Hourly Rate
P
52.06
Unit Cost
53,869.00
Quantity
3. Materials :
5%
Location
B.5
- PROJECT BILLBOARDS/SIGNBOARD
each
Output/Hour =
2 /day
Unit of Measurement =
Designation
1. Labor :
Construction Foreman
Skilled Laborers
Laborers
Quantity =
Duration =
2.00
1.00
each
/day
No. of
Person
No. of Days
1
1
1
1.00
1.00
1.00
No. of
Units
Units
Unit Cost
Unit
Quantity
Unit Cost
pcs.
bd.ft.
sq.ft
sq.ft
kg.
3
111
32
64
3
Daily Rate
P
P
P
575.60
416.48
321.20
P
P
P
P
P
680.00
37.00
50.00
50.00
65.00
8%
5%
Location
Unit Cost
Total Adjusted Cost
ITEM
B.7
1. Labor :
Part time Practitioner
First Aider
5.80
mons
No. of
Person
No. of Days
1
1
87
174
No. of
Units
Units
Unit Cost
Unit
Unit Cost
Quantity
man-day
man-day
man-day
7.77
2.77
0.25
Daily Rate
P
P
575.60
416.48
P
P
P
19,764.00
19,764.00
19,764.00
8%
5%
Location
ITEM
B.9
- MOBILIZATION/DEMOBILIZATION
ls
Output/Hour =
/hr
Unit of Measurement =
Quantity =
Duration =
1.00
16.00
hr
No. of
Person
No. of Hours
No. of
Units
1.00
1.00
4.00
Designation
Hourly Rate
2. Equipment :
Backhoe
Motorized Road Grader (G710A)
Road Roller
Crawler Crane
Vibro Hammer
One Bagger Concrete Mixer
Bar Cutter
Bar Bender
Plate Compactor
Concrete Vibrator
16
16
16
P
P
P
2,450.00
1,102.00
2,290.00
/day
/l.m.
Unit
3. Materials :
Quantity
Unit Cost
Location
OCM/CP
VAT
Total Item Cost
Unit Cost
Total Adjusted Cost
5%
Quantity =
Duration =
2,670.00
133.50
No. of
Person
No. of Hours
1
3
133.50
133.50
No. of
Units
No. of Hours
2
1
133.50
133.50
cu.m.
Hr.
Hourly Rate
P
P
71.95
40.15
Hourly Rate
P
P
1,420.00
1,537.00
Unit
Quantity
Unit Cost
3. Materials :
20%
Location
VAT
Total Item Cost
Unit Cost
Total Adjusted Cost
ITEM 1704(1)
5%
- EMBANKMENT
Unit of Measurement =
Output/Hour =
cu.m.
50 cu.m./hr
Quantity =
Duration =
Designation
1. Labor :
FOR SPREADING AND COMPACTION
Construction Foreman
Laborers for Compaction
4,147.40 cu.m.
82.95
Hr.
No. of
Person
No. of Hours
1
2
82.95
82.95
No. of
Units
No. of Hours
1
1
1
82.95
82.95
20.74
Unit
Quantity
cu.m.
5,184.25
Hourly Rate
P
P
71.95
40.15
0.25
Hourly Rate
P
P
P
2,173.00
1,846.00
2,450.00
/hr
Unit Cost
3. Materials :
Common Borrow (w/25% Shrinkage Factor)
2,514.25
235.00
20%
5%
Location
Unit Cost
Total Adjusted Cost
Location
Quantity =
Duration =
6,700.40
37.22
No. of
Person
No. of Hours
1
2
8
37.22
37.22
37.22
No. of
Units
No. of Hours
1
1
1
5.58
18.61
18.61
kgs.
Hr.
Hourly Rate
P
P
P
71.95
52.06
40.15
0.15
0.50
0.50
Hourly Rate
P
P
P
1,102.00
219.75
351.50
Unit
Quantity
kgs.
kgs.
7,035.42
140.708
Unit Cost
3. Materials :
P
P
37.00
56.67
20%
5%
Location
Quantity =
Duration =
222.50
158.93
cu.m.
Hr.
No. of
Person
No. of Hours
1
4
8
158.93
158.93
158.93
P
P
P
71.95
52.06
40.15
4
8
159
159
P
P
52.06
40.15
No. of
Units
No. of Hours
1
1
1
158.93
158.93
15.89
Hourly Rate
0.10
Hourly Rate
P
P
P
172.00
121.50
2,450.00
Unit
Quantity
bags.
cu.m.
cu.m.
pc.
bd.ft.
kgs.
kgs.
2,113.75
222.50
111.25
35.60
2,503.13
23.53
173.55
Unit Cost
3. Materials :
Portland Cement
Gravel
Sand
1/2" x 4" x 8" Marine Plywood (4 uses)
2" x 3" x 10' Lumber (4 uses)
Assorted CWN(1kg/100bd.ft of lumber).94
#16 Tie Wire (.78)
P
P
P
P
P
P
P
263.00
572.00
551.00
680.00
37.00
80.00
60.00
Lumber :
/ 4
(uses)
2503.13
142.4 / 4
(uses)
35.60
10012.5
Plywood :
20%
5%
Location
Unit Cost
Total Adjusted Cost
PART I-B
- BANK AND SLOPE PROTECTION WORKS
ITEM 1714(1)
- GABION
cu.m.
2.5 cu.m./hr
Unit of Measurement =
Output/Hour =
Designation
1. Labor :
Quantity =
Duration =
5,340.00 cu.m.
2136.00
No. of
Person
No. of Hours
1
2
8
2,136.00
2,136.00
2,136.00
Construction Foreman
Skilled Laborers
Laborers
hr
Hourly Rate
P
P
P
71.95
52.06
40.15
2.50
P198.91
/day
/l.m.
Unit
Quantity
pc.
cu.m.
2,670.00
5,607.00
Unit Cost
3. Materials :
P
P
2,308.00
991.10
20%
5%
Location
ITEM 1714(3)
- FILTER CLOTH
sq.m.
2.5 sq.m./hr
Unit of Measurement =
Output/Hour =
Designation
1. Labor :
Quantity =
Duration =
3,560.00 sq.m.
1424.00
No. of
Person
No. of Hours
1
2
8
1,424.00
1,424.00
1,424.00
Construction Foreman
Skilled Laborers
Laborers
hr
Hourly Rate
P
P
P
71.95
52.06
40.15
Cargo Truck
1.00
356.00
1,102.00
2.50
P309.11
/day
/l.m.
Unit
Quantity
sq.m.
3,738.00
Unit Cost
3. Materials :
Filter Cloth
Miscellaneous (5% of materials)
160.00
20%
5%
Location
Location
Quantity =
Duration =
6,675.00 l.m.
667.50
hr
Designation
No. of
Person
No. of Hours
Construction Foreman
Skilled Laborers
Laborers
1
2
4
667.50
667.50
667.50
No. of
Units
No. of Hours
1.00
667.50
1,902.00
1.00
1.00
1.00
667.50
166.88
166.88
P
P
P
2,123.00
371.00
45.45
1. Labor :
Hourly Rate
P
P
P
71.95
52.06
40.15
2. Equipment :
0.25
0.25
Hourly Rate
10.00
P
/day
/l.m.
446.58
Unit
Quantity
ln.m.
320,400.00
Unit Cost
3. Materials :
Steel Piles (48Kg./Lm.)
Minor Tools (1% of Materials)
52.00
20%
5%
Location
SUMMARY
ITEM NO.
Provision of Combined
A.1.1.(6)
Field
A.1.1.(6)
A-1.2(5) :
B.5
B.7
B.9
404 (1) a
405(1) a3
1702(1)a
1704(1)
1714(1)
1714(3)
1717(2)a
ITEM NO.
A.1.1.(6)
A.1.1.(6)
A-1.2(5) :
B.5
B.7
B.9
404 (1) a
405(1) a3
1702(1)a
1704(1)
1714(1)
1714(3)
1717(2)a
WORK ITEM
Office,
Laboratory
and Living
Quarters
Building for
Provision
of Combined
Field Office,
Laboratory
and Living Quarters Building for the Engineers
Operation
and Maintenance of 4x4 Pick up Type
(rental Basis)
Service Vehicle for the Engineers
PROJECT BILLBOARDS/SIGNBOARD
OCCUPATIONAL SAFETY AND HEALTH PROGRAM
MOBILIZATION/DEMOBILIZATION
REINFORCING STEEL BARS
STRUCTURAL CONCRETE (Class A)
STRUCTURE EXCAVATION
EMBANKMENT
GABION
FILTER CLOTH
P
P
P
P
P
P
P
P
P
P
268,284.40
873,603.98
590,848.75
11,719,457.70
627,984.00
16,827,408.00
31,218,982.42
(9.83)
31,218,972.59
WORK ITEM
DURATION
UNIT
Provision of Combined Field Office, Laboratory and
Provision of Combined Field Office, Laboratory and
mos.
Operation and Maintenance of 4x4 Pick up Type Se
mos.
PROJECT BILLBOARDS/SIGNBOARD
1.00
each
OCCUPATIONAL SAFETY AND HEALTH PROGRAM
mos
MOBILIZATION/DEMOBILIZATION
ls
REINFORCING STEEL BARS
4.65
kgs.
STRUCTURAL CONCRETE (Class A)
19.87
cu.m.
STRUCTURE EXCAVATION
16.69
cu.m.
EMBANKMENT
10.37
cu.m.
GABION
267.00
cu.m.
FILTER CLOTH
178.00
sq.m.
SHEET PILES - STEEL (Slope Protection)
667.50
l.m.
1165.08
say
1165
say
39
AGG. TAX
qty. of PSH
MATERIALS
the Engineers (rental Basis)
P
87,000.00 P
P
P
11,142.00 P
P
213,253.60 P
days of manpower
hours of manpower
#VALUE!
#VALUE!
19764.00
158112.027045048
LABOR
55,888.80
72,467.52
1,313.28
122,544.72
P
18,510.59
P
179,721.20
P
25,685.40
P
12,628.83
P 1,062,168.72
P
708,112.48
P
224,727.23
###
QUANTITY
5.80
5.80
2.00
5.80
1.00
6,700.40
222.50
2,670.00
4,147.40
5,340.00
3,560.00
6,675.00
days
mos.
12.5
Location
LABOR RATE
71.95 FOREMAN
52.06 SKILLED
40.15 LABORER
Amount
P
55,888.80
55,888.80
174
Amount
Amount
P
87,000.00
5.7
87,000.00
P
P
P
P
P
P
142,888.80
11,431.10
7,716.00
162,035.90
27,937.22
162,035.88
Amount
P
72,467.52
72,467.52
Amount
312,440.20
312,440.20
Amount
P
P
P
P
P
P
384,907.72
19,245.39
404,153.11
69,681.57
404,153.11
Amount
P
P
P
575.60
416.48
321.20
1,313.28
Amount
P
P
1,313.28
Amount
P
P
P
P
P
2,040.00
4,107.00
1,600.00
3,200.00
195.00
11,142.00
P
P
P
P
12,455.28
996.42
672.61
14,124.31
P
P
7,062.16
14,124.32
298323.41
82,471.89
Amount
P
P
50,077.20
72,467.52
122,544.72
Amount
10573.46
3,622.54
Amount
P
P
P
153,566.31
54,746.29
4,941.00
213,253.60
P
P
P
335,798.32
26,863.87
18,133.11
575.6
P
P
P
380,795.30
65,654.36
380,795.30
Amount
Amount
P
P
P
39,200.00
17,632.00
146,560.00
203,392.00
Amount
203,392.00
###
P
P
P
P
P
10,169.60
213,561.60
213,561.60
213,561.60
Amount
P
P
9,605.33
16,080.08
25,685.40
Amount
P
P
P
379,140.00
205,189.50
2,568.54
586,898.04
Amount
P
P
P
612,583.44
122,516.69
14%
5%
197,040.28
80,223.54
###
P
P
P
P
36,755.01
771,855.14
289.08
771,843.60
289.08
178
0
Amount
P
P
5,968.11
6,660.72
12,628.83
Amount
P
P
P
180,246.00
153,122.01
50,805.65
P
P
384,173.66
396,802.50
Amount
590,848.75
590,848.75
P
P
P
P
987,651.25
197,530.25
59,259.07
1,244,440.57
82.948
165.896
248.844
31.1055
P
P
300.05
1,244,427.37
Amount
P
P
P
2,678.30
3,875.81
11,956.49
18,510.59
Amount
P
P
P
6,153.20
4,090.03
6,542.19
P
P
16,785.43
35,296.02
Amount
P
P
260,310.46
7,973.94
268,284.40
P
P
P
P
P
P
303,580.42
60,716.08
18,214.83
382,511.33
57.09
382,525.71
37.22443267
74.44886533
297.7954613
409.4687593 51.18359492
Amount
P
P
P
11,434.91
33,095.29
51,047.86
P
P
33,095.29
51,047.86
158.9285714
635.7142857
1271.428571
2066.071429 258.2589286
635.7142857
1271.428571
1907.142857 238.3928571
496.6517857
179,721.20
Amount
P
P
P
27,335.71
19,309.82
38,937.50
P
P
85,583.04
265,304.23
Amount
P
P
P
P
P
P
P
555,916.25
127,270.00
61,298.75
24,208.00
92,615.63
1,882.35
10,413.00
873,603.98
P
P
P
P
1,138,908.21
227,781.64
68,334.49
1,435,024.34
P
P
6,449.55
1,435,024.88
0.54
Amount
P
P
P
153,685.20
222,400.32
686,083.20
2136
4272
17088
23496
2937
1,062,168.72
Amount
P
P
1,062,168.72
Amount
P
P
6,162,360.00
5,557,097.70
11,719,457.70
P
P
P
P
P
12,781,626.42
2,556,325.28
766,897.59
16,104,849.29
3,015.89
1740
97.16666667
P 16,104,849.29
Amount
P
P
P
102,456.80
148,266.88
457,388.80
667.5
1335
2670
4672.5
584.06
708,112.48
Amount
392,312.00
P
P
392,312.00
1,100,424.48
Amount
P
598,080.00
29,904.00
627,984.00
P
P
P
P
P
P
1,728,408.48
345,681.70
103,704.51
2,177,794.68
611.74
2,177,794.68
1424
2848
11392
15664
Amount
P
P
P
48,026.63
69,500.10
107,200.50
224,727.23
Amount
1,269,585.00
P
P
P
1,417,102.50
61,910.63
7,584.47
P
P
2,756,182.59
2,980,909.82
Amount
P
P
16,660,800.00
166,608.00
16,827,408.00
P
P
P
P
P
19,808,317.82
3,961,663.56
1,188,499.07
24,958,480.45
3,739.10
P 24,958,480.45
EQUIPMENT
P
312,440.20
P
P
P
203,392.00
P
16,785.43
P
85,583.04
P
586,898.04
P
384,173.66
P
P
392,312.00
P
2,756,182.59
P 4,737,766.96
P 38,440,508.32
MARK-UP
P
P
P
P
P
P
P
P
P
P
P
P
P
UNIT COST
P
P
P
P
P
P
P
P
P
P
P
P
27,937.22
69,681.57
7,062.16
65,654.36
213,561.60
57.09
6,449.55
289.08
300.05
3,015.89
611.74
3,739.10
11,431.10
996.42
26,863.87
60,716.08
227,781.64
122,516.69
197,530.25
2,556,325.28
345,681.70
3,961,663.56
7,511,506.59
VAT
P
P
P
P
P
P
P
P
P
P
P
P
P
7,716.00
19,245.39
672.61
18,133.11
10,169.60
18,214.83
68,334.49
36,755.01
59,259.07
766,897.59
103,704.51
1,188,499.07
2,297,601.27
ADJ.COST/ITEM
P
P
P
P
P
P
P
P
P
P
P
P
P
162,035.88
404,153.11
14,124.32
380,795.30
213,561.60
382,525.71
1,435,024.88
771,843.60
1,244,427.37
16,104,849.29
2,177,794.68
24,958,480.45
48,249,616.18
COST/ITEM
P
P
P
P
P
P
P
P
P
P
P
P
P
P
1
2
21
3
0.34
0.84
0.03
0.79
0.44
0.79
2.97
1.60
2.58
33.38
4.51
51.73
100.00
8
12
13
14
TOTAL
162,035.90
404,153.11
14,124.31
380,795.30
213,561.60
382,511.33
1,435,024.34
771,855.14
1,244,440.57
16,104,849.29
2,177,794.68
24,958,480.45
48,249,626.02
48,249,616.18
1
2
3
4
5
6
7
8
9
10
11
12
%
0.00
136.311
DC
9.83
52,789,625.68
0.00
142,888
384,907
12,455
335,798
203,392
303,580
1,138,908
612,583
987,651
12,781,626
1,728,408
19,808,317
38,440,518
DC
142,888.80
384,907.72
12,455.28
335,798.32
203,392.00
303,580.42
1,138,908.21
612,583.44
987,651.25
12,781,626.42
1,728,408.48
19,808,317.82
38,440,518.15
PROGRAM OF WORK
Region
: CAR
Pavement Width
N/A
District
: ABRA
Roadbed Width
N/A
Name of Project
Thickness
N/A
890.00
Revetment
Net Length
Type Structure
Type Substructure
Section
Location
:
: Brgy. Buli, La Paz, Abra
No. of Spans
No. of Piers
:
:
Appropriation
: P
Dimensions
Source of Fund
Station Limits
: GAA 2015
:
:
:
Classification
Starting Date
: By contract
: UPON APPROVAL
ITEM
PART A
A.1.1.(6)
50,000,000.00
0.84
PART B
B.5
B.7
B.9
PART F
MOBILIZATION/DEMOBILIZATION
BRIDGE CONSTRUCTION
0.44
404 (1) a
405(1) a3
PART J
PART I-A
1702(1)a
1704(1)
0.79
2.97
0.03
0.79
1.60
2.58
33.38
1714(3)
1717(2)a
4.51
51.73
FILTER CLOTH
SHEET PILES - STEEL (Slope Protection)
Total 100.00
174
EQUIPMENT
DESCRIPTION
NEEDED
1
1
1
1
Cargo Truck
m.
m.
m.
m.
C. D.
AVAILABLE
1
2
21
3
8
12
13
14
PROGRAM OF WORK
Provision
ESTIMATED COST OF PREPARED WORKS
of
DESCRIPTION
UNIT
QUANTITY
UNIT COST
ITEM COST
Combine
Field
PART A d
FACILITIES
FOR ENGINEER
Office,
Operation
A.1.1.(6) Provision of Combined Field Office, Laboratory and Living Quarters Building for the Enginee
Laborator
and
y and
Maintena
A.1.1.(6)
mos.
5.80
Living
nce
of
P
27,937.22 P
162,035.88
Quarters
4x4 Pick
Building
A-1.2(5) : up
Type
mos.
5.80
P
69,681.57 P
404,153.11
for the
Service
PART B Vehicle
OTHER GENERAL REQUIREMENTS
Engineer
sPROJECT
(rental
for
the
P
7,062.16 P
14,124.32
B.5
BILLBOARDS/SIGNBOARD
each
2.00
Basis)
Engineer
P
65,654.36 P
380,795.30
B.7
OCCUPATIONAL SAFETY AND HEALTH PROGRAM
mos
5.80
s
P
213,561.60 P
213,561.60
B.9
MOBILIZATION/DEMOBILIZATION
ls
1.00
ITEM
PART F
404 (1) a
405(1) a3
PART J
PART I-A
1702(1)a
BRIDGE CONSTRUCTION
REINFORCING STEEL BARS
STRUCTURAL CONCRETE (Class A)
FLOOD CONTROL AND DRAINAGE
EARTHWORK
STRUCTURE EXCAVATION
kgs.
cu.m.
6,700.40
222.50
P
P
57.09
6,449.55
P
P
382,525.71
1,435,024.88
P
P
289.08
300.05
P
P
771,843.60
1,244,427.37
3,015.89
16,104,849.29
P
P
611.74
3,739.10
P
P
2,177,794.68
24,958,480.45
48,249,616.18
cu.m.
2,670.00
1704(1) EMBANKMENT
PART I-B BANK AND SLOPE PROTECTION WORKS
cu.m.
4,147.40
1714(1) GABION
1714(3) FILTER CLOTH
1717(2)a SHEET PILES - STEEL (Slope Protection)
cu.m.
sq.m.
l.m.
5,340.00
3,560.00
6,675.00
DIRECT COST
1. Labor
2. Equipment
P
P
2,483,768.77
4,737,766.96
%
4.97
9.48
3. Materials
4. Project Supervision
31,218,972.59
62.44
38,440,508.32
76.88
1. Mark-up(OCM, Profit)
2. VAT
P
P
7,511,506.59
2,297,601.27
15.02
4.60
3. Quality Control
4. Eng'g & Administrative Overhead
5. Construction Contigency
1,750,000.00
3.50
383.82
0.00
Total Project
Cost (Direct &
Indirect Cost) :
48,249,616.18
8. Soil Exploration
9. Survey and Plan Preparation
10. Aggregate Tax
11. Publication Fee
12. Billboard
11,559,491.68
23.12
50,000,000.00
100.00
50,000,000.00
Page 2 of 2
Prepared :
Checked :
EDWIN T. BRINGAS
Chief, Maintenance Secction
Engineer II
Approved :
LORETO B. DACOROON
Assistant District Engineer
(Caretaker)
162,035.88
404,153.11
14,124.32
4
5
380,795.30
213,561.60
6
7
382,525.71
1,435,024.88
771,843.60
1,244,427.37
10
16,104,849.29
11
24,958,480.45
P 50,000,000.00
SE 1
SEC 2
TOTAL
DIFF
DIFF.
#VALUE!
#VALUE!
DIFF
ABC (ORIGINAL)
P
BIDDED ABC
(48,249,616.18)
Agg.tax
15,251.04
cu.m.
56.50
1.00
57.50 Kms.
1. Labor Cost :
Breaking, Picking, and Stockpiling
Labor Capacity
=
1.50 cu.m./man-day due to multiple handling
No. of Laborers
=
50.00
Total Output / day =
75.00 cu.m.
No. of Days
=
15251.04 cu.m./
75.00
=
Labor
50.00 Lab.
204.00
days
203.35
say
321.20 / day
3,276,240.00
x
=
2. Equipment Cost :
Average Hauling Distance
Loading Time
Unloading Time
Slack Time
Mountainous Unpaved :
Loaded Trip
Unloaded Trip
Mountainous Paved
=
=
=
=
57.50
6
2
6
1.00
kms.
kms.
min.
min.
min.
x
15
1.00
kms.
204.00
x
25
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
4.00
mins.
2.40
mins.
169.50
mins.
113.00
mins.
302.90
mins.
Loaded Trip
Unloaded Trip
56.50
kms.
x
20
56.50
kms.
x
30
min./hr.
No of Days Required
Payloader
Dumptrucks
=
=
Note:
hrs.
302.90
60
mins.
min./hr.
10.00
DT
10.00
cu.m./DT
100.00
15,251.04
x
1.58
96.24
days
1.00
10.00
DT
48.12
96.24
days
days
1.58
trip
10.00
DT
100.00
cu.m.
=
=
TOTAL COST :
UNIT COST :
14,352,694.08
14,352,694.08
15,251.04
13,864.00 /day
10,816.00 /day
x
x
941.10
=
=
P
667,135.68
P 10,409,318.40
P 11,076,454.08
/cu.m.
9.165 - 10.69 cu.m.
A. BOULDERS
Cost at Site
Aggregate Tax
Unit Cost of Boulders (Class A)
SAY
=
=
=
=
941.10
50.00
991.10
991.10
/cu.m.
/cu.m.
/cu.m.
/cu.m.
6,528.00
pcs.
16.10
1
17.1
Kms.
Loading Time
Cap. Of 1 CT (9-10T)
Total Weight of Gabion
10,000.00
6,528.00
Kgs.
Pcs
18.00 kg/pc =
x 1 min.
6
Unloading Time
Slack Time
=
=
=
117,504.00 Kgs.
42
mins.
42.00 mins.
6.00 mins.
Mountainous Unpaved :
Loaded Trip
Unloaded Trip
Mountainous Paved
1.00
kms.
x
15
1.00
kms.
x
25
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
4.00
mins.
2.40
mins.
48.30
mins.
32.20
mins.
176.90
mins.
Loaded Trip
Unloaded Trip
16.10
kms.
x
20
16.10
kms.
x
30
min./hr.
No of Days Required
hrs.
176.90
60
mins.
6,528.00
480.00
176.90
mins./day
mins./trip
Equipment Cost
1 Cargo Trucks
1.00
CT
Labor Cost
6 Laborers
6.00
CT
min./hr.
2.71
trip
18
=
x
10,000.00
trip
4.33
days
9,512.00 /day
4.33
days
41,186.96
321.20 /day
4.33
days
P
P
8,344.78
49,531.74
A. Gabion (2 x 1 x 1 X 3.05mm)
Cost/Pcs. at Source
Unit Cost of Hauling
2,300.00 /pc.
P
49,531.74
6,528.00
7.59 /pc.
=
=
2,307.59 /pc.
2,308.00 /pc.
408.00
pcs.
SOURCE :
16.10
1
17.1
Kms.
Loading Time
Cap. Of 1 CT (9-10T)
Total Weight of Matress
=
=
10,000.00
408.00
Kgs.
Pcs.
25.00 kg/pc =
x 1 min.
6
Unloading Time
Slack Time
10,200.00 Kgs.
42.00 mins.
=
=
42.00 mins.
6.00 mins.
Mountainous Unpaved :
Loaded Trip
Unloaded Trip
Mountainous Paved
1.00
kms.
x
15
1.00
kms.
x
25
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
4.00
mins.
2.40
mins.
48.30
mins.
32.20
mins.
176.90
mins.
Loaded Trip
Unloaded Trip
16.10
kms.
x
20
16.10
kms.
x
30
min./hr.
No of Days Required
hrs.
176.90
60
mins.
408.00
480.00
176.90
mins./day
mins./trip
Equipment Cost
1 Cargo Trucks
1.00
CT
Labor Cost
6 Laborers
6.00
CT
min./hr.
2.71
trip
25
=
x
10000.00
trip
0.38
days
9,512.00 /day
0.38
days
3,614.56
321.20 /day
0.38
days
P
P
732.34
4,346.90
3,700.00 /pc.
4,346.90
408.00
10.65 /pc.
=
=
3,710.65 /pc.
3,711.00 /pc.
6
419.1 sta. of Canan
409
16.1
442.3
405.95
36.35
3.05
16.1
1
56.5 Kms.
2306
=
=
=
=
4.00
40.00
1.00
4.00
DT
320,733.75
x
DT
DT
40.00
cu.m.
10.00
cu.m./DT
2004.59
days
1002.29
2004.59
days
days
=
=
SAY
=
=
=
=
=
313.73
207.62
50.00
571.35
572.00
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
SAY
=
=
=
=
=
313.73
186.86
50.00
550.59
551.00
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
4.00
13,864.00
10,816.00
4.00
/day
/day
x
x
A. GRAVEL
Unit Cost of Hauling
Production Cost
Aggregate Tax
Unit Cost of Coarse Aggregates
B. SAND
Unit Cost of Hauling
Production Cost
Aggregate Tax
Unit Cost of Fine Aggregates
P
P
P
13,895,789.72
86,726,406.00
100,622,195.72
4,769.51
cu.m.
2.50
2.50 Kms.
=
Note:
4,608.22
90% of Materials will be considered as suitable
Materials for Sub-base Coarse
Production Cost :
4,608.22
=
400.00
1 Bulldozer
18,392.00
/
day
x
=
Screening and Stockpiling (includes clearing of waste materials)
Utilizing 1 Payloader with average capacity of
=
4,608.22
No. of Days
=
=
240.00
13864.00
/ day
x
Payloader
1
Screen LS
2
No. of Days Required
11.52
days
11.52
211,886.06
480.00 cu.m./day
19.20
days
19.20
266,201.64
20,000.00
498,087.69
Unloaded Trip
Mountainous Paved
Loaded Trip
Unloaded Trip
=
=
=
=
2.5
3
2
6
2.50
120.10
kms.
min.
min.
min.
kms.
x
25
2.50
kms.
x
35
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
6.00
mins.
4.29
mins.
0.00
mins.
0.00
mins.
21.29
mins.
22.55
trip
4.00
DT
40.00
cu.m.
:
-
kms.
x
30
kms.
x
40
min./hr.
Utilizing 4 Dumptruck
w/ 10 cu.m. cap.
Volume Hauled/Day =
No of Days Required
Equipment Cost
Payloader
Dumptrucks
=
=
=
hrs.
x
21.29
60
mins.
min./hr.
=
4.00
DT
40.00
4,769.51
x
22.55
1.00
4.00
DT
13,864.00
10,816.00
10.00
cu.m./DT
5.29
days
2.64
5.29
days
days
=
=
=
=
=
=
=
64.00
120.10
50.00
234.10
235.00
/day
/day
x
x
P
P
P
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
36,653.83
228,763.87
265,417.70
cu.m.
#REF!
cu.m.
1. Labor Cost :
Breaking, Picking, and Stockpiling
Labor Capacity
=
No. of Laborers
=
Total Output / day =
No. of Days
=
Labor
2.50
2.50 Kms.
#REF!
days
#REF!
say
321.20 / day
#REF!
x
=
2. Equipment Cost :
Average Hauling Distance
Loading Time
Unloading Time
Slack Time
Mountainous Unpaved :
Loaded Trip
Unloaded Trip
Mountainous Paved
Loaded Trip
Unloaded Trip
=
=
=
=
2.50
6
3
6
1.50
kms.
kms.
min.
min.
min.
x
15
1.50
kms.
#REF!
x
25
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
6.00
mins.
3.60
mins.
3.00
mins.
2.00
mins.
29.60
mins.
:
=
=
1.00
kms.
x
20
1.00
kms.
x
30
min./hr.
mins.
Total Cycle Time
No. of Trip per Day
Utilizing 4 Dumptruck
w/ 10 cu.m. cap.
Volume Hauled/Day =
No of Days Required
Payloader
Dumptrucks
=
=
hrs.
60
mins.
min./hr.
10.00
cu.m./DT
#REF!
days
#REF!
days
#REF!
#REF!
days
days
29.60
16.00
trip
4.00
DT
40.00
cu.m.
=
4.00
DT
40.00
#REF!
1.00
4.00
DT
16.00
13,864.00
10,816.00
/day
/day
x
x
#REF!
#REF!
=
=
#REF!
TOTAL COST :
UNIT COST :
=
=
#REF!
#REF!
#REF!
#REF!
cu.m.
A. BOULDERS
Cost Delivered at Project Site
Aggregate Tax
Unit Cost of Boulders (Class A)
SAY
=
=
=
=
#REF!
50.00
#REF!
#REF!
/cu.m.
/cu.m.
/cu.m.
/cu.m.
2,113.75
bags
SOURCE :
Loading Time
Cap. Of 1 CT (9-10T)
16.10
16.1
Kms.
10,000.00
Kgs.
10,000.00
Kgs.
No. of Bags/Cargotruck
=
=
40.00
Kgs./bag
Loading Time: (Employing 6 Laborers)
250.00
bags x 1 min. /bag/man
=
6
Unloading Time
Slack Time
Mountainous Unpaved :
kms.
x
60
Loaded Trip
=
15
kms./hr.
kms.
x
60
Unloaded Trip
=
25
kms./hr.
Mountainous Paved :
16.10
kms.
x
60
Loaded Trip
=
20
kms./hr.
16.10
kms.
x
60
Unloaded Trip
=
30
kms./hr.
250.00
min./hr.
min./hr.
min./hr.
min./hr.
say
250.00
bags
41.67 mins.
=
=
41.67 mins.
6.00 mins.
0.00
mins.
0.00
mins.
48.30
mins.
32.20
mins.
169.83
mins.
No of Days Required
hrs.
169.83
60
mins.
2,113.75
480.00
169.83
mins./day
mins./trip
Equipment Cost
1 Cargo Trucks
1.00
CT
Labor Cost
6 Laborers
6.00
CT
min./hr.
bags
x
trip
250.00
2.83
trip
2.99
days
8,816.00
/day
2.99
days
26,359.84
321.20
/day
0.75
days
P
P
1,440.58
27,800.42
A. CEMENT
Cost/bag at Source
Unit Cost of Hauling
250.00 /bag
P
27,800.42
2,113.75
13.15 /bag
=
=
263.15 /bag
263.00 /bag
409
16.10
16.10 Kms.
SOURCE :
Manila, Philippines
Loading Time
Cap. Of 1 CT (9-10T)
=
10,000.00
Kgs.
Assume Capacity of 1 Laborer can carry 40 kgs. of RSB
Loading Time: (Employing 6 Laborers)
10,000.00 kgs.
x
=
40.00 kgs./man-min x
Unloading Time
Slack Time
Paved :
409.00
kms.
x
Loaded Trip
=
35
409.00
kms.
x
Unloaded Trip
=
55
Mountainous Unpaved :
kms.
x
Loaded Trip
=
15
kms.
x
Unloaded Trip
=
25
Mountainous Paved :
16.10
kms.
x
Loaded Trip
=
20
16.10
kms.
x
Unloaded Trip
=
30
1
6
min.
laborers
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
min./hr.
min./hr.
41.67 mins.
=
=
41.67 mins.
6.00 mins.
701.14
mins.
446.18
mins.
0.00
mins.
0.00
mins.
48.30
mins.
32.20
mins.
1317.16
mins.
No of Days Required
hrs.
1317.16
60
mins.
min./hr.
trip
1.93
days
trip
7,035.42
x
8,816.00
/day
0.48
days
4,253.72
321.20
/day
1.93
days
P
P
3,719.50
7,973.22
1.00
CT
Labor Cost
6 Laborers
6.00
kgs.
0.36
0.36
Equipment Cost
1 Cargo Trucks
kgs.
10,000.00
36.00 /kg
P
7,973.22
7,035.42
1.13 /kg
=
=
37.13 /kg
37.00 /kg
40
pcs.
=
=
=
=
16.10
16.1
Bangued, Abra
16.1
15
15
6
kms.
min.
min.
min.
kms.
Kms.
Paved :
Loaded Trip
Unloaded Trip
=
=
16.10
20
16.10
kms.
x
30
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
48.30
mins.
32.20
mins.
0.00
mins.
0.00
mins.
116.50
mins.
Mountainous Unpaved :
Loaded Trip
Unloaded Trip
=
=
kms.
x
15
kms.
x
25
min./hr.
No of Days Required
hrs.
116.50
trip
60
mins.
40.00
4.12
Equipment Cost
1 Cargo Trucks
1 Chain Block
=
=
1.00
1.00
CT
CB
Labor Cost
6 Laborers
6.00
min./hr.
ln.m.
10.00
pcs.
4.12
trip
0.97
days
say
0.97
days
8,816.00
500.00
/day
/day
x
x
0.97
0.97
days
days
=
=
P
P
8,551.52
485.00
321.20
/day
0.97
days
P
P
1,869.38
10,905.90
2,800.00 /pc
1,600.00 /pc
10,905.90
40.00
272.65 /pc
SAY
=
=
3,072.65 /pc
3,073.00 /pc
SAY
=
=
1,872.65 /pc
1,873.00 /pc
6
419.1 sta. of Canan
409
16.1
417
409
8
16.1
1
25.1 Kms.
2,350.00
40.00
Unloaded Trip
Mountainous Paved
#VALUE!
#VALUE!
cu.m.
31.0
1
32 Kms.
cu.m.
Mudeng gravel pit K0.412+081 1.1 KM. AWAY FROM NATIONAL ROAD
32
kms.
6
min.
3
min.
6
min.
=
=
=
=
6.00
kms.
x
15
6.00
kms.
x
25
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
24.00
mins.
14.40
mins.
78.00
mins.
52.00
mins.
183.40
mins.
Loaded Trip
Unloaded Trip
26.00
kms.
x
20
26.00
kms.
x
30
min./hr.
Utilizing 6 Dumptruck
w/ 10 cu.m. cap.
Volume Hauled/Day =
No of Days Required
Equipment Cost
Payloader
Dumptrucks
Note:
=
=
hrs.
183.40
60
mins.
min./hr.
DT
10.00
=
2.62
trip
6.00
DT
cu.m./DT
60.00
cu.m.
#VALUE!
days
#VALUE!
#VALUE!
days
days
=
6.00
60.00
1.00
6.00
#VALUE!
x
DT
2.62
13,864.00
10,816.00
/day
/day
x
x
#VALUE!
#VALUE!
#VALUE!
A. GRAVEL
Unit Cost of Hauling
Cost at Source
Unit Cost of Coarse Aggregates
SAY
=
=
=
=
#VALUE!
400.00
#VALUE!
#VALUE!
/cu.m.
/cu.m.
/cu.m.
/cu.m.
SAY
=
=
=
=
#VALUE!
350.00
#VALUE!
#VALUE!
/cu.m.
/cu.m.
/cu.m.
/cu.m.
B. SAND
Unit Cost of Hauling
Cost at Source
Unit Cost of Coarse Aggregates
=
=
Volume
=
#REF!
Considering 15% Swell Factor, Total Vol. Req'd.=
cu.m.
#REF!
Volume Required
Cycle Time
Source :
=
=
=
=
31.00
1
32
#REF!
Kms.
cu.m.
Mudeng gravel pit K0.412+081 1.1 KM. AWAY FROM NATIONAL ROAD
Loaded Trip
Unloaded Trip
Mountainous Paved
cu.m.
32
6
3
6
6.00
kms.
min.
min.
min.
kms.
x
15
6.00
kms.
x
25
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
24.00
mins.
14.40
mins.
78.00
mins.
52.00
mins.
183.40
mins.
mins.
Loaded Trip
Unloaded Trip
26.00
kms.
x
20
26.00
kms.
x
30
min./hr.
Utilizing 6 Dumptruck
w/ 10 cu.m. cap.
Volume Hauled/Day =
No of Days Required
Equipment Cost
Payloader
Dumptrucks
=
=
hrs.
183.40
60
mins.
min./hr.
=
6.00
DT
#REF!
x
60.00
1.00
6.00
DT
10.00
cu.m./DT
#REF!
days
#REF!
#REF!
days
days
2.62
13,864.00
10,816.00
/day
/day
x
x
2.62
trip
6.00
DT
60.00
cu.m.
#REF!
#REF!
=
=
#REF!
Note:
=
=
=
=
#REF!
350.00
#REF!
#REF!
/cu.m.
/cu.m.
/cu.m.
/cu.m.
Boulders
Volume
=
#VALUE!
Considering 5% Swell Factor, Total Vol. Req'd.=
cu.m.
#VALUE!
Volume Required
Cycle Time
Source :
=
=
=
=
31.00
1
32
#VALUE!
Kms.
cu.m.
Mudeng gravel pit K0.412+081 1.1 KM. AWAY FROM NATIONAL ROAD
Loaded Trip
Unloaded Trip
Mountainous Paved
cu.m.
32
6
3
6
6.00
kms.
min.
min.
min.
kms.
x
15
6.00
kms.
x
25
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
24.00
mins.
14.40
mins.
78.00
mins.
52.00
mins.
183.40
mins.
Loaded Trip
Unloaded Trip
26.00
kms.
x
20
26.00
kms.
x
30
min./hr.
mins.
Total Cycle Time
No. of Trip per Day
Utilizing 6 Dumptruck
w/ 10 cu.m. cap.
Volume Hauled/Day =
No of Days Required
Equipment Cost
Payloader
Dumptrucks
=
=
hrs.
183.40
60
mins.
6.00
60.00
1.00
6.00
DT
#VALUE!
x
DT
10.00
cu.m./DT
#VALUE!
days
#VALUE!
days
#VALUE!
#VALUE!
days
days
2.62
13,864.00
10,816.00
/day
/day
x
x
SAY
#VALUE!
bags
2.62
trip
6.00
DT
60.00
cu.m.
=
=
#VALUE!
#VALUE!
#VALUE!
A. BOULDERS
Unit Cost of Hauling
Cost at Site
Unit Cost of Boulders (Class A)
Cement
Quantity Required
Note:
min./hr.
=
=
=
=
#VALUE!
500.00
#VALUE!
#VALUE!
/cu.m.
/cu.m.
/cu.m.
/cu.m.
SOURCE :
Loading Time
Cap. Of 1 CT (9-10T)
34.00
1
35
Kms.
10,000.00
Kgs.
10,000.00
Kgs.
No. of Bags/Cargotruck
=
=
40.00 Kgs./bag
Loading Time: (Employing 6 Laborers)
250.00
bags x 1 min. /bag/man
=
6
Unloading Time
Slack Time
Mountainous Unpaved :
6.00
kms.
x
60
Loaded Trip
=
15
kms./hr.
6.00
kms.
x
60
Unloaded Trip
=
25
kms./hr.
Mountainous Paved :
29.00
kms.
x
60
Loaded Trip
=
20
kms./hr.
29.00
kms.
x
60
Unloaded Trip
=
30
kms./hr.
250.00
min./hr.
min./hr.
min./hr.
min./hr.
say
250.00
bags
41.67 mins.
=
=
41.67 mins.
6.00 mins.
24.00
mins.
14.40
mins.
87.00
mins.
58.00
mins.
272.73
mins.
No of Days Required
480.00
272.73
hrs.
272.73
#VALUE!
mins./day
x
mins./trip
Equipment Cost
1 Cargo Trucks
1.00
CT
Labor Cost
6 Laborers
6.00
60
mins.
CT
min./hr.
bags
x
trip
225.00
1.76
#VALUE!
trip
days
8,816.00
/day
#VALUE!
days
#VALUE!
321.20
/day
#VALUE!
days
#VALUE!
#VALUE!
A. CEMENT
Cost/bag at Source
Unit Cost of Hauling
230.00 /bag
#VALUE!
#VALUE!
=
=
=
#VALUE! /bag
#VALUE!
#VALUE!
409
34.00
1
/bag
/bag
TOTAL =
444
SOURCE :
Manila, Philippines
Loading Time
Cap. Of 1 CT (9-10T)
=
9,000.00
Kgs.
Assume Capacity of 1 Laborer can carry 40 kgs. of RSB
Loading Time: (Employing 6 Laborers)
9,000.00 kgs.
x
1
=
40.00 kgs./man-min x
6
Unloading Time
Slack Time
Paved :
409.00
kms.
x
60
Loaded Trip
=
35
kms./hr.
409.00
kms.
x
60
Unloaded Trip
=
55
kms./hr.
Mountainous Unpaved :
6.00
kms.
x
60
Loaded Trip
=
15
kms./hr.
6.00
kms.
x
60
Unloaded Trip
=
25
kms./hr.
Mountainous Paved :
29.00
kms.
x
60
Loaded Trip
=
20
kms./hr.
29.00
kms.
x
60
Unloaded Trip
=
30
kms./hr.
Kms.
min.
laborers
min./hr.
min./hr.
min./hr.
min./hr.
min./hr.
min./hr.
37.50 mins.
=
=
37.50 mins.
6.00 mins.
701.14
mins.
446.18
mins.
24.00
mins.
14.40
mins.
87.00
mins.
58.00
mins.
1411.72
mins.
No of Days Required
hrs.
1411.72
#VALUE!
0.34
trip
Equipment Cost
1 Cargo Trucks
1.00
CT
Labor Cost
6 Laborers
6.00
60
mins.
min./hr.
kgs.
6,000.00
kgs.
0.34
#VALUE!
days
8,816.00
/day
#VALUE!
days
#VALUE!
321.20
/day
#VALUE!
days
#VALUE!
#VALUE!
trip
33.00 /kg
#VALUE!
#VALUE!
=
=
=
#VALUE! /kg
#VALUE!
#VALUE!
/kg
/kg
6,675.00
pcs.
34.00
1
35
Kms.
SOURCE :
Average Hauling Distance
Loading Time
Unloading Time
Slack Time
Bangued, Abra
35
15
15
6
=
=
=
=
kms.
min.
min.
min.
Paved :
Loaded Trip
Unloaded Trip
=
=
29.00
kms.
x
20
29.00
kms.
x
30
60
kms./hr.
60
kms./hr.
min./hr.
60
kms./hr.
60
kms./hr.
min./hr.
min./hr.
87.00
mins.
58.00
mins.
24.00
mins.
14.40
mins.
219.40
mins.
Mountainous Unpaved :
Loaded Trip
Unloaded Trip
6.00
kms.
x
15
6.00
kms.
x
25
min./hr.
No of Days Required
2.19
hrs.
219.40
trip
Equipment Cost
1 Cargo Trucks
1 Chain Block
=
=
1.00
1.00
CT
CB
Labor Cost
6 Laborers
6.00
60
mins.
6,675.00
x
min./hr.
ln.m.
10.00
pcs.
2.19
trip
305.1
days
say
305.00
days
8,816.00
500.00
/day
/day
x
x
305.00
305.00
days
days
=
=
P
P
2,688,880.00
152,500.00
321.20
/day
305.00
days
P
P
587,796.00
3,429,176.00
2,800.00 /pc
1,600.00 /pc
=
513.73 /pc
SAY
=
=
3,313.73 /pc
3,314.00 /pc
SAY
=
=
2,113.73 /pc
2,114.00 /pc
3745.757
P50,000,000.00
P40,000,000.00
P30,000,000.00
P20,000,000.00
P10,000,000.00
P-
FA C IL IT IE S F O R E N G IN E E R
P ro v is io n o f C o m b in e d Fie ld O ffi c e , L a b o r a t o r y a n d L iv in g Q u a r t e r s B u ild in g fo r t h e E n g in e e r s ( re n t a l B
O p e r a t io n a n d M a in t e n a n c e o f 4 x 4 P ic k u p Ty p e S e r v ic e V e h ic le fo r t h e E n g in e e r s
T O TA L P A RT A
O T H E R G E N E RA L R E Q U IR E M E N T S
P R O JE C T B IL L B O A R D S /S IG N B O A R D
O C C U P A T IO N A L S A F E T Y A N D H E A LT H P R O G RA M
M O B IL IZ A T IO N /D E M O B IL IZ A T IO N
T O TA L P A RT B
B R ID G E C O N S T R U C T IO N
R E IN F O RC IN G S T E E L B A R S
S T R U C T U RA L C O N C R E T E ( C la s s A )
T O TA L P A RT F
F LO O D C O N T R O L A N D D RA IN A G E
E A RT H W O R K
S T R U C T U R E E XC A V A T IO N
EM B AN KM EN T
B A N K A N D S LO P E P R O T E C T IO N W O R K S
G A B IO N
F ILT E R C LO T H
S H E E T P IL E S - S T E E L ( S lo p e P ro t e c t io n )
T O TA L P A RT J
T O TA L
P60,000,000.00
PAR
A.1.1.(6)
TA
A-1.2(5)
PAR
: TB.5
B B.7 B.9
PAR
404
TF
405(1)
(1) a PAR
a3
PAR
T
1702(1)a
JT I-A
1704(1)
PAR
1714(1)
T I-B
1714(3)
1717(2)a
m. QUANTITY
UNIT
TOTAL COST
UNIT COST
(3)
(4)
VAT[3] (11)
(14)
SUMMARY OF QUANTITIES
ITEM
DESCRIPTION
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
B.9
MOBILIZATION/DEMOBILIZATION
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
405(1) a3 STRUCTURAL CONCRETE (Class A)
1702(1)a
STRUCTURE EXCAVATION
1704(1)
EMBANKMENT
1714(1)
GABION
1717(2)a
SHEET PILES - STEEL (Slope Protection)
0
0
#REF!
#REF!
DIRECT CO0
1. Labor
0
B.5
PROJECT BILLBOARDS/SIGNBOARD
ITEM
103 (1) a
104 (1) a1
404 (1)
405 (1) a1
506 (1)
SUMMARY OF QUANTITIES
DESCRIPTION
STRUCTURAL EXCAVATION
EMBANKMENT FROM EXCAVATION
REINFORCING STEEL BAR
STRUCTURAL CONCRETE
STONE MASONRY
QUANTITES
#REF!
#REF!
#REF!
#REF!
1.00
#REF!
#REF!
#REF!
222.50
2,670.00
4,147.40
5,340.00
6,675.00
0.00
#REF!
0.00
2,483,768.77
4,737,766.96
UNIT
#REF!
#REF!
#REF!
#REF!
ls
#REF!
#REF!
#REF!
cu.m.
cu.m.
cu.m.
cu.m.
l.m.
0.00
#REF!
0.00
0.00
each
QUANTITES
UNIT
172.24
Cu.m.
156.30
Cu.m.
10,502.08
Kgs
116.60
Cu.m.
242.14
Cu.m.
VOLUME
CONCRETE
(CU.M.)
STRUCTURE COMPONENT
0.5
width=
0.5
19
Thick=
0.2
2033
Thick=
0.2
UNIT
WEIGHT
(Kg/m.)
No. of pcs.=
10
10
0.617
0.617
AS
200
C
B
5,600
400
Transverse
Horizontal
12
12
0.888
0.888
400
400
C
C
5,500
5,500
Horizontal
Transverse
12
12
0.888
0.888
400
400
C
A
5,500
1,000
c
400
d
70
QTY.
INPLACED
QUANTITY
(kgs)
5.60
1.74
382.14
2676.00
1,320.38
2,872.90
5.50
5.50
4,623.909
4,718.00
22,583.17
23,042.71
900
100
100
5.50
2.10
583.64
1,338.50
GRADE 40=
2,850.48
2,496.03
55,165.68
Length=
3.00
VOLUME
CONCRETE
(CU.M.)
width=
0.5
0.5
Thick=
0.2
1664
FOUNDATION
Thick=
0.5
MARK
SIZE
(mm)
STATION
UNIT
WEIGHT
(Kg/m.)
0 TO
LENGTH=
SPACING
SHAPE
0
520
REINFORCEMENT
DIMENSION
a
Main Bars
Stirrups
10
10
0.617
0.617
AS
200
C
B
5,600
400
Transverse
Horizontal
12
12
0.888
0.888
400
400
C
C
5,500
5,500
Horizontal
Transverse
10
16
0.617
1.578
150
300
c
400
d
70
5,500
900
400
260
2,054 cu.m.
TOTAL=
Needed Weepholes
Quantity
SHEET PILES
LENGTH
PER BAR
(m.)
QTY.
INPLACED
QUANTITY
(kgs)
5.60
1.74
371.43
2601.00
1,283.36
2,792.38
5.50
5.50
3,784.727
3,876.00
18,484.61
18,930.38
5.50
3.00
1,323.64
1,734.33
GRADE 40=
130
REVETMENT WALL
Length=
4,013
16
2140
1070 m.
1,338
STRUCTURE COMPONENT
0.5
=
=
Total Length(m.)
Height=
LENGTH
PER BAR
(m.)
DIMENSION
Main Bars
Stirrups
Needed Weepholes
Quantity
0.40
Slant Ht.=
SHAPE
2,381 cu.m.
SHEET PILES
Dept=
SPACING
0
535
REINFORCEMENT
214
TOTAL=
Width=
SIZE
0 TO
LENGTH=
133.75
REVETMENT WALL
Slant Ht.=
MARK
STATION
Total Length(m.)
=
=
1560
780 m.
Length=
0.5
4,491.76
8,210.33 area=
54,192.83
structure excavation=
Width=
0.40
No. of pcs.=
Length=
3.00
3,900
1,300
VOLUME
CONCRETE
(CU.M.)
STRUCTURE COMPONENT
0.5
width=
0.5
227
0.2
1634.4
REVETMENT WALL
Slant Ht.=
Thick=
Thick=
0.2
MARK
SIZE
STATION
UNIT
WEIGHT
(Kg/m.)
0 TO
LENGTH=
SPACING
SHAPE
0
908
REINFORCEMENT
Main Bars
Stirrups
10
10
0.617
0.617
AS
200
C
B
5,600
400
Transverse
Horizontal
12
12
0.888
0.888
400
400
C
C
5,500
5,500
Horizontal
Transverse
12
12
0.888
0.888
400
400
C
A
5,500
1,000
c
400
900
d
70
100
100
363.2
Needed Weepholes
Quantity
SHEET PILES
0.40
No. of pcs.=
Length=
=
=
3632
1816 m.
Total Length(m.)
3.00
6,810
structure excavation=
2,270
UNIT
Kgs.
cu.m.
m
m
454 cum.
LENGTH
PER BAR
(m.)
DIMENSION
2,225 cu.m.
TOTAL=
Width=
714 cum.
Length=
0.5
QTY.
INPLACED
QUANTITY
(kgs)
5.60
1.74
648.57
4541.00
2,240.94
4,875.13
5.50
5.50
3,716.182
3,880.00
18,149.83
18,949.92
5.50
2.10
990.55
2,271.00
GRADE 40=
4,837.82
4,234.96 area=
53,288.61
27.99
14554.8
11.1 10089.696
vol. total
10,089.70
ITEM 404
REINFORCING STEEL BARS
REINFORCING STEEL BARS FOR RETAINING WALL
STATION
Length (m)
b1=.30
STEM
b2=.68
B=2.8
FOOTING
D=.38
Length/Bar Quantity
1.80
101
19.90
6
7.05
106
19.99
39
7.05
75
19.90
58
0.64
273
3.14
53
19.90
14
3.14
47
19.90
14
19.90
2
0.49
56
=
=
3897.10
2254.15
ITEM 404 REINFORCING STEEL BARS (GRADE 40) FOR 2.40 M.X1.8 M. SINGLE RCBC
Station
Length
11
ITEM 404
TOTAL=
Weight(kg/m.)
272.7
TOTAL
Weight(Kgs)
2999.7
780
3779.7
KGS
Length
11
Vol./m.
1.21
Total=
ITEM 405=
CU.M.
Volume(cu.m.)
13.31
14.16
27.47
Length (m)
441+680
442+030
375.00
350.00
442+590
442+941
376.07
351.00
441+000
442+390
Length/Bar Quantity
Bar Dia.
2.61
8.00
1167.67
10.00
10.00
3000.02
3047.61
1875.01
1904.76
2.61
8.00
1171.00
10.00
10.00
3008.59
3056.31
1880.37
1910.19
1489.30
1390.00
2.89
442+030
442+080
53.57
50.00
2.89
11.00
201.00
442+580
442+941
386.79
361.00
2.89
11.00
1445.00
ITEM 404
TOTAL=
12.00
10.00
12.00
10.00
TOTAL
14552.90
10044.56
589.29
580.89
523.49
363.06
4254.67
4176.05
3779.57
2610.03
39,443.51
( GRADE 40 )
39,443.51 KGS
LENGTH (m)
441+680
442+030
350.00
0.3
105
442+590
442+941
351.00
0.3
105.3
1390.00
0.285
396.15
442+030
442+080
50.00
0.285
14.25
0.285
102.885
723.59
442+580
442+941
ITEM 404
###
361.00
TOTAL
KGS
ITEM 405
723.59 CU.M.
REINFORCING STEEL BARS FOR CONC. CURB & GUTTER (DOWEL BAR)
STATION
432+000
432+119
432+121
432+285
432+287
433+159
432+161
432+303
432+305
432+469
432+471
432+899
432+901
433+160
432+000
432+120
432+121
432+286
432+287
433+160
432+161
432+304
432+305
432+470
Length (m)
Length/Bar Quantity
Bar Dia.
119
0.6
198.33
12
119
105.672
164
0.6
273.33
12
164
145.632
872
0.6
1453.33
12
872
774.336
142
0.6
236.67
12
142
126.096
164
0.6
273.33
12
164
145.632
428
0.6
713.33
12
428
380.064
259
0.6
431.67
12
259
229.992
120
0.6
200.00
12
120
106.56
165
0.6
275.00
12
165
146.52
873
0.6
1455.00
12
873
775.224
143
0.6
238.33
12
143
126.984
165
0.6
275.00
12
165
146.52
432+471
432+900
432+901
433+161
432+800
435+115
429
0.6
715.00
12
429
380.952
260
0.6
433.33
12
260
230.88
315
0.6
525.00
12
315
279.72
TOTAL
GRAND TOTAL
GRADE 40
GRADE 60
4,100.78
( GRADE 40 )
=
=
47,441.40
2254.15
ITEM 405
REINFORCED CONCRETE FOR RETAINING WALL
STATION
LENGTH (m)
AREA (Sq.m.)VOLUME(Cu.m.)
b1 = 0.3
STEM
20
2.9988
59.98
20
1.064
21.28
20
0.15
b12 = 0.68
B = 2.80
FOOTING
D = 0.38
PARAPET
WALL
b1 = 0.20
b12 = 0.30
TOTAL
=
VOL. OF Lean Conc. =
84.26
5.60
LENGTH (m)
0+000-1+021
1021
367.56
367.56
367.56
TOTAL
367.56
ITEM 407
CONCRETE SRUCTURE - LEAN CONCRETE
RETAINING WALL :
5.60
cu.m.
GRAND TOTAL =
1.10
17.48
cu.m.
0.10
=
11.88
Remarks
P1
P2
S1
S2
S3
S4
S5
F1
F2
F3
F4
F5
F6
kgs.
kgs.
kgs.
8 M. SINGLE RCBC
Remarks
WINGWALL
BC
NGLE RCBC
Remarks
wingwall
NAL
Remarks
Horizontal Bars
Vertical Bars
Horizontal Bars
Vertical Bars
Horizontal Bars
Vertical Bars
Horizontal Bars
Vertical Bars
Horizontal Bars
Vertical Bars
kgs.
DE 40 )
TEM 405)
Remarks
right lane
Left lane
left lane
right lane
right lane
cu.m.
no. Of ps
500.0032
507.935
1093.94
8
1021
2.61 3403.33
KG/PC
KG/M
501
3.75
0.625 10mm
509
5.33
0.888 12mm
3880.773
1884.532
10 8751.49
10 8882.7
OWEL BAR)
Remarks
Left Side
Left Side
Left Side
Left Side
Left Side
Left Side
Left Side
Right Side
Right Side
Right Side
Right Side
Right Side
Right Side
Right Side
Right Side
kgs.
DE 40 )
kgs.
kgs.
LL
Remarks
see details
see details
see details
cu.m.
cu.m.
E CANAL)
Remarks
see details
see details
cu.m.
cu.m.
cu.m.
ITEM 506
STONE MASONRY
LENGTH (m
STATION
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
HEIGHT
(m)H
2.50
2.00
3.00
2.40
2.00
2.00
2.00
2.50
160.00
250.00
75.00
28.00
140.00
30.00
60.00
356.00
HEIGHT
(m)h
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
Lower
Base=B
B=(H/2)
1.25
1.00
1.50
1.20
1.00
1.00
1.00
1.25
Upper
Base=b
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
Area
1=parapet
0.50m
x0.60m
Area 2
=0.50m.*(Hh)*(B+b)
1.66
1.05
2.40
1.53
1.05
1.05
1.05
1.66
Area3= Base=
(h*B)
0.75
0.60
0.90
0.72
0.60
0.60
0.60
0.75
TOTAL AREA=(Area
1+Area 2+Area 3 (m)
2.41
1.65
3.30
2.25
1.65
1.65
1.65
2.41
386.00
412.50
247.50
63.00
231.00
49.50
99.00
858.85
TOTAL =
say
GRAND TOTAL
(ITEM 506)
###
VOLUME (m)
2,347.35
2,347.00
ITEM 505
GROUTED RIPRAP (Slope Protection)
Area = 1.58 see Plan Details
STATION
0+020 - 0+040
0+300 - 0+400
0+100 - 0+140
0+760 - 0+820
1+060 - 1+080
LENGTH (m)
AREA (m)
1.58
1.58
1.58
1.58
1.58
VOLUME (m)
TOTAL =
say
-
GRAND TOTAL
(ITEM 505)
Cu.m.
REMARKS
embankmnet protection left lane
embankmnet protection left lane
embankmnet protection left lane
embankmnet protection left lane
embankmnet protection left lane
embankmnet protection left lane
embankmnet protection left lane
embankmnet protection right lane
Cu.m.
Cu.m.
REMARKS
Right Side
Right Side
Right Side
Right Side
Right Side
Cu.m.
Cu.m.
ITEM 311
PORTLAND CEMENT CONCRETE PAVEMENT
TABULATION AND COMPUTATION OF QUANTITIES FOR PCCP
STATION TO STATION LENGTH (m)WIDTH (m)
DESCRIPTION
442+390
442+390
442+491
1,390.00
1,390.00
21.00
###
442+580
89.00
###
###
441+811
442+899
442+941
442+941
441+809
442+901
361.00
361.00
6.10
6.10
1,941.00
###
###
###
3.00
3.00
3.00
3.00
3.00
2.00
2.00
TOTAL =
4,170.00
4,170.00
63.00
417.00
417.00
6.30
1,083.00
1,083.00
12.20
12.20
10,593.40
108.30
108.30
1.22
1.22
1,059.34
ITEM 612
TABULATION AND COMPUTATION OF QUANTITIES FOR ITEM 612
STATION TO STATION LENGTH (m)
DESCRIPTION
(sq.m)
###
###
443+019
442+390
2,019.00
1,390.00
###
442+580
89.00
442+941
361.00
###
###
###
###
###
###
###
###
###
###
###
441+080
441+180
441+380
441+540
441+900
442+040
442+260
442+380
442+490
442+941
403.80
=
=
302.85
40.00
60.00
60.00
140.00
260.00
60.00
160.00
60.00
60.00
401.00
881.75
255.30
2 lane(sq.m)
139.00
TOTAL =
0.00
ITEM 612(1)
ITEM 612(2)
2 lane(sq.m)
Sq.m.
Sq.m.
403.80
175.10
302.85
ITEM 603
METAL GUARDRAIL
STATION TO STATION LENGTH (m)
-
DESCRIPTION
L-SIDE
L-SIDE
TOTAL =
LENGTH
PIECE
(ln.m.)
each
0.00
-
ITEM 101
REMOVAL OF EXISTING PCCP 0.23 M. THK
STATION TO STATION LENGTH (m)WIDTH (m)
###
###
439+717.6
439+717.6
417.60
417.60
DESCRIPTION
3.00
2.00
-
1,700.00
TOTAL =
1,083.00
1,083.00
12.20
12.20
10,593.40
###
(sq.m)
6.00
9.00
9.00
21.00
39.00
9.00
24.00
9.00
9.00
120.30
255.30
2,088.00
ITEM 102
STONE MASONRY (EMBANKMENT PROTECTION)
A = ((L X W)
STATION
441+080
441+420
441+680
441+800
441+920
442+110
442+200
442+585
441+240
441+670
441+755
441+828
442+060
442+140
442+260
442+941
V = AxL
2.50
2.00
3.00
2.40
2.00
2.00
2.00
2.50
AREA (m)
VOLUME (m)
0.75
0.60
0.90
0.72
0.60
0.60
0.60
0.75
120.00
150.00
67.50
20.16
84.00
18.00
36.00
267.00
TOTAL =
say
REMARKS
762.66
763.00
Cu.m.
Cu.m.
STATION
441+811
442+899
441+809
442+901
LENGTH (m width
6.10
6.10
AREA (m)
2.00
2.00
REMARKS
12.20
12.20
TOTAL=
24.40
sq.m.
ITEM 103
TABULATION AND COMPUTATION OF QUANTITIES (610mm RCPC and INLET)
STATION
441+051
441+448
REMARKS
additional units
additional units
441+810
442+900
1
1
2
11.88
11.88
23.76
Replacement
Replacement
LENGTH (m)
441680
442030
350.00
0.68
238
442590
442941
351.00
0.68
238.68
TOTAL=
LENGTH=
ITEM 102
ITEM 103
=
=
AREA (m)
SECTION AREA = (0.80 X 0.85 )
763.00 Cu.m.
618.84 Cu.m.
VOLUME (m)
476.68
REMARKS
SEE
SEE
SEE
SEE
SETION
SETION
SETION
SETION
DETAIL
DETAIL
DETAIL
DETAIL
ITEM 500
ITEM 502
=
=
28.00 Ln.m.
4.00 Units
GROUTED RIPRAP
STATION
0+020 - 0+040
0+300 - 0+400
0+100 - 0+140
0+760 - 0+820
1+060 - 1+080
LENGTH (m)
TOTAL =
REMARKS
Right Side
Right Side
Right Side
Right Side
Right Side
VOLUME (m)
-
Cu.m.
REMARKS
REMARKS
INLET)
REMARKS
additional units
additional units
INLET)
Replacement
Replacement
EE
EE
EE
EE
REMARKS
SETION
SETION
SETION
SETION
DETAIL
DETAIL
DETAIL
DETAIL
240
REMARKS
Right Side
Right Side
Right Side
Right Side
Right Side
ITEM 600
CONCRETE CURB AND GUTTER (.065m)
STATION
LENGTH (m)
1,390.00
1,040.00
TOTAL =
2,430.00
LOCATION
Left Side
Right Side
mts.
195
649.50
SUMMARY
COMMON EARTH(C.E.)= 649.50
SOLID ROCK (S.R.) =
0.00
EMBANKMENT=
0.00
Roadway Excavation
196
0.00
1928.50
Roadway Excavation
197
Roadway Excavation
198
Roadway Excavation
199
Roadway Excavation
200
Roadway Excavation
201
Roadway Excavation
202
Roadway Excavation
203
TOTAL VOLUME :
COMMON EARTH =
SOLID ROCK
=
PREPARED BY :
3791.20 CU. M.
65.80 CU. M.
EMMANUEL COLLADO
Engineering aide
CHECKED :
JONATHAN T. BOBITA
ENGINEER II
SUBMITTED:
Roadway Excavation
204
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Roadway Excavation
254.32
452.04
382.8
469.24
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
320
340
360
380
400
420
440
460
480
500
520
540
560
580
600
620
640
660
680
700
720
740
760
780
800
820
840
860
880
900
920
205
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
0
0.00
VOLUME (CU.M.
0.00
Roadway Excavation
940
960
980
1000
1020
1040
1060
1080
1100
1120
1140
1160
1180
1200
1220
1240
1260
1280
1300
1320
1333.1
1353.1
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
206
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Roadway Excavation
207
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
3637
3660
3680
3691
Roadway Excavation
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
208
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Roadway Excavation
209
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Roadway Excavation
210
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Roadway Excavation
211
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Roadway Excavation
212
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Roadway Excavation
213
AND 104
EM 104- Embankment
AREA FILL
VOLUME(m)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Roadway Excavation
214
ITEM 605
TABULATION OF QUANTITIES FOR INFORMATIVE SIGN
QUANTITY
STATION
DESCRIPTION
REMARKS
441+040
441+050
441+060
441+070
441+080
441+140
441+150
441+160
441+170
441+180
441+410
441+420
441+430
441+440
441+450
441+460
441+470
441+640
441+650
441+660
441+670
441+680
441+800
441+810
441+820
441+830
441+840
441+870
441+880
441+890
441+900
441+980
441+990
442+000
442+010
442+020
442+030
442+200
442+210
442+220
442+230
442+240
442+320
442+330
442+340
442+350
442+360
442+370
442+380
442+440
442+450
442+460
442+470
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
LEFT LANE
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
RIGHT LANE
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
442+480
442+540
442+550
442+560
442+570
442+580
442+590
RIGHT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
LEFT LANE
TOTAL=
1
1
1
1
1
1
1
60 pcs
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34