Rooftop Solar Inspection
Form
Inspection Date:_________________
Name of Division______________ Name of Sub-Division:__________________
Connection Type: 1P / 3P Solar Application ID:___________________
National Portal Ref. No:_______________________
Details of Consumer
Particulars Observation
Consumer Number
Name of Consumer
Address of Consumer
MSEDCL Existing Sanction & Connected Load In kW
DTC Code
Solar System Equipment & Capacity Details
Particulars of Inverter & Modules Observation
Solar Grid Tie Inverter Make
PV Inverter Capacity in kW
PV Inveter Serial Number
PV Module Make
No's Module Installed & Capacity of each Module No's ( Wp)
Type of Module DCR/ Non DCR
Modules are approved in ALAMM List
The Solar Roof Top Capacity in DC ( Watt )
Whether AC capacity less than equal to Sanctioned load
SLD
Particulars YES NO Note
Single Line Schematic Diagrams in respect of its system
facility Submited
All Equipment installed as per specifications duly signed by
the licensed electrical contractor/ Solar PV installer
Inverter, Module Mounting structure, AC & DC DB with
Components DC Cable(s) AC Cable(s) Lightning Arrestor
Earthing System
Particulars YES NO Note
Separate Earthing provided ACDB Earthing
Separate Earthing provided For DCDB & Solar Panel
Structure
Separate Earthing provided for LA Earthing
All Metallic body Parts Earthed
Protection Switchgears
Particulars YES NO Note
DC Fuses or MCB Provided in DCDB
Surge Protection Device Installed in both Side ACDB &
DCDB
MCB Provided before AC Load Side in ACDB
Separate Lightning Arrestor installed for system
1. Whether switch has visible for verification
2. Whether switch clearly indicate Open/Close Position
3. Whether switch has facility of locking in openPosition
Islanding is working after disconnect AC Supply
Net Metering System Details
Particulars Observation
Net meter Installed in Grid System at the
time of Joint Inspection
Net Meter is Tested at MSEDCL If (Yes) Testing Date & Seal
No
Meter Make
Meter Serial No
Meter Capacity
Location meter easily assessable for meter reading
Whether Net Meter connection properly found
Generation Meter Details
Particulars Observation
Generation meter Installed in Grid System at the
time of Joint Inspection
Generation Meter is Tested at MSEDCL If Yes Testing Date
& Seal No
Meter Make
Meter Serial No
Meter Capacity
Location meter easily assessable for meter reading
Whether Generation Meter connection properly found
Overall Observation
Particulars YES No Observation
Whether System is working Properly
Islanding of Solar System working Satisfactory
The Above inspected Solar System with
associated equipment & Metering System can be
taken into system (Yes/No)
Any Remarks Discrepancies to be attended by consumer
for to be complied
Is PV Panels are DCR, if Yes
Sr. PV Panel Serial No. Wp Sr. PV Panel Serial No. Wp
No No.
.
1 16
2 17
3 18
4 19
5 20
6 21
7 22
8 23
9 24
10 25
11 26
12 27
13 28
14 29
15 30
Dy. EE/ Add. EE MSEDCL AEQC Consumer Vendor
Verified Verified Verified Verified with Seal