Boq Retail
Boq Retail
Description
General
This Package is based on the latest architectural drawing set as received on 01.10.2023
SBC 100 T/SQM soil parameters is considered as per geotechnical soil report.
1 Earth work
Excavtion is considered in this boq.
Back filling around RW and foundation is considered in this boq.
Retention system is not considered in this boq.
3 RCC
RCC flat slab system is considered for all floors.
Concrete in the slab all around the column for 600 mm width is considered of higher grade same as that of column below.
RCC Raft is considered for Core portion Area and RCC Isolated Footing is considered for remaining Area.
Grade slab of 200 mm thick is considered.
Retaining wall of 300 mm thick is considered.
Ramp beam of 1200mm height is considered.
Ramp slab of 300mm thick is considered.
RCC staircase with 200mm waist slab and landing is considered for entire building.
Fire Sump, RWT, OHT and LMR are considered in this boq as per Arch drawing
RCC columns are considered from Basement to terrace floor.
RCC parapet is considered for 4th,5th,6th floor and Terrace.
No elevation feautures is not considered in this boq.
4 Formwork
System formwork is considered for complete structure.
6 Flooring works
VDF Flooring of 100mm thk screed is considered for parking area.
Serrated finish is considered for ramps.
7 Waterproofing works
HDPE Pressure sensitive, Pre-laid Fully Bonded Membrane waterproofing System is considered for foundation sides and bottom, grade
slab bottom and sub soil well
Crystalline Hydrophilic waterproofing system is considered for Fire Sump, RWT, OHT(Internal face).
Waterproofing Systems using elastomeric polyurethane membrane is considered for Retaining wall.
Dimple sheet is considered for the retaining wall.
Waterproofing by spray applied water based polyurethane built up membrane is considered for podium.
Waterproofing by Spray Applied Advance polyurathane membrane System is considered for terrace areas, refuge teraces.
Water based food grade epoxy resin wall finish is considered for OHT and Fire Sumps.
Waterproofing by cementitious Elastomeric Built up membrane systems is considered for wet areas like toilet, lift pits and
waterproofing for toilet walls is considered for a height of 1m.
Construction joint treatment is considered in this boq
8 Miscellaneous works
Subsoil drainage system is considered in this boq.
External Development Works such as compound wall, entrance portal, Transformer Yard, DG Yard, landscape related works etc., are not
considered in this BOQ.
Quantity for civil works related to services need to be filled by PHE consultants.
INSTRUCTIONS TO TENDER
The Schedule of Rate shall be read with all the other sections of this bidding document including
1 technical specification, preamble, general and special conditions of contract, safety requirements, EHS
norms etc.
The bidder is deemed to have studied the drawings, specifications and the details of work to be done
2
within the time schedule and should have acquainted himself with the conditions prevailing at site.
The OWNER reserves the right to interpolate or extrapolate the rates for any new items of work not
covered in the schedule of price from the similar items already available in the schedule of rates. All
the works shall be measured upon completion and paid for at the rate quoted and accepted in the
3 “Schedule of Price”. In case any activity though specifically not covered in schedule of rates
descriptions but the same is covered under scope of work/scope of supply/specification drawings etc.
no extra claim on this account shall be entertained, since schedule of price is to be read in conjunction
with all other documents forming part of the contract.
4 The Bidder to quote for all items and for all the quantities.
If the Bidder does not quote for any of the items, the highest rate quoted by any other bidder will be
5 applicable for evaluation, but lowest rate quoted by any other bidder shall be considered for payment
in case the job is awarded to the bidder.
All items of work mentioned in the Schedule of Rates shall be carried out as per the specifications,
drawings and instructions of OWNER/Engineer-in-Charge and the rates are deemed to be inclusive of
6 material, consumable, labour, supervision, testing, tools and tackles and detailing of
construction/fabrication drawings, wherever required as called for in the detail specification and
conditions of the Contract.
OWNER reserve the right to cancel/delete/curtail any item or group of work if necessary. Such a step
7
shall not be construed as reason for changing the rates.
8 Amount to be quoted in the nearest Indian Rupees only
The drawings included in the bidding document are for reference and general understanding of the
9 scope of work. Any variation in dimension, levels and details in working drawing shall not be reason by
any means for change in quoted rates.
This is an item rate tender and quantities are tentative. The Contractor's unit rates quoted shall not
10
change for any variation in quantities
11 Contractor to visit the site prior to quoting.
Suitable barigading, warning systems, signages, sand cushing. Multiple handling of materials shall be
12 taken into account in view of restricted area availabe for contruction. Extra claim for cost and time will
be not be accepted on account of failure to take into account the above factors prior to quoting.
Tests on materials shall conform to IS Specification and the test shall be carried out as directed either
13
at site Laboratory or at any approved test laboratory.
Please note that the power required for construction shall be arranged by contractor and shall be
14 included in the rates quoted. Bringing DG, temporary power, power distribution lines etc area all part
of the rates quoted.
The quantities shown against the items are only approximate & may vary to any extent individually. No
15
claim shall be entertained during the currency of this contract towards any items due to the above.
Material shall be of good ,approved ,acceptable quality & purchased from approved source; got
16
approved from engineer in charge prior to usage and meeting all relevant codal norms.
Work shall be carried out as per latest construction drawings, specifications & carried out to the
17
satisfaction of engineer-in-charge.
18 Work will be measured and paid only as shown on the drawing as per applicable clause in IS 1200
Total Amount
Sl.No. Description
Tower Rate/ Sft
CIVIL & STRUCTURAL WORKS
1a General excavation ₹ 1,82,50,000.00 ₹ 57.44
1b Earth Works ₹ 24,42,750.00 ₹ 7.69
NOTE :1. This costing is worked out based on Tender stage structural drawings and hence can vary in design development stages.
Structural Area Statement
Sl.No Description Area
1 Basement-2
2 Basement-1 6239.1
3 Ground Floor 6257.76
4 1st Floor 2579.81
5 2nd Floor 2579.81
6 3rd Floor 2665.2
7 4th Floor 2665.2
8 5th Floor 2665.2
9 6th Floor 1066.08
19 Terrace 2398.68
20 Above Terrace 399.78
General Notes for all Excavation Items: Contractor shall take all required permissions from the appropriate authorities for
Excavation, Blasting, Carting away materials etc. and shall bear all the expenses for the same.
Rate shall include
1. Removal of all kinds of vegetation, small shrubs etc. If there are any shrubs, bushes, roots of the trees to be removed for
min depth 1.5m including all necessary permissions. The necessary approval shall be taken for removal of trees with the
consent of the clients if applicable. The contractor shall be fully responsible for liasoning with local authoritites, compliance
to all the statutory obligations, including all labour lanes in force, facilities, policies etc. towards all employees , labour and
under no circumstance nor any acting party pass on the responsiblitites of the contractor to the other contractor/clients.
2. Contractor shall get acquainted with site conditions, nature of soil and adopt suitable dewatering system as deemed fit for
the nature of soil and prevailing water table and water collected by runoff or rain needs to be disposed off from the site.
The rate shall include keeping the excavated surface dry till completion of the scope of work. Dewatered water/ Slush shall
be drained out by suitable means to places not objected by civic authorities. The contractor shall submit the method
statement for dewatering and the same shall be let out of the building premises through proper pipes & channels as
required.
3. The rate shall include necessary general shoring, strutting with approved timber/steel accessories wherever necessary as
approved by the Engineer-in-charge. Special soil retention systems like contiguous piling, soldier piling, soil nailing &
guniting, diaphargm wall etc., shall be paid separately .
4. Contour level to be taken jointly with the Project Manager and prior written approval be taken before starting any
excavation/ filling at every 3 / 5 mt grids for arriving at the actual quantity using simpsons rule. Cost to include all and
necessary royalty and other permission charges required to execute the works. The rate shall include all necessary setting out
of building, excavation line, barrication by grid/plot marking, survey by Total station, transfer of bench mark, etc., complete
5. The rate shall include all necessary setting out of building, excavation line, barrication by grid/plot marking, survey by
Total station, transfer of bench mark, etc., complete
6.The quoted rates includes seggregating of good quality excavated earth from the clay / silty soil and storing in designted
area for further treatment within the site premises for future landscape purposes including preserving top 300 mm layer of
existing soil to meet MOEF requirements.. No extra is payable towards double handling.
7. Quoted rates shall incldue the preparation of temporary access road and temporary drains, rerouting of existing roads,
supporting systems for existing MEP services if any and re-routing if required, etc. complete.
8. Carting away all types of excavated earth outside or within the site shall be included and environmental norms to be
followed for discarding excavated material with submission of document of proof.
9. Soil shall be classified as three types for billing purpose.
a.Classification under hard rock excavation item which requires chiselling with compressed air/mechanical
equipment's,controlled blasting, chemical splitting, diamond cutting etc. with necessary mechanical equipment's and loose
boulders which requires splitting and handling.
b. Classification under soft/medium/ weathered rock excavation item which is non poclainable, can be excavated using rock
breaker attachments to JCB/Poclain, manual chiselling, etc. and loose boulders removal without spliting etc.
c. Classification under soil excavation which is poclainable, can be excavated using JCB/Poclain etc.
10. Please note that the water and power required for construction shall be arranged by contractor and shall be included in
the rates quoted. Necessary bore wells , bringing water from tankers from outside, DG, temporary power, power distribution
lines etc are all part of the rates quoted.
11. The method statement shall include all safety features and protection to workmen, third party as well as property and
services nearby. Methods of shoring and strutting should be fully detailed in the method statement. Removal of excavated
material from excavated area, method of handling, method of storage (including any handling if necessary) as well as
disposal shall be explained fully. Where controlled blasting is restricted, the contractor should ensure that all necessary
statutory approvals are obtained in advance and kept in current and all necessary insurance and other covers shall be taken
and kept valid in the case of sub-contracting this job, such cover shall include sub-contractor's workman also. Where
controlled blasting is resorted to, contractor should take all necessary precaution for ensuring safety of life end property in
the vicinity.
12. Carting away of excavated soil/surplus /dense soil/ disintegrated/ weathered/ soft rock /other materials away from the
site to a place designated and not objected by civic authorities by mechanical means including lead, lift, loading, unloading
etc., complete. Including taking necessary approval from local authorities, environmental norms to be followed for discarding
earth with submission of document of proof and fee if any. For the purpose of payment, quantities from the excavated area
based on contour profile shall be accounted and loose earth or truck load will not be measured and paid. Rate to include all
royalties, Seignorage, taking statutory approvals, traffic permits from Police and Local body, as necessary to carry out the
works etc., complete. Disposal should also to an approved site only. No Lift / lead distance or limitation is specified or
accepted. Contractor are required to examine the scope of work, inspect the site and find out before quoting the approved
disposal points. No increase in rate is allowable on account of difference between lift / lead distances.
3. Contour level to be taken jointly with the Project Manager and prior written approval be taken
before starting any excavation/ filling at every 3 / 5 mt grids for arriving at the actual quantity using
simpsons rule. Cost to include all and necessary royalty and other permission charges required to
execute the works. The rate shall include all necessary setting out of building, excavation line,
barrication by grid/plot marking, survey by Total station, transfer of bench mark, etc., complete
4.Trimming all sides to plumb or otherwise as instructed at site, levelling all bottoms, clearing out all
loose earth etc. The rates to include necessary cutting, trimming and filling with compaction .
5. The selected fill material shall be approved by the Engineer In Charge before the same is used for
filling. The fill material shall be as specified. Black cotton, clayey or silty soil shall not be used. Soils
having laboratory density of less than 1.44 gm/cc may not be used for filling. Filled earth shall be
watered and compacted by power roller or any other approved mechanical means or adequate
capacity to achieve the required minimum proctor density of 95% to 98 % with 2.0gm/cc MDD . Cost
to include necessary plate load test at intervals to meet the specified compaction requirement. Filling
in foundations and in plinth in layers not exceeding 150 mm, watering, consolidation, dressing etc.
complete and include for all lifts and leads, transport from stacks, rehandling etc. Sample stretch
needs to be prepared as testing layer prior to start the actual filling works and number of passes
required to achieve the required density with optimum moisture content is derived considering all
factors like type of soil, type of rolling, number of passes etc.
6. Measurements for filling will be taken for consolidated thickness only. Cost to include all and
necessary royalty and other permission charges required to execute the works including testing of
core samples at intervals as per BIS codes etc., complete. The compaction load tests as per BIS Codes
needs to be done for each layer by the contractor to ensure that the required compaction is
achieved .
7. The method statement shall include all safety features and protection to workmen, third party as
well as property and services nearby. Methods of shoring and strutting should be fully detailed in the
method statement. Removal of excavated material from excavated area, method of handling, method
of storage(including any handling if necessary) as well as disposal shall be explained fully. Where
controlled blasting is restricted, the contractor should ensure that all necessary statutory approvals
are obtained in advance and kept in current and all necessary insurance and other covers shall be
taken and kept valid in the case of sub-contracting this job, such cover shall include sub-contractor's
workman also. Where controlled blasting is resorted to, contractor should take all necessary
precaution for ensuring safety of life end property in the vicinity.
Excavation by mechanical means using JCB / Poclaim etc in all types of soil including dense soil,
disintegrated/ weathered/ soft rock including necessary manual excavation for dressing the edges &
levelling, all leads and lifts. Rate to include storing the excess earth within the site to the required
levels wherever specified, removal of slurry generated while excavation and keeping the area free of
water, excavating loose pockets and compacting the same including providing required shoring,
strutting etc to retain the side earth from sliding. Contractor shall get accquainted with site
EW 01 conditions, nature of soil and adopt adequate conventional dewatering system as deemed fit for the
nature of soil and prevailing water table to get the surface reasonably dry at the time of execution so
that execution will not be hampered or delayed. Carting away all types of excess excavated earth
outside or within the site shall be included and environmental norms to be followed for discarding
earth with submission of document of proof. Rate is inclusive of making temporary stepping/sloping,
shoring with planking, strutting, sectioning, trimming, dressing of sides, leveling or grading, cleaning,
removing and excavating loose pockets.
Specification & scope of work same as EW 01 but for earthwork excavation in unpoclainable
Weathered rock/medium rock at all levels for general excavation with non blasting method like
EW 02
chisseling, quenching etc. using mechanical rock breaker attachment inclusive of all lead & lifts,
shifting, stacking at the plot of approved location.
2.1 For Foundation & Sub structure works Cum 450 3,770 16,96,500
Filling and consolidation from existing ground level / foundations / trenches etc with approved
available earth within the campus, where ever specified with approved good quality filling materials
including filling in layers of 15 cms, breaking clods, watering and consolidation, etc., complete.
Consolidation shall be properly done, using approved capacity mechanical compactor, to achieve a
EW 03 proctor density of 98%. Block levels at the place of depositing of earth at intervals as directed by the
Engineer should be jointly recorded by the contractor's representative and the Client Project
Manager before depositing of earth. Such levels shall be used for calculating the quantity of earth
deposited. The rate to include loading, unloading, hire and fuel charges for tools and plants and
other incidental charges etc., complete.
For Foundation & Sub structure works Cum 150 1,460 2,19,000
Filling around retaining wall Cum 150 3,515 5,27,250
Providing and laying plain cement concrete of grade M10 at all levels using
coarse graded aggregate of 20mm and down size, fine aggregates, cement
for levelling course under footings, flooring, steps, walls, platform, for
PCC 02 - -
external development works and at locations specified etc. including base
preparation, form work wherever necessary, levelling, compacting, curing
etc. all complete, as directed by Engineer-in-charge and as per drawings.
FW FORM WORK
Unless otherwise specified rates quoted for all Form works shall include the
following :
Cost of all materials, labour, equipment / tools & plants required, lead and lifts,
1
conveyance, infrastructure facilities required etc.
Form work shall include splayed edges, notching, allowances for overlaps and
passing at angles, batterns, strutting, bolting, wedging, casing, rocking,
centering, boxing, shuttering, propping strut braces etc., removal thereof and
2 coating the shuttering with releasing agent /oil to prevent cement sticking to
shutter faces. Form work shall be either straight, curved, plain or tapered and
also with provision for specified slopes, if directed. Wind tie bolts for wall
shuttering.
Cost of suitable framework and bracing according to the floor height specified
in the drawing, moulds, centering and shuttering, single / double height
scaffolding, as directed at site. Dimension of form work will be within the
3
tolerance as specified in IS 456 and shuttering should be water tight. Shuttering
materials shall be Aluminum / steel / timber or plywood as suitable for the work
intended.
Tenderer shall ensure that they have adequate quantity of shuttering and
suitable propping materials according to the floor height specified in the
drawing to keep up the required Concreting cycle per floor as set out in the
Tender Documents, Drawings and Programme. They shall also ensure that the
4 de-shuttering sequence with proper propping, taking into account the
Construction Loading of the upper slabs, as set out in the Tender Drawings, is
also kept up. Scheme to maintain the props shall ensure that main supports are
not disturbed. Reproping by means of removal and reintroducing of props is
not allowed.
Any honey coombs, any undulations, bulging, any leakage of slurry, concrete
5 etc is not acceptable and decision of the structural consultant along with the
architect is final.
Formwork shall be designed for close jointed rigid, durable and shall have
adequate strength, water tightness and ensure easy removal etc., Props,
shorings and bracings shall be all in steel. Formwork designed with proposed
6 materials (to be approved prior to making) shall be able to retain its shape, line,
dimension, level within the allowable limits of variations. Necessary
arrangement shall be envisaged to provide camber in beams or slabs as per
design.
All tie rod holes to be filled with approved grouting material. Cost to include
7 necessary embedded tie rod for fixing the one sided shuttering and water
retaining structures.
Shuttering & deshuttering sequence shall be 100%, 80% & 40% from the slab
to be cast respectively depending on the progress. The same is as per the details
enumerated in General Notes. Contractors shall submit drawings showing the
scheme of formwork including back propping and proper sequence of removal
8 of formwork and back propping so that the structural slab will not be
overloaded due to construction loads. All slabs shall be progressively DE
shuttered and back propped. It is compulsory to provide adequate back props to
the slab on which the supports are resting before taking up concreting work for
every slab.
Minimum of 150mm high MS frame works is required for kickers and starters
9 in case required and formwork design calculations including re-propping
arrangements needs to be submitted for approval.
Providing foam sheet at joints to prevent leakage of slurry during compaction,
10
removing adhesive tape from concrete surface if any after deshuttering
FORMWORK
Providing, erecting, laying & fixing of suitable Centering / Shuttering / staging /
form work systems as temporary works for execution of permanent works at all
levels for the following works including strutting, propping, bracing, staging,
moulding, de-moulding, deshuttering, etc., using approved formwork systems
including transportation, shifting the materials from yard to place of work,
assembling, multiple handling of the materials with necessary consumables
such as nails, screws, binding wires, fasteners, tools and tackels etc complete.
Cost to include sealing the joints in the formwork system with heavy duty
adhesive tape, sealers, applying mould releasing agents, aligning to required
line and levels including MS ties, concrete cover blocks spacers etc., complete.
FW 01 Foundations for all vertical elements including independent, combined, raft etc; Sqm 600 1,965 11,79,000.00
- -
FW 02 Grade slab Sqm 600 50 30,000.00
- -
FW 03 Retaining Wall Sqm 650 5,410 35,16,500.00
- -
FW 04 Ramp Beam Sqm 650 805 5,23,250.00
- -
FW 05 Ramp slab Sqm 600 545 3,27,000.00
- -
FW 06 Pedestals Sqm 600 200 1,20,000.00
- -
FW 08 Trenches / Ramp drain Sqm 600 180 1,08,000.00
- -
FW 09 Lintels Sqm 600 50 30,000.00
- -
FW 11 RCC Parapet at all levels - -
4th floor Sqm 650 35 22,750.00
5th floor Sqm 650 90 58,500.00
6th floor Sqm 650 270 1,75,500.00
terrace Sqm 650 650 4,22,500.00
- -
FW 13 FIRE SUMP and RWT - -
Walls Sqm 650 765 4,97,250.00
- -
FW 14 OHT - -
Bottom Slab Sqm 650 15 9,750.00
Walls Sqm 650 405 2,63,250.00
Top Slab Sqm 650 105 68,250.00
- -
FW 15 Sub-Soil Well - -
Bottom Slab Sqm 650 25 16,250.00
Walls Sqm 650 730 4,74,500.00
Top Slab Sqm 650 40 26,000.00
- -
FW 16 Staircase - -
Basement 02 Sqm 700 210 1,47,000.00
Basement 01 Sqm 700 273 1,91,100.00
Ground floor Sqm 700 252 1,76,400.00
1st floor Sqm 700 252 1,76,400.00
2nd floor Sqm 700 252 1,76,400.00
3rd floor Sqm 700 252 1,76,400.00
4th floor Sqm 700 252 1,76,400.00
5th floor Sqm 700 210 1,47,000.00
6th floor Sqm 700 210 1,47,000.00
- -
FW 17 Columns at all levels - -
Basement 02 Sqm 750 2,050 15,37,500.00
Basement 01 Sqm 750 1,495 11,21,250.00
Ground floor Sqm 750 875 6,56,250.00
1st floor Sqm 750 760 5,70,000.00
2nd floor Sqm 750 760 5,70,000.00
3rd floor Sqm 750 760 5,70,000.00
4th floor Sqm 750 760 5,70,000.00
5th floor Sqm 750 760 5,70,000.00
6th floor Sqm 750 760 5,70,000.00
- -
FW 18 Core wall at all levels - -
Basement 02 Sqm 750 2,115 15,86,250.00
Basement 01 Sqm 750 1,415 10,61,250.00
Ground floor Sqm 750 1,325 9,93,750.00
1st floor Sqm 750 1,240 9,30,000.00
2nd floor Sqm 750 1,240 9,30,000.00
3rd floor Sqm 750 1,240 9,30,000.00
4th floor Sqm 750 1,240 9,30,000.00
5th floor Sqm 750 1,240 9,30,000.00
6th floor Sqm 750 1,240 9,30,000.00
Terrace floor Sqm 750 1,240 9,30,000.00
-
FW 19 Flat Slab including drops at All Levels - -
Basement 01 sqm 650 5,505 35,78,250.00
Ground floor sqm 650 5,265 34,22,250.00
1st floor sqm 650 1,790 11,63,500.00
2nd floor sqm 650 1,960 12,74,000.00
3rd floor sqm 650 2,015 13,09,750.00
4th floor sqm 650 2,015 13,09,750.00
5th floor sqm 650 2,620 17,03,000.00
6th floor sqm 650 805 5,23,250.00
- -
FW 20 Regular Slab - -
Basement 01 Sqm 650 185 1,20,250.00
Ground floor Sqm 650 260 1,69,000.00
1st floor Sqm 650 430 2,79,500.00
2nd floor Sqm 650 330 2,14,500.00
3rd floor Sqm 650 405 2,63,250.00
4th floor Sqm 650 405 2,63,250.00
5th floor Sqm 650 405 2,63,250.00
6th floor Sqm 650 165 1,07,250.00
Terrace floor Sqm 650 265 1,72,250.00
Above Terrace Sqm 650 400 2,60,000.00
- -
FW 20 Voided Slab - -
Terrace floor Sqm 650 1,800 11,70,000.00
- -
FW 21 Beams at all levels - -
Basement 01 Sqm 650 450 2,92,500.00
Ground floor Sqm 650 645 4,19,250.00
1st floor Sqm 650 645 4,19,250.00
2nd floor Sqm 650 555 3,60,750.00
3rd floor Sqm 650 510 3,31,500.00
4th floor Sqm 650 510 3,31,500.00
5th floor Sqm 650 660 4,29,000.00
6th floor Sqm 650 205 1,33,250.00
Terrace floor Sqm 650 330 2,14,500.00
Above Terrace Sqm 650 80 52,000.00
- -
FW 23 Double Height Shuttering - -
Extra for providing double height staging work in addition to the respective
floor formwork and staging systems for a period of max 30 days at all levels &
heights, with steel scaffolding materials including erection and dismantling -
charges etc. complete with all lead & lift for all materials & labour and as
directed, at all heights & locations (only plan area will be measured).
5. Form work (which shall be measured and paid separately under relevant
item) include splayed edges, notching, allowances for overlaps and passing at
angles, battens, strutting, bolting, wedging, casing, rocking, centring, boxing,
shuttering, propping strut braces etc., removal thereof and dressing the
shuttering with oil to prevent, cement sticking to shutter faces. Form work shall
be either straight, curved, plain or tapered and also with provision for specified
slopes, if directed. Wind tie bolts for wall shuttering.
6. Keeping the work, well watered for 10 days after casting and it shall confirm
to IS Specification.
7. Placing in position any inserts like bolts, plates, sleeves, plugs for fixing
window frames in RCC members, pipes etc.
8. The contractors are particularly advised to study the relevant drawings
carefully before quoting.
9. Consolidation using vibrators of approved type as directed.
10. Work on all floors at levels as per drawing.
11. Reinforcement steel is measured and paid under relevant item separately.
12. Rate to include bonding agents for bonding old concrete to new concrete
wherever necessary.
13. All cover blocks shall be with PVC /Cement concrete with binding wires for
tying.
14. All Construction joints shall be at pre approved locations only. All
Construction joints and concrete set surface shall be chipped immediately after
final setting using mechanical chippers and thoroughly cleaned and shall be
treated with epoxy bonding agent while concreting further without any extra
cost. Expanded GI mesh shall be considered between the junction of difference
in grade of concrete only in slab & column/core wall with shear walls.
15. Forming key and construction joints, providing cement slurry work and
cleaning at any stage of work, sand papering of existing reinforcement bars of
column and dowels etc. as directed before taking up fresh work.
16. Coarse graded sand/ manufactured sand of approved make shall be used
for all concrete works.
17. Machine crushed coarse graded aggregate shall be hard broken blue
granite of sizes specified.
18. Cement for all concrete works shall only be High strength ordinary Portland
cement Grade-53.
19.Designing the concrete mix and batching as per specifications and approved
concrete design mix with necessary admixtures for various workability and
surface finish requirements.
20. Adding of admixture to meet the required standards and specifications for
various workability, consistency, self compaction, retardation, acceleration,
surface finish, colour, uniformity, strength, shrinkage control, durability, fire
rating, cohesiveness in the concrete as appropriate.
34. Making all sunk floors, pockets, cutouts, holes, sleeves, embedding
electrical conduits, junction boxes, fan hooks, cutout boxes and other inserts,
sleeves hold fasts, pipes etc as specified in the drawings.
35.All the lifting equipments including tower crane, boom placer, pumping
lines, material hoist, lifts shall have independent supporting systems and shall
not transfer any stress on building components.
36. Minimum cementatious content for concrete shall be as per cement
constants enclosed in the Technical specification.
Providing & laying plant mixed design mix reinforced cement concrete
conforming to grades as specified in (IS 456 - 2000) and as per specifications
mentioned below at all levels using 20mm & down size aggregates, fine
aggregates, OPC, necessary admixtures approved by Consultants, including
designing the mix, trial cubes, accelerated curing, weigh batching, mechanical
mixing, transporting, pumping and placing at all levels, excluding the cost of
steel reinforcement, centring, shuttering but inclusive of cost towards pumping
using line pump or boom placer, scaffolding, compacting with vibrators,
construction joint treatments, curing and hacking the exposed surfaces
wherever required to receive plaster or floated steel trowelled surface whenever
specified. The rate shall include cost of arrangements to provide recesses to
slabs, columns, walls and placing and securing properly within the formwork
sleeves and / or opening in slabs, construction joints, laying to required shape,
size and slope all as per drawings.
Cost to include appropriate dewatering wherever necessary, cost of all
materials, labours, all lead and lifts, tools, plant and machinery, hire and fuel
charges and all other incidental charges etc., all as per specifications, drawings
and as directed.
RCC 01 Foundations for all vertical elements including independent, combined, raft, etc; Cum 5,100 2,090 1,06,59,000.00
- -
RCC 02 Grade slab Cum 5,100 1,310 66,81,000.00
- -
RCC 03 Retaining wall Cum 5,100 815 41,56,500.00
- -
RCC 04 Ramp Beam Cum 5,100 155 7,90,500.00
- -
RCC 05 Ramp slab Cum 5,100 165 8,41,500.00
- -
RCC 06 Pedestals Cum 5,100 50 2,55,000.00
- -
RCC 07 Trenches / Ramp drain Cum 5,100 20 1,02,000.00
- -
RCC 08 Lintels Cum 5,100 10 51,000.00
- -
RCC 09 Parapet wall - -
4th floor Cum 5,100 5 25,500.00
5th floor Cum 5,100 10 51,000.00
6th floor Cum 5,100 30 1,53,000.00
terrace Cum 5,100 65 3,31,500.00
- -
RCC 10 FIRE SUMP and RWT - -
Walls Cum 5,100 80 4,08,000.00
- -
RCC 11 OHT - -
Bottom Slab Cum 5,100 30 1,53,000.00
Walls Cum 5,100 45 2,29,500.00
Top Slab Cum 5,100 25 1,27,500.00
- -
Sub-Soil Well along with the retaining wall including bottom and top
RCC 12 - -
slabs
Bottom Slab Cum 5,100 20 1,02,000.00
Walls Cum 5,100 75 3,82,500.00
Top Slab Cum 5,100 10 51,000.00
- -
RCC 13 Staircase at all levels - -
M30 grade - -
Basement 02 Cum 5,100 30 1,53,000.00
Basement 01 Cum 5,100 39 1,98,900.00
Ground floor Cum 5,100 36 1,83,600.00
1st floor Cum 5,100 36 1,83,600.00
2nd floor Cum 5,100 36 1,83,600.00
3rd floor Cum 5,100 36 1,83,600.00
4th floor Cum 5,100 36 1,83,600.00
5th floor Cum 5,100 30 1,53,000.00
6th floor Cum 5,100 30 1,53,000.00
- -
RCC 14 Columns and shear walls at all levels - -
M40 grade - -
Basement 02 Cum 5,600 370 20,72,000.00
Basement 01 Cum 5,600 270 15,12,000.00
M30 grade -
Ground floor Cum 5,100 175 8,92,500.00
1st floor Cum 5,100 155 7,90,500.00
2nd floor Cum 5,100 155 7,90,500.00
3rd floor Cum 5,100 155 7,90,500.00
4th floor Cum 5,100 155 7,90,500.00
5th floor Cum 5,100 155 7,90,500.00
6th floor Cum 5,100 155 7,90,500.00
- -
RCC 15 Column Drops - -
M40 grade - -
Basement 01 Cum 5,600 150 8,40,000.00
Ground floor Cum 5,600 155 8,68,000.00
M30 grade -
1st floor Cum 5,100 40 2,04,000.00
2nd floor Cum 5,100 50 2,55,000.00
3rd floor Cum 5,100 50 2,55,000.00
4th floor Cum 5,100 50 2,55,000.00
5th floor Cum 5,100 50 2,55,000.00
6th floor Cum 5,100 20 1,02,000.00
-
RCC 16 Flat Slab including drops at All Levels -
M30 grade -
Basement 01 Cum 5,100 1,330 67,83,000.00
Ground floor Cum 5,100 1,375 70,12,500.00
1st floor Cum 5,100 435 22,18,500.00
2nd floor Cum 5,100 475 24,22,500.00
3rd floor Cum 5,100 490 24,99,000.00
4th floor Cum 5,100 490 24,99,000.00
5th floor Cum 5,100 635 32,38,500.00
6th floor Cum 5,100 195 9,94,500.00
- -
RCC 17 Regular Slab - -
M30 grade - -
Basement 01 Cum 5,100 50 2,55,000.00
Ground floor Cum 5,100 60 3,06,000.00
1st floor Cum 5,100 65 3,31,500.00
2nd floor Cum 5,100 50 2,55,000.00
3rd floor Cum 5,100 60 3,06,000.00
4th floor Cum 5,100 60 3,06,000.00
5th floor Cum 5,100 60 3,06,000.00
6th floor Cum 5,100 25 1,27,500.00
Terrace Cum 5,100 40 2,04,000.00
Above Terrace Cum 5,100 80 4,08,000.00
- -
RCC 18 Beams at all levels - -
M30 grade - -
Basement 01 Cum 5,100 85 4,33,500.00
Ground floor Cum 5,100 140 7,14,000.00
1st floor Cum 5,100 145 7,39,500.00
2nd floor Cum 5,100 130 6,63,000.00
3rd floor Cum 5,100 115 5,86,500.00
4th floor Cum 5,100 115 5,86,500.00
5th floor Cum 5,100 150 7,65,000.00
6th floor Cum 5,100 50 2,55,000.00
Terrace Cum 5,100 75 3,82,500.00
Above Terrace Cum 5,100 20 1,02,000.00
- -
Free flow concrete for below mentioned elements - -
Providing and placing of specified grade FREE FLOW CONCRETE, with specified
cementitious content and admixture, aggregates used shall be 20 mm and
down etc complete, trails shall be conducted to establish typical mix as per site
requirements and as per manufacturer's specification and as per directions of
- -
engineer in charge, including all leads and lifts, pumping using line pump or
boom placer, vibrating (if required)/ compaction, scaffolding wherever
necessary, curing as directed, excluding cost of shuttering and reinforcement
works.
RCC 19 Core Walls and Staircase walls at RCC core area in all levels - -
M40 grade - -
Basement 02 Cum 6,000 210 12,60,000.00
Basement 01 Cum 6,000 140 8,40,000.00
M30 grade -
Ground floor Cum 5,400 135 7,29,000.00
1st floor Cum 5,400 125 6,75,000.00
2nd floor Cum 5,400 125 6,75,000.00
3rd floor Cum 5,400 125 6,75,000.00
4th floor Cum 5,400 125 6,75,000.00
5th floor Cum 5,400 125 6,75,000.00
6th floor Cum 5,400 125 6,75,000.00
Terrace floor Cum 5,400 125 6,75,000.00
-
RCC 20 Voided Slab -
Transfer slabs use in Voided slab system including solid drops at All Levels.
Necessary arrangement to be made for concreting of voided slab system -
without any construction joints. Thermocole is measured under separate item.
M50 Grade -
Terrace-(900 x 900 x 750 (150 mm thk top & 150 thk bottom slab & 500 mm
Cum 7,000 1,350 94,50,000.00
thck deep thermocole))
-
Providing, supplying and fixing in position extruded polysterene cubes of
specified size (thermocole) of minimum density of 20 kg/cum for creation of
voids in between the concrete slabs. cost to include wrapping thermocole with
RCC 21 -
150 micron polythene sheets, placing the same after casting of bottom slab
during concreting, alignment, line level etc complete. Necessary arrangement to
be made for concreting of voided slab system without any construction joints.
2 All reinforcement steel shall be from the primary steel ingots qualifying IS 1786.
All reinforcement steel shall be cut & bent to the required size and shape as
detailed in the structural drawings using necessary plants & machinery in the
factory/ site and all lapping for 16mm and above in columns, corewalls,
4
shearwalls & staircase walls shall be using mechanical threaded couplers as per
the code. For all other elements lap length shall be considered as per structural
drawings & details.
Quantity of steel shall be as per drawing and authorised overlaps only shall be
measured and paid. Contractor shall prepare bar bending schedule and
fabrication shall be carried out as per approved bar bending
5
schedules/fabrication drawing. All testing including physical & chemical and
quality assurances shall be as per the tender conditions/ Specifications and no
extra shall be paid for the same.
Unless otherwise noted in the bills of Quantities, method of measurements shall
be generally in accordance with IS 1200. Reinforcement shall be measured only
in lengths of bars as actually placed in position on standard weight basis, no
6 allowance being made in the weight for rolling margin. Authorised laps and
splices only will be measured. Chairs of any shape & profile, Spacer bar of any
shape & profile, cover block, wastage and binding wire will not be measured
and shall be included in the quoted rates.
Tests on materials shall conform to IS Specification and the test shall be carried
8
out as directed either at site Laboratory or at any approved test laboratory.
Quoted rate to include lead, lift, necessary fixing and tying arrangements for
9 dowel bars, protection to dowel bars rebending of dowel bars, placing at all
levels and as directed.
STEEL WORKS
Quantity of steel as per drawing and with authorised overlaps only shall be
measured and paid for. Contractor shall prepare bar bending schedule and
fabrication shall be carried out as per bar bending schedules. (Note: All testing
(including physical & chemical) and quality assurances shall be as per the
tender conditions/ Specifications and no extra shall be paid for the same.)
Couplers
a Couplers
For 32 mm dia Nos 300 468.00 1,40,400
For 25 mm dia Nos 240 1,404.00 3,36,960
For 20 mm dia Nos 220 1,053.00 2,31,660
For 16 mm dia Nos 200 1,404.00 2,80,800
- -
b Reduced couplers - -
For 32-25 mm dia Nos 300 93.60 28,080
For 32-20 mm dia Nos 300 46.80 14,040
For 32-16 mm dia Nos 300 70.20 21,060
For 25-20 mm dia Nos 250 468.00 1,17,000
For 25-16mm dia Nos 250 46.80 11,700
For 25-12mm dia Nos 220 351.00 77,220
For 20-16 mm dia Nos 220 117.00 25,740
For 20-12 mm dia Nos 200 187.20 37,440
Cost of all materials, labour, equipment / tools & plants required, conveyance,
5 infrastructure facilities required etc. Scope includes All necessary Plant and
Machineries, Power and Water supply and site establishments.
Rate to include shims and packing pieces. No extra on this account will be paid
6 for and rate to include preparation of fabrication shop drawing for Engineer in
charge approval.
The structural steel work shall include welded and built up sections, trusses,
built-up purlins, framework welded and/or bolted, girders, gusset plates, base
plates, cleats, installing inserts etc., as per drawings. Cost to include fabricating
7
necessary Gusset Plates, Stiffener plates, Brackets, Bolts, Cleats, seating angles,
bolts, washers, and grouting for bolts etc., to the required size, shape,
alignment etc., as per the drawings
Work at any depth below ground level or any height above ground level and at
8
all levels, heights & elevation and location.
Tests on materials shall conform to IS Specification and the test shall be carried
17
out as directed either at site Laboratory or at any approved test laboratory.
All structural steel works shall be done in accordance with technical specification
18 Division 5 Section 05100 and intumescent fireproofing shall be done in
accordance with technical specification Division 5 Section 05250.
The rate to include lifting, erection, aligning, levelling, providing and fixing
bolts, nuts, washers, supplying required templates for embedment etc., to the
required size, shape, alignment etc, as per the drawings.
MW MISCELLANEOUS WORKS
Unless otherwise specified rates quoted for all miscellaneous works shall include the following :
1. Cost of all materials, labour, equipment / tools & plants required, conveyance, infrastructure
facilities required etc.
2. Work shall be at all levels, heights & elevation and location.
4. Cement for all works shall be High strength ordinary portland cement Grade 43 or Grade 53
5. Coarse graded natural sand/ approved make manufactured sand shall be used.
6. Machine crushed coarse graded aggregate shall be hard broken blue granite of sizes specified
only to be used for concrete works.
7. All materials supplied from successful tenderer shall be free from manufacturing defects and
defective workmanship and guaranteed. Any defects noticed shall be made good,at no extra cost
8. Tests on materials shall conform to IS Specification and the test shall be carried out as directed
either at site Laboratory or at any approved test laboratory.
9. Provide all materials, hardwares, bolts and nuts, washers, any fastening materials and devices,
anchor fasteners shall be of approved make and conform to IS specification if required.
Excavation in all sorts of soil for laying sub soil drainage pipe upto 160mm dia (internal) including
forming bottom surface to required level refilling selected excavated earth around the pipe in
MW 01 Cum 350.0 155 54,250.00
layers of 150mm thick watering consolidating and disposing off the surplus earth with in the site or
as directed by the site Engineer with in a lead of 300m etc., complete.
-
Providing and laying plain cement concrete of grade M10 at all levels using coarse graded
aggregate of 20mm and down size, fine aggregates,OPC/PPC for levelling course under footings,
MW 02 flooring, steps, walls, platform, for external development works and at locations specified etc. Cum 5,000.0 35.00 1,75,000.00
including base preparation, form work wherever necessary, levelling, compacting, curing etc. all
complete, as directed by Engineer-in-charge and as per drawings.
Providing and laying fine aggregate cushion layer in the trenches, drainage systems for full width
MW 03 and all-round the pipes as indicated in the drawing. Cost to include necessary compaction etc., Cum 1,500.0 75.00 1,12,500.00
complete including lead and lift etc., complete as directed by the Engineer-in-charge.
-
Providing and laying 20mm single size aggregate for sub-soil drainage system to the specified
MW 04 width and depth as indicated in the drawing, Cost shall include necessay lead and lift etc., complete Cum 1,300.0 80.00 1,04,000.00
as directed by the Engineer- in-charge.
- -
Providing and laying hard sub soil drainage pipe made up of moulded core. Drainage pipe shall
have two third as porous and factory slotted to give route for water to drained out. Pipe shall have
good water permeability, high pressure resistance, light weight, long service life etc. Thechnical
MW 05 details: Cannular size: f80, weight: 1800g/m, void ratio: 85%, Pressure Resistance: (flat rate 20%): - -
125. Rate quoted shall include 180GSM Gio-fabric sheet (geo-filter mesh) of approved make all-
round the pipes as indicated in the drawing. etc., complete including lead and lift as per drawing &
other associated works.etc,complete as directed by the Engineer-in-charge.
i 160mm dia Rmt 1,250 360.00 4,50,000.00
- -
Providing and wrapping polypropelene non woven geo fabric of GSM 180 mm thick encasing
along the retaining wall as indicated in the drawing for smooth drainage system without any
MW 06 - -
clogging etc., complete as instructed by the Engineer-in-charge. Cost to include all the necessry
lappings, only syrface area will be measured and paid.
i Along the retaining wall around filling towards earth side Sqm 150 2,705.00 4,05,750.00
i Along the perimeter of the drainage trench Sqm 150 695.00 1,04,250.00
- -
- -
Civil Work associated with PHE works (Quantity to be provided by PHE Consultants)
Supplying, installing, testing and commissioning of GI - Heavy duty "C " Class puddle flange of
MW 07 900mm length for inlet, outlet, vent and overflow pipes, overhead water tank and under ground - -
water tank complete as shown in the drawings complete, accessories comprising of the following :
a 50 mm dia Nos - -
b 80 mm dia Nos - -
c 100 mm dia Nos - -
d 150 mm dia Nos - -
e 200 mm dia Nos - -
f 250 mm dia Nos - -
g 300 mm dia Nos - -
- -
MW 08 Supplying, installing and commissioning of D.I frame & Cover with locking facility. Make- NECO - -
a DI Manhole frame & cover (0.6x0.6m) A Class loading for OHT Nos - -
b DI Manhole frame & cover (0.6x0.6m) C Class loading Nos - -
c DI Manhole frame & cover (0.9x0.6m) C Class loading Nos - -
- -
Supplying, fabrication and installing MS grill for the sumps below the DI frame and cover, all the
MW 09 necessary fittings, Aldrops, hinges and hardware etc. The MS frame shall be covered with 2 coats of - -
anticorrosive paints & 2 coats of epoxy paints.
a a 0.6mx 0.6m Kgs - -
- -
Basement Drainage - -
Supplying, installing, testing and commissioning of inlet and outlet G.I “C” class puddle flange,
MW 10 conforming to table F with thickness of wall ratio 1:2 for storm water collection sump with PVC - -
steps as shown on the drawings etc., complete with accessories comprising of the following.
a 100mm dia puddle flange for vent pipe with mosquito proof mesh Nos - -
b 50 mm dia puddle flange Nos - -
c 80mm dia puddle flange Nos - -
All puddle flanges to be hot dip galvanised. - -
- -
Supplying, installing and fixing of PVC encased MS steps/ Rungs capable to bear upto 200kg of
MW 11 weight as shown on the drawings complete with accessories, Hardwares, tools , tackles etc, - -
comprising of the following sizes.
a 200mmx200mm Nos - -
- -
Supplying of material and making 300mm wide drain as per structural detail and Medium duty
370mm wide X 600mm length (each piece) over storm water drain as per the drawing incl. All
MW 12 Nos - -
leads and lifts, finishing the joints with CM 1:3 curing with precast or cast insitu top slab. The top
slab should have perforations by giving necessary 50mm dia sleeves.
- -
Supplying, installing and fixing of MS Cage ladder with all the necessary L angles, Pipes, etc as
MW 13 - -
shown in the drawings.
a 450mm wide Kg - -
b 600mm wide Kg - -
- -
C STORM WATER DRAINAGE SYSTEM - -
Construction of Catch basin of size mentioned below upto 600mm clear internal dimension and
depth upto 1200mm dimension for external storm water drainage with RCC walls overall bed of
100mm thick PCC 1:4:8 internal walls plastered smooth with necessary water proof compound in
CM 1:3 and external walls plastered in1:6 with sponge finish. Supply, Fixing precast D.I manhole
MW 14 Nos - -
cover with frames Heavy duty as per IS-12592 on top surface flushed to the finished floor / road
level with necessary excavation, backfilling around the catch basin with selected excavated earth
and disposal of surplus earth upto the dumping site as allowed by the authorities.complete in all
respect.
- -
Providing 15mm thk waterproof smooth finish cement rendered plaster to drain walls etc, including
water proof compound, wherever required in cement mortar 1:4 below mentioned thick, finishing
MW 15 Sqm - -
to line and level at all levels & lifts including lead and lift, cost to include scaffolding, cleaning,
necessary hacking, curing and providing necessary architectural grooves as directed, etc complete.
- -
Providing and laying to the required gradient 900mm wide precast Concrete perforated ( 50mm
dia) cover slab of 100mm thick over storm water drain wall as per the drawing incl. All leads and
MW 16 Rmt - -
lifts, finishing the joints with CM 1:3 curing etc.,complete. Design is as per landscape intent (Quoted
rate shall include steel reinforcement as per the drawing.)
- -
Construction of well with Precast Concrete rings of 1.2m dia and 75mm thick of suitable height of
the ring upto 3.0m deep and upto the formation level as per DRG with Heavy duty D.I manhole
MW 17 cover along with the Pre-cast slab at the top inlcuding all lead and lift. Rate shall also include Nos - -
backfilling around the well, Filtration Media Installation For Injection As per Drg. Mixture of Brick
Bats and Gravels for filling the gap between excavated earth . The rate shall includes The geofabric
filters, PVC encased MS rungs of 200mm x 200mm size at every 300mm and making a Drill hole of
150mm upt0 30RM deep for ground water charging
- -
MW 18 RCC Hume Pipes / PVC Pipes / GI Pipes - -
Quoted rate shall include necessary excavation, back filling, cementing of joints and construction of
- -
chambers of 1mtr X 1mtr X 1.5mtr depth with heavy duty cover @ every 20mtr.
class NP2 RCC hume pipe sleeves with collar with concrete encasing for laying below the
- -
landscaped area outside the buildings between the cable pulll pits and road crossing
a RCC Hume Pipe-200 mm dia. with collers on both sides Rmt - -
b RCC Hume Pipe-150 mm dia. with collers on both sides Rmt - -
c PVC Pipe-100 mm dia 2 mm thick Rmt - -
d PVC Pipe-65 mm dia 2 mm thick Rmt - -
e Flexible pipe (equivalent to LAPP brand)-25 mm dia Rmt - -
HDPE (High density polyethylene) pipes with 6KG. - -
f 32 mm dia. Rmt - -
g 50 mm dia. Rmt - -
h 75mm dia. Rmt - -
- -
MW 19 Concealed conduit in Staircase - For Basements - -
Supply & installation of conduits and accessories in the civil works associated with the staircases - -
a 25mm dia, 2mm thick rigid PVC conduit with accessories Rmt - -
b GI deep junction box 75x75x65mm Nos - -
- -
MW 20 Providing & fixing chainlink fencing for a height of 2.50m including Rmt - -
a) providing and fixing of 50mm dia nominal boreM.S Medium duty pipe supports at every 2.00m
c/c in position with necessary excavation, PCC 1:3:6 of size 300x300x600mm using 20 mm and
- -
down size graded aggregates,re filling etc.,complete. The cost should include 200mm thick Solid
blockmasonsry upto 750mm high including sponge finish plaster on both sides of the wall.
b) Providing and fixing in position 10Guage GIchainlink mesh stiffened with peripheral MS
- -
angle(40x40x6) and flat (25x3mm) to MS tube bynecessary Inserts,MS angles and welding
c) Providing door of specified width with chain link meshstiffened with MS angles and location - -
d) providing two coats of synthetic Enamel painting over a coat of primer for the MS fence. - -
- -
Providing and making 150 mm wide Scupper drain including plastering, slurry finish, etc all
MW 21 Rmt - -
complete as per the drawings and specification and complete satisfaction of engineer.
- -
MW 22 Providing Manpower for Miscellaneous Works as directed by the Project in charge for 8hrs shift - -
a) Skilled Labour No - -
b) Unskilled Labour ( M/c) No - -
c) Mason No - -
d) Tile Mason/ Granite Mason No - -
e) Fitter - Barbender No - -
f) Carpenter No - -
g) Welder No - -
h) Khalasi No - -
- -
Supply and mixing of Recron-3s Polypropylene Fibre CTP2424/2mm to the ready mix Concrete as
MW 23 per the proportion recommended by the Consultant . This item should not be opreated for the Kgs - -
screed done above the water proofing in the terrace and poidum levels
- -
Providing and fixing of Reinforcement Steel using Lock Fix material of FOSROC make. Rate shall
MW 24 - -
include for drilling of holes at all levels and as specified by project in charge
16mm dia No's - -
12mm dia No's - -
10mm dia No's - -
8mm dia No's - -
- -
Providing, supplying, mixing, injecting, and grouting of rock fischers, grieviences, using cement
grout made up of OPC, water and necessary admixtures in the required proportion to fill up the
MW 25 cracks and stabilise the rock formations below foundation surface. cost to include necessary mixing Kg - -
buckets, storage, aggitators, pumping mechanism, nozzles etc including drilling, inserting nozzles
etc complete. Rate shall be quoted based on the consumption of the cement.
Providing and laying of light weight material fill on structural slab using light weight aggregates
having higher compressive strength and highest fire resistance with thermal / acoustic insulation
properties etc of Multilite in mix proportion of 1:10:3.5 (1cement : 10 Multilite : 3.5water) in the
MW 26
suggested proportion to get the desired density, mixing, transportation, placing, compacting and
finishing to the required level with necessary side supports, equipments, rate to include for a coat of
latex SBR to fill up the porosity of finished surface etc complete.