Professional Documents
Culture Documents
PART- A
1.0 SITE DEVLOPMENT AND EARTH WORK
1.1
Excavation over areas / foundation trenches below excavated pit level
7,696.86
Earth work in excavation in foundation/ over area all kind of soils as met at
site in foundation trenches including dressing of sides and ramming of
bottoms, dewatering, bailing, pumping out or otherwise removing all water
25.1.1 which may accumulate in the excavation from all causes, for all lifts & leads Cum. 65.01 129.00 129.00 100.00 59.67 59.67 7,696.86
including getting out the excavated soil for all leads / lifts/depth and
Disposal of excavated earth as suitable areas inside the premises as
Directed by by Engineer- in –Charge
1.2.1
Filling with selected, suitable excavated earth in plinths, back of retaining
walls, foundations and trenches and other locations as directed by the Engg-
in-Charge and shall be done in layers, not exceeding 20cm in depth and
consolidating each deposited layer by mechanical means, ramming and
watering as per specifications including transportation, loading, unloading,
100.A1.3 carriage to dumping spot and all incidentals at all depth, levels, leads and cum. 65.01 94.00 94.00 100.00
lifts complete. (Net consolidated area fill volume will be computed from the
initial and final levels. Volume in slopes, embankments etc. will be computed
applying appropriate formula, as per CPWD specification). Note:- filling shall
be done with the available excavated earth done by the vendor or with the
earth supplied by the client.
2.1.3 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm and 20,18,138.76
101.1.5 cum 536.03 3,966.00 3,966.00 100.00 508.86 508.86 20,18,138.76
down gauge)
2.3
Providing and laying in position machine batched, machine mixed and
machine vibrated design mix cement concrete of M-25 gradeusing Fly
ash for reinforced cement concrete structural elements, excluding the cost
of centring, shuttering, finishing and reinforcement steel but including
admixture in recommended proportion (as per IS: 9103) to accelerate, retard
setting of concrete, improve workability without impairing strength and
durability, cost of making shear keys and provision of construction /
contraction / control joints in various locations, laid, consolidated and cured,
item to include all structural items like base raft, ramp, column, wall, footings,
equipment foundations, fins, mullions, beams, lintels, pergola, chajja, facia,
parapet, railing, slab, trenches, drains and sumps etc. of any shape and
sizes. (The rates of concrete to include the cost of admixtures / plasticisers
to achieve specified strength and to facilitate pumpable concrete.The quoted
rates are for all height,depths,leads and lifts. Cost of transportation of fly
ash also to be included in the quoted rate).
e 79,320.00
Suspended slab, Roof , loft slab, chajja, stairs waist slab and landings
101.5.5 Cum. 20.00 3,966.00 3,966.00 100.00 20.00 20.00 79,320.00
,shelves,counters,suspended slab of tank,cantilever projections etc.
f 2,60,727.62
101.5.6 vertical and horizontal fins, facias,planters,copings,cills,parapets,pergolas Cum. 62.45 4,249.00 4,249.00 100.00 61.36 61.36 2,60,727.62
Allow for forming grooves, drip course, chamfers, cut-outs, openings etc.
where called for and for dressing with approved shuttering oil to prevent
adhesion. Unexposed concrete surfaces subsequently left untreated (in the
condition obtained on removal of form work) shall not constitute exposed
concrete work and shall be measured under this item only. Irregular shapes
with sides which may not be perpendicular to each other for shapes not
conforming to rectangle or square shall not be paid separately.The item to
include centering and shuttering at all heights and levels. (quoted rate to
include all staging upto 3.5 m heights and levels).
c. 6,74,793.42
Suspended floors, roofs, landings, balconies, stairs and landings,
102.2.3 slabs of water tank, ramp slabs , Lintels, beams, floor beams, girders, sqm 1,324.72 519.00 519.00 100.00 1,300.18 1,300.18 6,74,793.42
cantilever beams, deep beams, ramp beams, bridge etc.
d. Columns, pillars, piers, abutments, posts and struts, off sets & 98,964.61
102.2.4 projection of columns, transfer columns, lift walls, O.H.water tank sqm 216.91 519.00 519.00 100.00 190.68 190.68 98,964.61
walls, etc.
e. 102.2.5 Shelves in kitchen/ pantries and toilets etc sqm 405.41 567.00 567.00 100.00 399.95 399.95 2,26,771.65 2,26,771.65
h.
Extra for every additional height of one (01) meter beyond 3.5 m height
in centering, shuttering where ever required with adequate bracing,
sqm. RO 75.00 75.00
proppling etc. including cost of de-shuttering and de-centering at all
levels for (plan area to be measured only for a minimum height of 8mtr).
14,98,146.50
Providing and constructing half brick masonry using selected quality
burnt clay FPS brick of class designation 75 in super structure laid in
cement mortar 1:4 (1 cement : 4 coarse sand) mix, joints finished, flush
106.1.3 / raked to 6mm depth as directed by Engg-in-Charge including sqm 2,002.00 755.00 755.00 100.00 1,984.30 1,984.30 14,98,146.50
providing and placing 2 Nos. 6mm dia. M.S. bars at every third course of
half brick masonry, scaffolding, curing, complete as per specification and
drawing or as directed by Engg-in-Charge.
106.1.30
3.4 Brick work 7cm thick with FPS bricks of class designation 75 in 46,336.24
106.1.4 sqm 61.37 755.00 755.00 100.00 61.37 61.37 46,336.24
cement mortar 1:3 (1cement: 3coarse sand)
Cleaning RCC surfaces and plastering of RCC and brick wall surface
with 12mm cement mortar 1:4 ( 1 cement : 4 coarse sand) mixed with
CICO or equivalent admixture as per manufacturer's specifications.
(A) Providing and laying water proofing treatment for terrace with the
following including cleaning the RCC slab top surface.
4.9.1
FOR VERTICAL WALLS/OTHERS LOCATIONS ( post construction )
5.1.1
Fixing in position of wooden door frame(App. Size-65x125 mm )
including cutting the masonary of size 300x100x150 mm. and the cost of
40x5 mm flat iron holdfast 400 mm long embedding in concrete blocks
300x100x150 mm in cement concrete 1:3:6 as directed. The item includes
108.2.1 providing and fixing beading, applying anti termite wood preservative paint No 163.00 1,180.00 1,180.00 100.00 163.00 163.00 1,92,340.00 1,92,340.00
on the surface coming in contact with wall,chasing,priming coat and two coat
of painting complete.(Only wooden frame will be supplied by Owner free of
cost. All other activities and works in the scope of contractor including
labours and materials).
5.1.1
Providing and Fixing in position of wooden door frame(App. Size-65x125
mm ) including cutting the masonary of size 300x100x150 mm. and the cost
of 40x5 mm flat iron holdfast 400 mm long embedding in concrete blocks
300x100x150 mm in cement concrete 1:3:6 as directed. The item includes
108.2.2 No 18.00 5,005.00 4,504.50 90.00 18.00 18.00 81,081.00 81,081.00
providing and fixing beading, applying anti termite wood preservative paint
on the surface coming in contact with wall,chasing,priming coat and two coat
of painting complete.(Basic Rate of pre-fabricted seasoned wooden door
frame for standard size - 2.1m x 1.0m = Rs. 2950 each).
5.6 Providing and fixing brush finished stainless steel hanging type floor
112.1.15 Each. 1,000.00 307.00 260.95 85.00 468.00 468.00 1,22,124.60 1,22,124.60
door stopper with necessary screws etc. complete.
108.2.11 After complition 30.70 10.00 468.00 468.00 14,367.60 14,367.60
15.35 5.00 468.00 7,183.80
5.8 Providing and fixing of Magic eye of approved make including screws and
108.2.13 Each 90.00 179.00 179.00 100.00 90.00 90.00 16,110.00 16,110.00
all necessary accessories etc. complete.
6 SUB-FINISHING WORKS
6.1 Wall plaster
6.1.1 Internal surface
6.2 6 mm plaster
Providing and applying 6 mm thick plaster to RCC surface and ceiling in
cement mortar 1:`3 (1 cement : 3 fine sand ) finished smooth including
109.1.9 sqm 5,000.00 165.00 165.00 100.00 4,424.60 4,424.60 7,30,058.48 7,30,058.48
hacking the surfaces, scaffolding, curing, making grooves at desired location
etc. complete as per drawing.
Providing and fixing 600mm long hot dipped galvanised iron puddle
flange for water tank as per IS :1239 (Class C), threaded on both side and
6mm thick M.S. plate of suitable size and welded alround the pipe fixed in
walls, beams and top slab of tank as per detail complete in all respects.
7.3.4 111.1.7 50 mm dia each 3.00 1,416.00 1,416.00 100.00 3.00 3.00 4,248.00 4,248.00
7.3.5 111.1.8 80 mm dia each 24.00 1,605.00 1,605.00 100.00 24.00 24.00 38,520.00 38,520.00
7.3.6 111.1.9 150 mm dia each 3.00 3,022.00 3,022.00 100.00 3.00 3.00 9,066.00 9,066.00
8 MISCELLANEOUS
8.3
Dismantling of brick work in cement mortar, (full brick) with plaster on
115.1.1 both sides stacking of serviceable material and disposal of unserviceable cum. 35.94 1,416.00 1,416.00 100.00 29.17 29.17 41,302.09 41,302.09
material to dumping area as directed by Engg-in-Charge.
8.4
Dismantling of brick work in cement mortar, (half brick) with plaster on
115.1.2 both sides stacking of serviceable material and disposal of unserviceable sqm 69.70 189.00 189.00 100.00 69.70 69.70 13,173.21 13,173.21
material to dumping area as directed by the Engg-in-Charge.
8.5 Dismantling of RCC works in beams, columns, slabs etc. including sub-
base, cutting and removal of reinforce-ment, stacking of serviceable
115.1.3 cum 28.00 7,082.00 7,082.00 100.00 26.84 26.84 1,90,110.77 1,90,110.77
material and disposal of unserviceable material to dumping area as directed
by the Engg-in-Charge.
8.6 Chipping of Plaster/ Brick work and disposal of malba out side the
115.1.4 sqm 70.00 70.00 70.00 100.00 26.55 26.55 1,858.64 1,858.64
premises as directed by the Engg-in-Charge.
PART - B
S. No. Description Unit
1.0 FLOORING WORK
Providing and laying 18 mm thick Cement plaster with cement mortar 1:3
108.1.43 (1 cement : 3 coarse sand) finished with a floating coat of neat cement as sqm 1,300.00 198.00 198.00 100.00 1,300.00 1,300.00 2,57,399.90 2,57,399.90
per drawing and design.
1.3
Glazed tile
1.3.2
Providing and fixing 1st quality glazed ceramic tiles conforming to IS
:13753 of minimum thickness 5 mm of any sizes and in all colours and
shades as approved by Engg-in-Charge on 20 mm thick bed of cement
108.1.45
plaster 1:4 (1 cement:4 coarse sand) including pointing thejoints with white
cement mixed with pigment of matching shade complete in all respect as per
drawings.(Tiles will be supplied by owner free of cost)
1.4.2
Providing and fixing 1st quality vitrified tiles of minimum thickness
8mm to 10 mm of any sizes and in all colours and shades as approved
by Engg-in-Charge on 20mm thick bed of cement morter 1:4 (1
108.1.49
cement:4 coarse sand) including pointing and grouting the joints with
white cement mixed with pigment of matching shade complete in all
respect as per drawings.(Tiles will be supplied by Owner free of cost)
1.4.4
Providing and fixing 1st quality vitrified tiles of minimum thickness
8mm to 10 mm of any sizes and in all colours and shades as approved
by Engg-in-Charge on 12 mm thick bed of cement morter 1:4 (1
108.1.51
cement:4 coarse sand) including pointing and grouting the joints with
white cement mixed with pigment of matching shade complete in all
respect as per drawings.(Tiles will be supplied by Owner free of cost)
1.6
Providing and Fixing 18 mm thick granite stone (Full size/single piece is
to be used. sample of granite stone shall be approved by Engg-in-
Charge)in flooring, lift lobby walls,corridor walls,counters of toilet
etc,.including rubbing and curing,cutting the stone for sink&
washbasin as per required shape and size etc complete. over 20mm
thick base of cement mortar 1:4 (1cement: 4coarse sand) laid and
jointed with white cement slurry mixed with pigment including rubbing and
polishing complete at all levels with :
1.6.1 Granite stone with approved shade and size on sink & toilet counter
108.1.54 Sqm. 2,100.00 3,258.00 3,258.00
(Basic rate of stone =Rs.125/sft)
FLOORING WORK Sqm. 2,932.20 90.00 2,100.00 2,100.00 61,57,623.74 61,57,623.74
After complition 162.90 5.00 1,085.00 1,015.00 2,100.00 1,76,746.50 1,65,343.71 3,42,090.21
162.90 5.00 2,100.00 3,42,090.21
1.6.2 Granite stone with approved shade and size in lift lobby wall (Basic
108.1.55 Sqm. 191.37 3,258.00 3,258.00
rate of stone =Rs.125/sft)
skirting Sqm. 2,932.20 90.00 191.37 191.37 5,61,132.18 5,61,132.18
PART RATE RELEASE 162.90 5.00 191.37 191.37 31,174.01 31,174.01
162.90 5.00 191.37 31,174.01
1.9 Extra for providing edge moulding ( half) to 18 mm thick marble/Granite
stone counters,vanities etc. over item no.1.8 & 1.11 including machine
108.1.64
polishing to edge to give high gloss finish etc complete as per design
approved by Engineer-in-Charge.
1.9.1 Granite work/Marble work metre 2,739.23 165.00 148.50 90.00 2,459.23 2,459.23 3,65,194.91 3,65,194.91
After complition 8.25 5.00 2,459.23 2,459.23 20,288.61 20,288.61
8.25 5.00 2,459.23 20,288.61
1.10
Extra for providing full (all round) edge moulding to 18 mm thick
marble/Granite stone counters,vanities etc. over item no.1.7 & 1.8
108.1.65
including machine polishing to edge to give high gloss finish etc
complete as per design approved by Engineer-in-Charge.
1.10.1 Granite work/Marble work metre 343.40 189.00 170.10 90.00 343.40 343.40 58,412.34 58,412.34
After complition 18.90 10.00 343.40 6,490.26
1.14
Providing and laying 25 mm thick kota sotne in flooring,steps,riser of of
steps & skirting with 130 mm wide-12 mm thick white marble strip as
per design for marble/stone work,over 25 thick base cement mortar
1:3(Cement:3 Coarse sand) and jointed with grey cement slurry mixed sqm 990.26 1,464.00 1,464.00
with pigment to march the sahde of the slabs/marble,araldite including
making nosing,rubbing and polishing complete as per design
Engineer-in- charge)
108.1.110 After fixing sqm 1,244.40 85.00 990.26 990.26 12,32,278.30 12,32,278.30
after rubbing 73.20 5.00 990.26 990.26 72,486.96 72,486.96
after rubbing 73.20 5.00 990.26 990.26 72,486.96 72,486.96
2.1 P.O.P.punning 73.20 5.00 990.26 72,486.96
435.00 1,02,660.00
P.O.P.cornice
Providing and applying two coats of approved external paint over one
coat of cement primer of approved brand on new surface to give an
even shade with exterior Emulsion paints of Asian paints make Apex-
Ultima or equivalent of approved shade over existing plastered wall and
110.1.13 other surfaces including preparing the surface, making good the damaged sqm 3,036.80 279.00 209.25 75.00 2,858.43 2,858.43 5,98,125.64 5,98,125.64
and rough surface smooth,minor repairs,sealing of cracks with cement slurry
and cleaning of doors,windows,ventilators,washing the sorrounding after
completion of work including cost of all materials,labours etc. complete as
per manufacturer's specification and as approved by the Engg-in-Charge.
1st Coat Paint 27.90 10.00 1,858.00 1,000.43 2,858.43 51,838.20 27,911.89 79,750.09
41.85 15.00 2,858.43 1,19,625.13
2.3.2 Texture paint
Primer sqm 27,000.00 54.60 35.00 27,000.00 0.00 27,000.00 14,74,199.98 14,74,199.98
1st Coat Paint sqm 27,000.00 31.20 20.00 27,000.00 0.00 27,000.00 8,42,399.99 8,42,399.99
sqm 27,000.00 31.20 20.00 27,000.00 0.00 27,000.00 8,42,399.99 8,42,399.99
Final Coat sqm 27,000.00 15.60 10.00 1,489.50 25,510.50 27,000.00 23,236.20 3,97,963.79 4,21,199.99
23.40 15.00 27,000.00 6,31,799.99
2.4.3 O.B.D.
Providing and applying Acrylic washable distemper paint two coats with
approved paint from Acrylic Tractor distemper of Asian Paints/ Bison
Acrylic Distemper of Berger Paints/ ICI Maxilite Acrylic distemper of ICI
Dulux make and approved shade over the new surface of ceiling. Item
includes following jobs. 1. Carrying out minor repairs including sealing cracks
with cement or putty as instructed by Engineer 2. Applying one coat of
acrylic putty of approved brand 4. Making the surface smooth by sand paper
110.1.8 etc. 5. Applying one coat of primer of suitable quality of approved brand. 6. sqm 15,430.00 123.00 123.00
Applying Two coats of Acrylic washable distemper. Item includes scaffolding;
making good the damaged and rough surfaces smooth; cleaning of dirt;
removal of old mortar drippings wherever required; preparation of surface;
cleaning doors, windows, ventilators, etc. after completion of work. Item also
includes cost of all materials, labour, tools and tackles etc. complete. All
material shall be applied as per manufacturer’s specification and as directed
by the Engineer-in-charge.
b.
For shutters of doors, windows & ventilators including providing and
112.1.2 fixing hinges/pivots and making provision for fixing of fittings whereever Kg 3,350.00 425.00 425.00
required including the cost of PVC/neoprene gasket required.
After fixing Kg 361.25 85.00 3,243.60 3,243.60 11,71,748.79 11,71,748.79
after hardware fixing Kg 21.25 5.00 3,243.60 3,243.60 68,926.40 68,926.40
after hardware fixing Kg 21.25 5.00 3,243.60 3,243.60 68,926.40 68,926.40
21.25 5.00 3,243.60 68,926.40
3.1
Providing and fixing glazing in aluminium door, window, ventilator
shutters and partitions etc. with PVC/neoprene gasket etc. complete as
per architectural drawings and the direction of Engg-in-Charge.(Cost
ofaluminium snap beading shall be paid in basic item).
a. With glass panes of 4.00 mm thickness (weight not less than 10.00
112.1.3 sqm 240.00 425.00 425.00
kg/sqm)
382.50 90.00 110.40 110.40 42,228.00 42,228.00
21.25 5.00 110.40 110.40 2,346.00 2,346.00
21.25 5.00 110.40 2,346.00
b. With glass panes of 5 mm thickness (weight not less than 13.75
112.1.4 sqm 1,313.00 614.00 614.00
kg/sqm)
sqm 552.60 90.00 1,312.89 1,312.89 7,25,500.51 7,25,500.51
30.70 5.00 1,312.89 1,312.89 40,305.72 40,305.72
4 MISCELLANEOUS 30.70 5.00 1,312.89 40,305.72
Additional Items
4.4
Providing and fixing of Daiken Gypsum ceiling tiles (PVC Top Layer and
Aluminium foil at the Back) without four sided protective white tape,
with hot dipped galvanized steel grid work, surface chemically cleaned
capping Pre-finished in baked polyester Paint, Main Tees of size 38 (H) x 24
mm every 1.2 M center to center, stitched cross Tee at0.6 M center to from
113.1.51 a gried of size 600x600 mm and suspending the gried from RCC roof using 3 SQM 1,438.37 755.00 755.00
mm GI rod, 6 mm nylon rawl plug and 6 mm j bolt at every 1200 mm
intervals. And laying "Daiken" Gypsum celling tiles of size 600x600x9 mm
over the formed gried. Light reflection of >85% .Flame spread Class A
(ASTM E-84). Water resistans tiles, grid thickness is 0.3 mm and used
butterfly hanger. Thermal Conductivity=0.045 k Cal/mh c.
4.7 Providing and Fixing Cylindrical Lock with Key S S Finish of approved
108.2.10A Each 525.00 496.00 446.40 90.00 378.00 378.00 1,68,739.20 1,68,739.20
make with necessary screws etc. complete
Relase part rate 24.80 5.00 378.00 378.00 9,374.40 9,374.40
Relase part rate 24.80 5.00 378.00 9,374.40
4.8 Providing and Fixing Cylindrical Lock Without key SS Finish of approved
108.2.10AA Each 467.00 467.00 420.30 90.00 404.00 404.00 1,69,801.20 1,69,801.20
make with necessary screws etc. complete
23.35 5.00 404.00 404.00 9,433.40 9,433.40
23.35 5.00 404.00 9,433.40
5.2
Providing and laying 22 mm thick Screeding under flooring with Cement
Concrete 1:2:4 (1cement : 2 coarse sand : 4 graded stone aggregate of
101.1.7.1 Sqm 1,800.00 236.00 236.00 984.15 984.15 2,32,258.22 2,32,258.22
12.5mm nominal size) including all accessories, formwork ,additives joint
etc complete in true lines and level as per direction of EIC.
101.1.7.1
5.3
Providing and applying on new Wood/steel work two or more coats of
48.4.99 Sqm 2,500.00 118.00 82.60 70.00 1,783.01 1,783.01 1,47,276.63 1,47,276.63
plastic emulsion paint of approved brand and manufacturer
12 26.6.11 Cutting of steel 16 mm dia including cost of manpower & T&P etc Nos. 632.00 25.00 25.00 100.00 632.00 632.00 15,800.00 15,800.00
13 26.6.12 Cutting of steel 20 mm dia including cost of manpower & T&P etc. Nos. 840.00 50.00 50.00 100.00 840.00 840.00 42,000.00 42,000.00
14 109.1.21A Groove making in granite stone work Rmt 800.00 160.00 160.00 100.00 796.32 796.32 1,27,411.20 1,27,411.20
15 Flat repair works including repairs in internal plaster,filling
chases,allignments of jams,repairs in vitrified tiles,grenite stone
113.9.16 Nos. 68.00 16,785.00 10,071.00 60.00 68.00 68.00 6,84,828.00 6,84,828.00
works,pop cornince,repairs of any kind in brickworks (full & half), ms
railing restorations etc
Nos. 2,517.75 15.00 68.00 68.00 1,71,207.00 1,71,207.00
Nos. 1,678.50 10.00 68.00 68.00 1,14,138.00 1,14,138.00
2,517.75 15.00 68.00 1,71,207.00
16 113.1.13.1 R.C.C Slab & granite counter Cutting for washbasin Nos. 390.00 550.00 550.00 100.00 40.00 40.00 22,000.00 22,000.00
17 113.12.63 Repair & alignment of Wooden Door frame Nos 100.00 300.00 300.00 100.00 60.00 60.00 18,000.00 18,000.00
18 115A.4 Disposal of Malba from site to outside of the premises Trip 850.00 400.00 400.00 100.00 625.00 225.00 850.00 2,50,000.00 90,000.00 3,40,000.00
19 115A.6 Disposal of Malba stock from floor to outside of the Building Trip 346.00 400.00 400.00 100.00 346.00 346.00 1,38,400.00 1,38,400.00
20 4A26.3B Supply of un-skilled labour @ 8 Hrs. Nos. 1,024.00 375.00 375.00 100.00 394.50 521.50 916.00 1,47,937.50 1,95,562.50 3,43,500.00
21 4A26.2.3 Supply of skilled labour @ 8 Hrs. Nos. 196.50 475.00 475.00 100.00 148.50 148.50 70,537.50 70,537.50
22
108.1.31A Dipcourse making in balcony at all height in all respect of works. Nos. 110.00 350.00 350.00 100.00 72.00 72.00 25,200.00 25,200.00
25 Providing & fixing of Mortise Handle (PL 304 AW)with Mortice Lock (PL
108.2.63A 304 S) set of DORSET as per approved sample in wooden door shutter Nos. 150.00 1,582.00 1,423.80 90.00 150.00 150.00 2,13,570.00 2,13,570.00
with necessary screws
Relase part rate 79.10 5.00 150.00 150.00 11,865.00 11,865.00
79.10 5.00 150.00 11,865.00
26
ex.ia Chipping & repairing of Balcony expention joints portion per nos 86.00 2,800.00 2,800.00 100.00 86.00 86.00 2,40,800.00 2,40,800.00
27
ex.ib Providing & fixing of Hilti Fastner in Door Frame per nos 2,250.00 65.00 65.00 100.00 2,220.00 2,220.00 1,44,300.00 1,44,300.00
31
ex.if : Applying Kitchen sink protaction works,(Kitchen) nos 91.00 265.00 265.00 100.00 91.00 91.00 24,115.00 24,115.00
32
ex.ii : Applying vetrified grouating and cleanning works sqm 2,528.99 210.00 84.00 40.00 2,429.54 2,429.54 2,04,081.11 2,04,081.11
20,57,320.00 35,45,746.00
19,74,395.39 34,02,827.26