0% found this document useful (0 votes)
83 views2 pages

Mechanical Work Daily Report

Uploaded by

ahmed HOSNY
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views2 pages

Mechanical Work Daily Report

Uploaded by

ahmed HOSNY
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Daily Report for Mechanical Work

Project Address Job Type


Super Hornet Clin04 AJAB Construction build
Work
Disipline TASK
Plumbing Prepare Angle and support for suspended water pipes
Install angle & support for suspened fire fihgting pipes in mechan
Install angle and suspened branche above the hanger door Fa
Fire fihgitng
Prepare fire fighting pipes (painting & threding) on the yard to be ready
Install Suspended Main Line of Fire Pipes for Sprinklers System in Bay
Install Main Supply Duct in Bay Area Facility-I
HVAC Install duct connections for exhaust fans in area above hanger doors
Prepare Duct connection with DOAS units
Placement and alignment of AFFF Tank at the site
Utilities Install connection of Fire Water Line with Clin01
Install PVC pipe connections for storm water pipes in facili

Crew
Type Number of Groups
Plumbing 2 Group
Fire Fighting 3 Group
HVAC 4 Group

Equipment
Type
Paint blower (by S/C)
Manlift (by S/C)
Chais blocks (by S/C)
Drillers
Forklift

Other Events
Type
Coordination with NBTC Need to open manh
Coordination with NBTC Need to remove test c
chanical Work
Job Type Prepared By Date
Construction build Ahmed Hassan - Mechanical Eng 6/23/2024

TASK Status
pport for suspended water pipes Doing
ned fire fihgting pipes in mechanical room Done
ranche above the hanger door Facility-I Doing
threding) on the yard to be ready for installation Doing
ipes for Sprinklers System in Bay Area Facility-I Doing
ly Duct in Bay Area Facility-I Doing
t fans in area above hanger doors in Facility-O Doing
nnection with DOAS units To Do
ment of AFFF Tank at the site Doing
of Fire Water Line with Clin01 Doing
ons for storm water pipes in facility I Doing

Number of Groups Hours


2 Group 8
3 Group 8
4 Group 8

nt
Qty Status Hours
1 In Use 4
5 In Use 7
1 In Use 4
2 In Use 3
1 In Use 2

nts
Description
Need to open manhole cover belong to NBTC near to Facility I
Need to remove test connection with Gate Valve for main fire line

You might also like