You are on page 1of 9

NDCT-2

Activity Racker column- Single racker column Racker column- pair Racker column- pair Racker column- pair Racker column- pair Racker column- Single racler column Racket beam Bottom Fixing- 1st pour segment Reinforcement-1st pour segment Upright fixing-1st pour segment Shuttering-1st pour segment Pouring -1st pour segment Bottom Fixing- 2nd pour segment Reinforcement-2nd pour segment Upright fixing- 2nd pour segment Shuttering- 2nd pour segment Pouring- 2nd pour segment Bottom Fixing- 3rd pour segment Reinforcement- 3rd pour segment Upright fixing- 3rd pour segment Shuttering- 3rd pour segment Pouring- 3rd pour segment Bottom Fixing-4th pour segment Reinforcement- 4th pour segment Upright fixing-4th pour segment Shuttering- 4th pour segment Pouring- 4th pour segment ( Racker beam complete) Shell 2nd lift EL Shell 3rd lift Shell 4th lift Shell 5th lift Shell 6th lift Jumpform & Platform erection Shell casting start with jump form Basin beam & pile head PCC for basin slab RCC for basin slab Grillage column pre-cast Pre cast yard Pre cast beams casting RCC for Hot Water duct column 1 RCC for Duct beams Misc item stair case etc CW channel RCC for Duct Erection of pre cast col / beam in Driveway( Ext/ Tower crane ) PVC fills erection Distribution pipes erection Nozzles erection Hot water pipe erection and hydro test Start Finish 25-Nov-11 25-Nov-11 26-Nov-11 26-Nov-11 27-Nov-11 27-Nov-11 28-Nov-11 28-Nov-11 29-Nov-11 29-Nov-11 30-Nov-11 30-Nov-11 5-Nov-11 9-Nov-11 11-Nov-11 14-Nov-11 16-Nov-11 9-Nov-11 13-Nov-11 16-Nov-11 19-Nov-11 21-Nov-11 14-Nov-11 19-Nov-11 23-Nov-11 26-Nov-11 28-Nov-11 20-Nov-11 25-Nov-11 28-Nov-11 1-Dec-11 3-Dec-11 18-Nov-11 29-Nov-11 10-Dec-11 21-Dec-11 6-Jan-12 20-Jan-12 12-Feb-12 14-Sep-11 19-Oct-11 3-Nov-11 17-Nov-11 18-Sep-11 25-Oct-11 6-Nov-11 26-Nov-11 10-Dec-11 14-Jan-12 19-Feb-12 2-Aug-12 8-Nov-11 11-Nov-11 13-Nov-11 15-Nov-11 12-Nov-11 15-Nov-11 18-Nov-11 20-Nov-11 18-Nov-11 22-Nov-11 25-Nov-11 27-Nov-11 24-Nov-11 27-Nov-11 30-Nov-11 2-Dec-11 28-Nov-11 9-Dec-11 20-Dec-11 5-Jan-12 17-Jan-12 7-Feb-12 11-Jun-12 28-Nov-11 13-Dec-11 18-Dec-11 16-Mar-12 18-Oct-11 22-May-12 4-Feb-12 24-Feb-12 9-Jan-12 8-Feb-12 19-Apr-12 17-Aug-12 5-Nov-11 6-Nov-11 7-Nov-11 8-Nov-11

Issues
PCTL Racker column completion need to be expedited Manpower planning Column shuttering is idle at site

Construction Lightning Protection scheme SEPCO

To be finalised

9-Nov-11

10-Nov-11

11-Nov-11

12-Nov-11

13-Nov-11

14-Nov-11

15-Nov-11

16-Nov-11

17-Nov-11

18-Nov-11

RING BEAM

19-Nov-11

20-Nov-11

21-Nov-11

22-Nov-11

23-Nov-11

24-Nov-11

25-Nov-11 26-Nov-11

27-Nov-11

28-Nov-11

Finish Date 8-Nov-11 11-Nov-11 13-Nov-11 11/15/2011 12-Nov-11 15-Nov-11 18-Nov-11 20-Nov-11 18-Nov-11 22-Nov-11 25-Nov-11 27-Nov-11 24-Nov-11 27-Nov-11 30-Nov-11 2-Dec-11

29-Nov-11 30-Nov-11

1-Dec-11

2-Dec-11

3-Dec-11

4-Dec-11

5-Dec-11

6-Dec-11

7-Dec-11

8-Dec-11

9-Dec-11

10-Dec-11

11-Dec-11

12-Dec-11

13-Dec-11 14-Dec-11

You might also like