Arbitration Application: Danieli vs. Mishra
Arbitration Application: Danieli vs. Mishra
AT HYDERABD
BETWEEN:
Danieli India Limited … Applicant
AND
RUNNING INDEX
AND
AND
AFFIDAVIT
The Parties:
Brief Facts:
5. The Applicant and the Respondent entered into contracts dated April 28,
2017 bearing numbers MDN/PUR/CG/5870004 for Phase I and
MDN/PUR/CG/5870005 for Phase II (hereinafter referred to as
“Contracts”) for setting up Single Stand Reversing 4-HI Wide Plate Hot
Rolling Mill for Rolling of Plates (Phase-I) and Shear, Leveler, Roller
Hearth Furnace, Roller Pressure Quench, Cooling Beds etc and its
Auxiliaries (Phase-II) at the premises of Respondent at Hyderabad. Copy
of the Contracts are appended herewith and marked as Annexure-P2.
6. That in terms of the Contracts, the Applicant had inter alia agreed to
supply, impart and deliver the requisite confidential, proprietary and
copyright protected engineering data, design, drawings, documents etc. in
respect of the plant, equipment and spares, which was within its scope of
work under the Contracts.
Clauses 17.10.4, 34.1 and 34.2 of the GCC are reproduced below for
reference:
10. In July 2023, it came to the notice of the Applicant that Respondent had
floated the Applicant’s drawings in the open market for procurement of
work rolls and other associated parts in tender bearing no.
MDN/PUR/58230007/ADVT/079/23-24 dated May 8, 2023 (“Tender”).
This Tender contained the Proprietary and Confidential Information of the
Applicant namely its drawings bearing numbers 8.827075.Z (Work Roll
Assembly), 7.240753.S (Work Roll-2 Sheets) and 6.342163.C (Work Roll
Operating Conditions Data Sheet) with respect to work rolls and other
associated parts (hereinafter collectively referred to as “Work Roll
Drawings”).
11. Despite an express declaration of confidentiality and the fact that the Work
Roll Drawings could not be reproduced without the written consent of
Applicant, these drawings which constitute Proprietary and Confidential
Information of Applicant were used and uploaded online by the
Respondent in an unauthorized and unlawful manner – to be viewed by the
public at large.
12. The Applicant was accordingly constrained to file a Petition under Section
9 of the Arbitration and Conciliation Act, 1996 before the Hon’ble
Additional Special Court in the Cadre of District Judge for Trial and
Disposal of Commercial Disputes at Hyderabad, City Civil Court,
Hyderabad for ad-interim orders restraining the Respondent from any
further disclosure or misuse or dissemination of the Proprietary and
Confidential Information of Applicant to any third party and for ad-interim
orders restraining the Respondent from using, uploading or sharing all
Proprietary and Confidential Information of the Applicant on any website,
online platform or any other public platform. On September 13, 2023, the
Hon’ble Court was pleased to grant an injunction restraining the
Respondent from disclosing the Proprietary and Confidential Information
of the Applicant to any third party or uploading or sharing the same in
breach of the Contracts. Copy of order passed by Additional Special Court
in the Cadre of District Judge for Trial and Disposal of Commercial
Disputes at Hyderabad, City Civil Court, Hyderabad is appended herewith
and marked as Annexure – P3.
14. Article 9 of the Contracts and Clause 40 of the GCC are reproduced below
for reference:
40.0 ARBITRATION
40.1 Any dispute(s) or difference(s) whatsoever arises under or out of or
in connection with this Contract, or in respect of any defined legal
relationship associated therewith or derived therefrom, the parties agree
resolve/settle the same by submitting that dispute to arbitration in
accordance with the International Centre for Alternative Dispute
Resolution (ICADR) Arbitration Rules 1996.
15. Thereafter, during the pendency of the aforesaid Petition under Section 9,
the Applicant invoked arbitration by sending a Notice of Arbitration dated
December 11, 2023 under Article 9 of the Contracts read with Clause 40
of the GCC to ICADR (and copied to the Respondent) requesting it to
provide details of the documents and information required to take further
steps in the arbitration. The Applicant has however, not received a response
to the notice from ICADR or the Respondent till date. Copy of the Notice
for Arbitration dated December 11, 2023 is appended herewith and marked
as Annexure – P4.
16. That the Applicant has additional claims totaling INR 97.3 Crore arising
out of the same Contracts. These includes INR 42.1 Crore towards supply
retention amounts, INR 4.2 Crore towards engineering payments upon
completion of contractual milestones, and INR 51 Crore towards extra
expenses due to the project prolongation.
17. The Respondent withheld the claim related to supply retention amounts.
These retention amounts are meant to be released upon the issuance of the
project Preliminary Acceptance Certificate (“PAC”) and Final Acceptance
Certificate (“FAC”). The PAC for the project was obtained in March 2022
with effective from December 2021. The Applicant has successfully
fulfilled all contractual obligations and was granted the FAC in February
2023.
18. On July 11, 2023, the Respondent communicated via email to the
Applicant, informing them of their intention to impose Liquidated
Damaged (“LD”) at a rate of 10% due to the delayed commissioning of the
Contracts. The Applicant, however, rejected the unilateral imposition of
LD and informed the Respondent that the delay in project completion was
not attributable to them and requested for waiver of the LD penalty.
Additionally, they urged the release of the withheld amount of INR 42.1
Crore related to the supply retention amounts.
19. The engineering invoices related to the PAC milestone were submitted for
claim in April 2022, and similarly, the invoices for the FAC milestone were
submitted in May 2022. In June 2022, the Applicant received a partial
amount against the Phase 1 PAC engineering invoice, while the remaining
balance of INR 4.2 Crore has been withheld by the Respondent since May
2022. Despite consistent follow-ups and reminder communications
regarding the release of these pending payments, the Respondent has
remained silent up to the present date.
20. The Applicant being a joint developer, drove this Contracts with special
efforts despite of various project challenges. These efforts were crucial to
recover lost time in the initial delay of civil & structural works by the
Respondent as well as to manage the site and project services during peak
COVID scenarios and other force majeure situations for successful
completion of the project. In view of the above, the Applicant incurred
additional expenses and absorbed an amount of INR 51 Crore during this
project completion.
21. Therefore, in light of the aforesaid facts and circumstances, the Applicant,
not being left with any alternative is constrained to invoke the jurisdiction
of this Hon’ble Court under the auspices of the Arbitration and
Conciliation Act, 1996, more specifically under Section 11(6)(c), seeking
appointment of a sole arbitrator for adjudication of the disputes between
the Parties.
22. That the disputes and differences between the Parties are covered by the
arbitration clause as contained in the Contracts. By reason of the facts
stated hereinabove, no part of the claim/dispute is barred by limitation.
23. That the Applicant has no other alternative but to approach this Hon’ble
Court by filing this application under Section 11 of the Arbitration and
Conciliation Act, 1996. Unless appropriate orders are made as prayed
herein, the Applicant will suffer irreparable loss, prejudice and injury.
24. The Applicant craves leave of this Hon’ble Court to submit a detailed claim
along with comprehensive documentation before the Arbitral Tribunal
when the matter will be referred for adjudication through arbitration by this
Hon’ble Court.
25. That the place of arbitration in terms of the Contracts is Telangana and the
parties have specifically agreed to the jurisdiction of courts in Telangana
and therefore, this Hon’ble Court has the jurisdiction to entertain the
present petition.
26. The Applicant states that the Applicant has not filed any other application
before any other Court praying for the same relief.
27. This application is made bonafide and for the ends of justice.
DEPONENT
VERIFICATION
I, R. Achuthan, authorized signatory of the Applicant Danieli India Limited, do
hereby verify that the contents of the foregoing Affidavit are true and correct to
the best of my knowledge as derived from the records of the Company. All legal
contentions are as per legal advice received.
DEPONENT
Date: ___. ___. 2024
Place:
APPENDIX-1
WRITTEN STATEMENT
The Parties:
1. The Applicant, Danieli India Limited, is a company incorporated under the
provisions of the Companies Act, 1956 having its registered office at
Technopolis, Block – BP, Plot – IV, 5th Floor, ‘B’ Wing, Sector V, Salt
Lake, Kolkata – 700091. The Applicant is represented by its authorized
signatory Mr. R. Achuthan, Son of Mr. K. Raman. Copy of the Board
Resolution dated November 17, 2022 is appended herewith and marked as
Annexure-P1.
Brief Facts:
4. The Applicant and the Respondent entered into contracts dated April 28,
2017 bearing numbers MDN/PUR/CG/5870004 for Phase I and
MDN/PUR/CG/5870005 for Phase II (hereinafter referred to as
“Contracts”) for setting up Single Stand Reversing 4-HI Wide Plate Hot
Rolling Mill for Rolling of Plates (Phase-I) and Shear, Leveler, Roller
Hearth Furnace, Roller Pressure Quench, Cooling Beds etc and its
Auxiliaries (Phase-II) at the premises of Respondent at Hyderabad. Copy
of the Contracts are appended herewith and marked as Annexure-P2.
5. That in terms of the Contracts, the Applicant had inter alia agreed to
supply, impart and deliver the requisite confidential, proprietary and
copyright protected engineering data, design, drawings, documents etc. in
respect of the plant, equipment and spares, which was within its scope of
work under the Contracts.
Clauses 17.10.4, 34.1 and 34.2 of the GCC are reproduced below for
reference:
9. In July 2023, it came to the notice of the Applicant that Respondent had
floated the Applicant’s drawings in the open market for procurement of
work rolls and other associated parts in tender bearing no.
MDN/PUR/58230007/ADVT/079/23-24 dated May 8, 2023 (“Tender”).
This Tender contained the Proprietary and Confidential Information of the
Applicant namely its drawings bearing numbers 8.827075.Z (Work Roll
Assembly), 7.240753.S (Work Roll-2 Sheets) and 6.342163.C (Work Roll
Operating Conditions Data Sheet) with respect to work rolls and other
associated parts (hereinafter collectively referred to as “Work Roll
Drawings”).
10. Despite an express declaration of confidentiality and the fact that the Work
Roll Drawings could not be reproduced without the written consent of
Applicant, these drawings which constitute Proprietary and Confidential
Information of Applicant were used and uploaded online by the
Respondent in an unauthorized and unlawful manner – to be viewed by the
public at large.
11. The Applicant was accordingly constrained to file a Petition under Section
9 of the Arbitration and Conciliation Act, 1996 before the Hon’ble
Additional Special Court in the Cadre of District Judge for Trial and
Disposal of Commercial Disputes at Hyderabad, City Civil Court,
Hyderabad for ad-interim orders restraining the Respondent from any
further disclosure or misuse or dissemination of the Proprietary and
Confidential Information of Applicant to any third party and for ad-interim
orders restraining the Respondent from using, uploading or sharing all
Proprietary and Confidential Information of the Applicant on any website,
online platform or any other public platform. On September 13, 2023, the
Hon’ble Court was pleased to grant an injunction restraining the
Respondent from disclosing the Proprietary and Confidential Information
of the Applicant to any third party or uploading or sharing the same in
breach of the Contracts. Copy of order passed by Additional Special Court
in the Cadre of District Judge for Trial and Disposal of Commercial
Disputes at Hyderabad, City Civil Court, Hyderabad is appended herewith
and marked as Annexure – P3.
13. Article 9 of the Contracts and Clause 40 of the GCC are reproduced below
for reference:
40.0 ARBITRATION
40.1 Any dispute(s) or difference(s) whatsoever arises under or out of or
in connection with this Contract, or in respect of any defined legal
relationship associated therewith or derived therefrom, the parties agree
resolve/settle the same by submitting that dispute to arbitration in
accordance with the International Centre for Alternative Dispute
Resolution (ICADR) Arbitration Rules 1996.
Work under the contract shall be continued by the contractor during the
arbitration proceedings, unless otherwise directed in writing by the
Purchaser or unless the matter is such that the work cannot possibly be
continued until the decision of the arbitrators is obtained, and save as those
which are otherwise expressly provided in the Contract, no payment due
or payable by the purchaser shall be withheld on account of such
arbitration proceedings, unless it is the subject matter or one of the subject
matter thereof.
14. Thereafter, during the pendency of the aforesaid Petition under Section 9,
the Applicant invoked arbitration by sending a Notice of Arbitration dated
December 11, 2023 under Article 9 of the Contracts read with Clause 40
of the GCC to ICADR (and copied to the Respondent) requesting it to
provide details of the documents and information required to take further
steps in the arbitration. The Applicant has however, not received a response
to the notice from ICADR or the Respondent till date. Copy of the Notice
for Arbitration dated December 11, 2023 is appended herewith and marked
as Annexure – P4.
15. That the Applicant has additional claims totaling INR 97.3 Crore arising
out of the same Contracts. These includes INR 42.1 Crore towards supply
retention amounts, INR 4.2 Crore towards engineering payments upon
completion of contractual milestones, and INR 51 Crore towards extra
expenses due to the project prolongation.
16. The Respondent withheld the claim related to supply retention amounts.
These retention amounts are meant to be released upon the issuance of the
project Preliminary Acceptance Certificate (“PAC”) and Final Acceptance
Certificate (“FAC”). The PAC for the project was obtained in March 2022
with effective from December 2021. The Applicant has successfully
fulfilled all contractual obligations and was granted the FAC in February
2023.
17. On July 11, 2023, the Respondent communicated via email to the
Applicant, informing them of their intention to impose Liquidated
Damaged (“LD”) at a rate of 10% due to the delayed commissioning of the
Contracts. The Applicant, however, rejected the unilateral imposition of
LD and informed the Respondent that the delay in project completion was
not attributable to them and requested for waiver of the LD penalty.
Additionally, they urged the release of the withheld amount of INR 42.1
Crore related to the supply retention amounts.
18. The engineering invoices related to the PAC milestone were submitted for
claim in April 2022, and similarly, the invoices for the FAC milestone were
submitted in May 2022. In June 2022, the Applicant received a partial
amount against the Phase 1 PAC engineering invoice, while the remaining
balance of INR 4.2 Crore has been withheld by the Respondent since May
2022. Despite consistent follow-ups and reminder communications
regarding the release of these pending payments, the Respondent has
remained silent up to the present date.
19. The Applicant being a joint developer, drove this Contracts with special
efforts despite of various project challenges. These efforts were crucial to
recover lost time in the initial delay of civil & structural works by the
Respondent as well as to manage the site and project services during peak
COVID scenarios and other force majeure situations for successful
completion of the project. In view of the above, the Applicant incurred
additional expenses and absorbed an amount of INR 51 Crore during this
project completion.
20. Therefore, in light of the aforesaid facts and circumstances, the Applicant,
not being left with any alternative is constrained to invoke the jurisdiction
of this Hon’ble Court under the auspices of the Arbitration and
Conciliation Act, 1996, more specifically under Section 11(6)(c), seeking
appointment of a sole arbitrator for adjudication of the disputes between
the Parties.
21. That the disputes and differences between the Parties are covered by the
arbitration clause as contained in the Contracts. By reason of the facts
stated hereinabove, no part of the claim/dispute is barred by limitation.
22. That the Applicant has no other alternative but to approach this Hon’ble
Court by filing this application under Section 11 of the Arbitration and
Conciliation Act, 1996. Unless appropriate orders are made as prayed
herein, the Applicant will suffer irreparable loss, prejudice and injury.
23. The Applicant craves leave of this Hon’ble Court to submit a detailed claim
along with comprehensive documentation before the Arbitral Tribunal
when the matter will be referred for adjudication through arbitration by this
Hon’ble Court.
24. That the place of arbitration in terms of the Contracts is Telangana and the
parties have specifically agreed to the jurisdiction of courts in Telangana
and therefore, this Hon’ble Court has the jurisdiction to entertain the
present petition.
25. The Applicant states that the Applicant has not filed any other application
before any other Court praying for the same relief.
26. This application is made bonafide and for the ends of justice.
Valuation of the subject matter:
The value of this Petition for the purpose of jurisdiction is fixed as Rs.
__________/-. However, fixed amount of Rs . 2500/- as prescribed under the
law has been affixed on this Petition.
PRAYER:
It is therefore most respectfully prayed before this Hon’ble Court may be
graciously pleased to:
Applicant
VERIFICATION
AT HYDERABD
AND
VERIFICATION AFFIDAVIT
3. That the contents of the accompanying application are true and correct to
the best of my knowledge and nothing material has been concealed
therefrom.
DEPONENT
VERIFICATION:
I the above-named Deponent do hereby solemnly affirm and verify that the
contents of the above Para Nos 1 to 3 are true and correct to the best of my
knowledge and nothing material has been concealed therefrom.
DEPONENT
Advocate
APPENDIX - II
AND
For the reasons stated in the accompanying affidavit, it is hereby prayed that this
Hon’ble Court may be pleased to a) intervene in the matter and appoint a sole
arbitrator to adjudicate the disputes between the Parties b) pass such further order
(s) and this Hon’ble Court may deems fit, just and proper in the interest of justice.
Date:
Hyderabad Counsel for the Applicant