Burn Pit Sizing Calculation Guide

The document outlines the calculations for sizing a burn pit, including the net heat of vaporization and combustion, flow rates, and required dimensions. It provides detailed input data and results for the burn pit area, diameter, and depth based on specific equations and references. The calculations utilize both British and SI units and highlight discrepancies in existing equations, opting for Exxon Mobile Design Practice as a reference.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views1 page

Burn Pit Sizing Calculation Guide

The document outlines the calculations for sizing a burn pit, including the net heat of vaporization and combustion, flow rates, and required dimensions. It provides detailed input data and results for the burn pit area, diameter, and depth based on specific equations and references. The calculations utilize both British and SI units and highlight discrepancies in existing equations, opting for Exxon Mobile Design Practice as a reference.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Contract No.

:
SJ-CN-SC-99-0060
Document No.: Page 3 Of 3
Burn Pit Sizing Calculation For Receiving Area and Manifolds
Input Data Input Data
Result Result
Reference : IPS-E-PR-460 and Exxon dp15e
British Unit SI Unit
1st STAGE : Vꝏ Calculation
Net Heat Of Vaporization Qv 696 Btu/lb 1614 KJ/Kg
Net Heat Of Combustion LHV 18,490 Btu/lb 43,000 kJ/Kg
Vꝏ = 0.003(LHV/Qv ) "British"
Linear Regression Rate Of Liquid 0.0797 0.0338
Vꝏ= 0.00127 (LHV/Qv) "Metric"
2nd STAGE : Area Calculation (A)
Incoming Liquid Flow WL 64571 lb/hr 8.135 Kg/s
Liquid Density ρL 54.81 lb/ft3 877.8 Kg/m3
A= 0.2(WL/(ρL X Vꝏ)) "British"
Burn Pit Area 5910.14 ft2
A=1001(WL/(ρL X Vꝏ)) "Metric" 548.28 m2
Burn Pit Diameter D 86.77 ft 26.43 m
Burn Pit Diameter D 26.4 m 26.4 m
3rd STAGE : Depth of Burn pit Calculation (HB)
Water Flow Rate 421.4 ft3/hr 11.93 m3/hr
Required Volume For 30 Min Water Release 211 ft3 5.97 m3/hr
Required Height For 30 min Water Release Hw (Calculated) 0.04 ft 0.011 m
Water Height In Pool Of Burn Pit (Max of 1 ft (0.3 m) and Hw) Hw (selected) 1.00 ft 0.3 m
HC Flow Rate 755.8 ft3/hr 21.43 m3/hr
Required Volume For 30 Min HC Liquid Release 378 ft3 10.72 m3
Required Height For 30 min HC Liquid Release HL (Calculated) 0.06 ft 0.020 m
HC Liquid Height (Min of 6.65 ft (2 m) and HL) HL (Selected) 0.06 ft 0.020 m
Calculated Depth Of Burn Pit (HB = HL + Hw + 1.5 ft (0.45 m)) HB (Calculated) 2.82 ft 0.846 m
Real Depth of burn pit (MAX OF 4 ft (1.2 m) OR HB) L (Selected) 5.00 ft 1.5 m
Real Depth of burn pit L 1.5 m 1.5 m
Result
Burn pit dimension D 26.4 m 26.4 m
Burn pit Height L 1.5 m 1.5 m
Burn Pit Volume V 836.8 m3 836.8 m3

Note : All input data are according to Project material balance.


Some equations in IPS-E-PR-460 are incorrect . For example equation 7 is not reasonable . Therefore the Exxon Mobile Design Practice dp15e is used as
reference of this calculation (Attachment).