STRUCTURAL INSPECTION REQUEST
Plot Number Building Permit No.
Consultant
Contractor
Standard Inspection
Application Details Late Inspection
(Tick Appropriate Box) Holiday Inspection
3rd inspection
Structural Member @ Building Floor No. Grid No.
Submission Details Initial Submission
(Tick Appropriate Box) Re-submission
Notes:
• Contractor engineer and consultant engineer must be at site at the time of Inspection.
• The Contractor should cast the inspected member within one week from the date of approval, if this is not completed within
the required time frame then a further inspection will need to take place.
• Passenger Hoist shall not exceed 4 floors.
• The below documents must be available at site at the time of inspection:
1. Scaffolding Certificate from third party
2. Confirmation Letter from soil laboratory in the foundation stage
3. Piling/Shoring Completion Certificate (if applicable)
4. Ready mixed concrete plants conformity certificate from DM
5. Cubes and steel tests results along with Confirmation Letter stamped and signed by consultant
CONTRACTOR & CONSULTANT
• We hereby certify that the information, data and documents provided with this application are true, genuine and correct to the
best of my knowledge. In case of default/failure to comply with any of the aforesaid conditions or the documents submitted by
us is found false/forged, our application will be rejected forfeiting any applicable fees paid.
• We hereby undertake that the above inspection and the vertical elements are checked and found to be consistent with the
zoning affairs approved drawings, specifications, building construction workmanship and industrial safety.
Contractor Consultant
Contact Person Contact Person
Contact No. Contact No.
Date Date
Signature & Signature &
Stamp Stamp
PO Box 478844, Dubai, UAE
T +971 800-4-DDA (332)
F +971 4 427 2449
ZA-DC-F-10 Issue 10 dda.gov.ae
R STRUCTURAL INSPECTION SLAB CHECKLIST
Project Name Date:
Plot No.
Location
Consultant Contractor
SECTION S.NO. ELEMENTS TO BE CHECKED CONSULTANT CONTRACTOR
NOT NOT
OK N/A OK N/A
GENERAL OK OK
1 Setbacks/coordinates
2 Levels
3 Column layout
4 Safety
5 Access
6 Scaffolding safety certificate
7 Last cube test results
8 Cleaning
9 Valid building permit
SOLID
10 Dimensions
11 Shutter
12 Covers
13 Reinforcement (main and distribution bars)
14A Extra bars: length
14B Extra bars: diameter
14C Extra bars: cover
15 Starter bars
16 Connection details
HOURDI
17 Dimension
18 Shutter
19 Cover (i.e. Ribs/blocks)
20 Reinforcement
21 Starter bars
22 Connection details
POST TENSION
23 Dimension
24 Cover
25 Reinforcement
26A Strand: details
PO Box 478844, Dubai, UAE
T +971 800-4-DDA (332)
F +971 4 427 2449
ZA-DC-F-12 Issue 4, Rev 1, Dated 19/12/2018 Page 1 of 2 dda.gov.ae
26B Strand: number
26C Strand: spacing
26D Strand: alignment
26E Strand: chairs
BEAM
27 Dimension
28 Cover
29 Reinforcement
30 Reinforcement layers
31 Overlap
32 Stirrup spacing
COLUMN
33 Dimension
34 Cover
35 Reinforcement
36 Overlap length
37 Connection details
38 Planted/floating columns
39 Punching shear
40 Stirrup spacing
REVIEWER’S COMMENT(S)
CONTRACTOR CONSULTANT
NAME STAMP NAME STAMP
DESIGNATION DESIGNATION
SIGNATURE SIGNATURE
DATE DATE
PO Box 478844, Dubai, UAE
T +971 800-4-DDA (332)
F +971 4 427 2449
ZA-DC-F-12 Issue 4, Rev 1, Dated 19/12/2018 Page 2 of 2 dda.gov.ae