Personal Note Book 04
Personal Note Book 04
fffgfgbfbvffgfgfg
(Construction) :
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
# :
:
:
:
:
:
#
:
:
:
:
#
:
(BIM) :
:
@RayenReza.Ibrahim Page : 1
: 3D
(IOT) :
: :
:
:
:
:
: :
:
:
:
a)
b)
-
-
B. -
-
@RayenReza.Ibrahim Page : 2
:
=================
• - -
@RayenReza.Ibrahim Page : 3
•
# ৪ ।
-
MDB, DB SB
DB, SB
-
, ,
@RayenReza.Ibrahim Page : 4
- ,
-
,
# -
Unit Converter –
Rebar Weight –
Column capacity –
Footing Design –
SPT to Bearing – . .
Electric Bill – ( )
Shutter Weight –
Pile Estimate –
# ,
@RayenReza.Ibrahim Page : 5
ISO = International Organization for Standardization, Swizerland.
#
=============================================
# /
====================
#
# ( )/
, ,
, ,
#
,
# -৭
# , - ,
,
, , - ,
, ,
# -
,
, ( ) ,
,
, , ,
# / /
, ,
@RayenReza.Ibrahim Page : 6
# - ,
# ,
- ,
, ,
, ,
,
,
#
a.
b. ,
c. , ,
( ) ,
# -
========================
# / : ,
# ( ): ,
# - / - ( ): -
a.
b. ( - , , , , , , , , ,
)
c. ( , )
d. ( ) ( )
e. ( )
f.
g. , ,
@RayenReza.Ibrahim Page : 7
,
#
================
# /
, ,
,
# ( /
-
( ),
, , ,
# :
================================
# - - :
, , ,
# : .
, , , ,
, ,
, ,
,
, , ,
.
,
# :
@RayenReza.Ibrahim Page : 8
, ,
,
/
OSHA
/
. ,
,
,
,
,
,
, /
,
/ ,
OSHA
# - : -
,
,
, , , , ,
, , , ,
: ,
, , , , ,
, , , ,
! !
# :
a.
b. -
c. ( )
@RayenReza.Ibrahim Page : 9
d. , , ০০০ -
e. ০ -
f. -
g.
h. -
i. - ৪( )
j. -
k.
l.
m. - ,ঐ
n. - ০%
o.
p.
q. , - , - %
# :
150 6
2.75
9.5
2.4
2.75
5
1.8
2
1.8
2.2
3
2.4
2.5 X5
1 , 1.5 ,
2
250
150
( ) 2.2
- -
@RayenReza.Ibrahim Page : 10
(Building) :
,
, , ,
, , , ,
, , ,
,
।
1.
2.
# - - : -
# - : , ,
# :
-
200
,
, , , -
,
@RayenReza.Ibrahim Page : 11
# :
200 100
R.C.C.
-
-
,
, R.C.C
a) -
-
b) -
c)
d)
e) ঐ
f) - -
g)
(Foundation) :
:
@RayenReza.Ibrahim Page : 12
:
:
:
(Function of foundation) :
-
a) (Reduction of load intensity) :
d) (Lateral stability) :
- -
@RayenReza.Ibrahim Page : 13
-
-
-
-
a) -
b)
c)
a)
b) -
c)
d)
:
-
a)
b)
c) 1.5 1
d)
e) 10
- -
-
a) 5.5 4.9
b) 50
@RayenReza.Ibrahim Page : 14
-
15
90
-
-
a)
b) - -
c) 1 :2:4
d)
e)
f) 60 90 -
1.
2.
3.
4.
@RayenReza.Ibrahim Page : 15
5. -
6. -
a)
b) -
a)
1.
2.
3. -
4. - -
5.
: :
1.
2.
a) :
b) :
-
-
-
@RayenReza.Ibrahim Page : 16
–
a) (Deep Foundation)
b) (Shallow Foundation)
A. Deep Foundation) -
(Pile Foundation)
(Cofferdam)
(Pier Foundation)
1. Pile Foundation) :
(Caisson) :
3. (Cofferdam) :
(Pier Foundation) :
B. (Shallow Foundation) :
-
(Spread Footing)
(Combined Footing)
a)
b)
@RayenReza.Ibrahim Page : 17
c)
d)
-
-
-
-
-
15
1:3:6 1:4:8
3 15
3 - 4.50 20
4.50 - 6 25
6 30
1. (Pile) :
― ‖
-
-
(Trestle-bridge- -
@RayenReza.Ibrahim Page : 18
# -
-
-
b. —
1. (Timber pile )
2. (Concrete pile)
3. (Composite pile)
4. (Steel pile)
5. (Sand pile)
@RayenReza.Ibrahim Page : 19
- -
1) Raymond pile)
2) - (Mac-arthur case pile )
3) (Monotube pile)
4) (Button bottom pile)
5) (Swage pile)
- -
1) (Simplex pile)
2) (Franki pile)
3) (Vibro pile)
4) (Pedestal pile)
1) - (H-Pile)
2) (Pipe pile)
3) - (Screw pile)
4) (Disc Pile)
5) (Sheet pile)
(Method of construction) : —
1. - (Pre-cast pile)
2. - - (Cast-in-situ pile)
(a)
(b)
(c)
@RayenReza.Ibrahim Page : 20
(d) -
(e)
(f) -
-
(g)
==========================
(Wood pile) :
7.25- 30 50 30
50 15 18 20
-
(Composite pile) :
-
- -
-
1. -
2.
3.
4.
5.
@RayenReza.Ibrahim Page : 21
6.
1.
2.
3.
4.
5.
(Sand pile) :
20 40
1
2 5
(Advantages) :
-
(Disadvantages) :
(Concrete pile) :
1) -
2)
@RayenReza.Ibrahim Page : 22
A. - -
৪ ০
-
- ৪
- - - -
- -
-
-
- -
-
@RayenReza.Ibrahim Page : 23
- -
- -
====================
- - (Cased cast in situ concrete pile) :
-
1. (Raymond pile)
2. - (Mac-arthur cased pile)
3. (Monotube pile)
4. (Swage pile)
5. (Button bottom pile)
(Raymond pile) : - - ৪০ ০
০ ০
(Swage pile) :
-
(Monotube pile) :
@RayenReza.Ibrahim Page : 24
- - (Uncased cast-in-situ pile) :
1. (Simplex pile)
2. (Franki pile)
3. (Vibro pile)
4. (Pedestal pile)
(Simplex pile) : ০
(Franki pile) : -
০ ০
-
(Vibro pile) :
০
-
-
০৭
==============
-
-
@RayenReza.Ibrahim Page : 25
- - - :-
========================
- - -
1) - -
2)
3)
- -
1) -
2)
3)
(Screw pile) : ০ -
৪ ০
(Disc pile) :
1.
2.
3. -
4.
@RayenReza.Ibrahim Page : 26
6
4 -
1)
2)
3)
4)
:-
@RayenReza.Ibrahim Page : 27
10 35
10-15 40
12 30 x 30
15 36 x 36
18 40 x 40
21 46 x 46
40 20
1.
৪
2.
3. -
4.
(b) -
- -
@RayenReza.Ibrahim Page : 28
-
(Loads on piles) : -
-
(Dynamic formula)
(Static formula)
- -
-
- -
-
1.
2.
@RayenReza.Ibrahim Page : 29
3.
4.
5. .5
6.
7. -
-
1.
2.
3.
4.
5.
6.
-
1. (Cyclic load method)
2. (Constant penetration method).
3. (Housel's method)
4. (Equilibrium method)
(Pile driving) :
-
1. (Pile frames)
2. (Pile hammers)
3. (Leads)
4. (Winches)
5. (Miscellaneous equipment)
(Pile frame) :
(Pile hammer) : —
a. (Drop hammer)
b. (Single acting steam hammer)
c. (Double acting steam hammer)
d. (Diesel hammer)
(Leads) : -
(Winches) :
-
@RayenReza.Ibrahim Page : 30
(Pile driving methods) : -
1) (By drop hammer)
2) (By steam hammer)
a) (Single acting)
b) - (Double acting)
c) (Differential acting)
3) (By water jet)
4)
(Drop hammer) : - - - -
(Steam hammer) :
- -
(Stroke length)
-
a) (Compact)
b)
c)
d)
e)
(Water jet) :
(Boring) :
-
@RayenReza.Ibrahim Page : 31
0.5
.5
-
===================
1.
2.
3.
4.
5.
6. 1:2:4/1:3:6
7.
:
=================
# Cutter
‘ ‘
‘ ‘ ‘
8 16
Tre
2 6 ‘
C 6 18
Clear
@RayenReza.Ibrahim Page : 32
6
-
or 3.5 to 7.5 Cm o
# Maximum Tolerance:
- :
20 1/1.5
# Casing Driving : 18 20
# Pile Inclination :
Be
@RayenReza.Ibrahim Page : 33
।
Sodium-activated bentonite
Sand conten
In General 4-6 1000 40-60 15
# Workers Safety :
- (Bore pile) :
===========================================
# Wash : 30 45
10/15
15/20
10/15
# Reinforcement Checking :
=====================
# Shape Ring : 1.5 5
600mm/ 2 Feet, ‘
- - - - Inch.
# Core Dia :
Covering 75mm
420mm!
@RayenReza.Ibrahim Page : 34
# Rebar to Rebar Distance :
# Welding : ‖
2 N
# Pile Hook :
-) 2.4 8
-) 1.8 6
2 0.6
-) 0.3 1
1.8-0.3] = 1.5 5
(Caisson) :
a)
b)
a)
b)
@RayenReza.Ibrahim Page : 35
c)
d)
। । -
a)
b)
c)
d)
# , -
(Single circular)
(Twin hexagonal)
(Twin circular)
(Twin octagonal)
(Dumb well)
(Rectangular)
- (Double-D)
# (Curb) -
(Cutting edge) ,
৪
- , -
-
-
. ৪.
,
(Verticall)
-
-
@RayenReza.Ibrahim Page : 36
2. (Pneumatic caison) : ,
, ,
,
,
,
,
, ,
,
,
,
, ,
, ,
, ,
" " , ,
, ,
,
, ,
, , ,
, , ,
, ,
, , ,
,
,
, , , ,
,
,
, , ,
,
, ,
, ,
,
, ,
,
, ,
@RayenReza.Ibrahim Page : 37
,
# :
( ) 3-7
, 3-7
# :
,
,
,
haunches .
(Cofferdam) :
-
@RayenReza.Ibrahim Page : 38
a) (Earthen coffer dam)
b) - (Rock fill coffer dam)
c) (Sand bag coffer dam)
d) (Single walled coffer dam)
e) (Double walled coffer dam)
f) - (Rock-Filled crib coffer dam)
g) Concrete coffer dam)
h) Cellular coffer dam)
i) (Cantilever sheet pile coffer dam)
j) (Braced coffer dam)
k) Suspended coffer dam)
-
-
-
@RayenReza.Ibrahim Page : 39
-
-
-
@RayenReza.Ibrahim Page : 40
e) (Double walled coffer dam) :
@RayenReza.Ibrahim Page : 41
h) (Cellular coffer dam) :
@RayenReza.Ibrahim Page : 42
4. (Pier Foundation) :
(Pier Foundation)
===================
(Drilled Pier) :
(Caisson Pier) :
@RayenReza.Ibrahim Page : 43
:
1. (Spread Footing) :
,
, ,
-
, RCC
, ,
# -
(a) (Strip footing)
1) (Simple footing)
2) (Stepped footing)
(b) (Reinforced concrete footing)
(c) (Isolated or pad footing)
1) .
2) .
3) .
(d) (Eccentrically loaded footing)
1) (Offsetting the footing)
2) (Strap footing)
(e) (Grillage foundation)
1) (Steel grillage)
2) (Timber grillage)
(f) (Inverted arch footing)
@RayenReza.Ibrahim Page : 44
(a) (Strip footing) : ,
০ ,
( - ) ০ (
)
# , -
, -
( )
# , -
1) (Simple footing)
2) (Stepped footing)
1) : , - , ,
2) :
, ,
# , -
1) (Square footing of uniform thickness)
2) (Sloped square footing)
3) (Stepped square footing)
4) (Rectangular footing of uniform thickness)
5) (Sloped rectangular footing)
# -
-
@RayenReza.Ibrahim Page : 45
-
-
# ' , -
1. (Steel grillage)
2. (Timber grillage)
, -
০
০ -
# , ০
,
,
•
Steel column
@RayenReza.Ibrahim Page : 46
- ০
৪ ০
০ , (b = ০.৭ d)
# :
- ,
,
,
# :
,
,
,
,
,
3 ksi < f'c < 4 ksi , 4 ksi < f'c < 8 ksi
,
# :
, :-
A=
, Qt q
# : , :-
,
,
,
footings .
- ,
@RayenReza.Ibrahim Page : 47
,
, .
# :
,
,
(Combined Footing) :
(Combined
@RayenReza.Ibrahim Page : 48
3) (Continuous footing) :
(Reinforcement) :
1. -
2.
3.
4. - -
@RayenReza.Ibrahim Page : 49
(Strap Footing) :
(Cantilever Footing) :
===========
@RayenReza.Ibrahim Page : 50
=============
- -
@RayenReza.Ibrahim Page : 51
:
# :
(Grade Beam) :
1. -
2. - -
@RayenReza.Ibrahim Page : 52
*
৪ ৪ ৪
================
@RayenReza.Ibrahim Page : 53
(Soling) :
:
- -
―80- ―90
a) (Brick Soling)
b)
(Brick Soling) :
a) (Flat Soling)
b) - (Herring-Bone Bond Soling)
c) (Diagonal Soling)
-
@RayenReza.Ibrahim Page : 54
(Stone Soling) :
@RayenReza.Ibrahim Page : 55
(Single Layer Stone Soling) :
1)
2)
3)
a) :
b)
c)
d)
e)
f)
@RayenReza.Ibrahim Page : 56
(Column) :
-
- (Unsupported length) -
-
-
—
a) (Short column)
b) (Long column)
a) (Short column) :
b) (Long column) :
80
# (Slenderness ratio) : - -
SR = =
r= √ , Imin = Ix + Iy Iz -
@RayenReza.Ibrahim Page : 57
-
a) (Tied column)
b) (Spiral column )
c) (Composite column)
d) (Combination column )
a) (Tied column) : -
-
-
b) (Spiral column) :
c) (Composite column) : -
d) (Combination column) :
# (Pipe column) :
# (State the minimum size and minimum number of rod required for tied
column and sprial column) :
৪
(b)
(i)
(ii)
(iii)
@RayenReza.Ibrahim Page : 58
(Arrangement of tie rod in column) :
‘
‘
‗ ‘
#
a)
b)
c)
d)
e)
f)
৭ ৪
@RayenReza.Ibrahim Page : 59
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
–
-
‘ ‘
ACI ‗ ‘
10 2 (4.5+4.5+1)
a) ,
3/4/5
b) ,
6/7/8
(Beam) :
@RayenReza.Ibrahim Page : 60
# ।
==============
(Concrete Beams) :
(i) (Reinforced Concrete Beams) :
(i) - (I-Beams) : -
(ii) - (H-Beams) : -
(Wooden Beams) :
(i) (Solid Wooden Beams) : -
2. :
a) (Simply supported beam) :
-
b) (Cantilever beam) :
c) (Overhanging beam)
d) (Fixed beam) :
e) (Continuous beam) :
3 :
a) (Girder Beams) :
b) (Lintel Beams) :
c) (Floor Beams) :
@RayenReza.Ibrahim Page : 61
4 :
a) Span Beams) : (Short
5.
a) : ঐ
b)
:
a) (Rectangular Beam) :
b) (T Beam) :
ঐ
- - - - (Flanged)
-
-
- -
-
-
-
#
1. ∑H = 0
2. ∑
3. M=0
CC 3 -
a)
b)
c)
@RayenReza.Ibrahim Page : 62
(Types of support) :
a) (Simple or roller)
b) (Hinged)
c) (Fixed)
a) (Simple support) : -
b) - (Rotation) -
-
c)
a)
b)
c)
d)
-
e)
a) (Dead load) :
b) Lv L
c) (Environmental load) : -
@RayenReza.Ibrahim Page : 63
AI
৪
-
5 (Pouring of Concrete) :
৪
@RayenReza.Ibrahim Page : 64
:
:
9.
:
:
‘
-
a) ,
3/4/5
b) ,
6/7/8
a)
b)
c)
(Slab) :
(Floor)
@RayenReza.Ibrahim Page : 65
a) -
1)
2)
3) ( )
1. : , -
100 500 , ,
, ,
,
:
, ,
, 21
, ,
2. RCC
( ): " "
- -
[
, , , ,
, , ,
b) :-
- :
: 800
400 , ,
@RayenReza.Ibrahim Page : 66
: ,
2. : , -
:
,
,
-
-
#
================
a) - —
1) (One-way solid slab)
(i)
(ii)
(iii)
2) (One way ribbed slab)
3) (Pre-
2. (Two way -
1) (Two-way solid slab)
(i)
(ii)
2) (Two-way ribbed slab)
3) (Beamless slab)
(i)
(ii)
(iii)
# -
a) (One-way slab)
b) (Two-way slab)
c) (Flat slab)
@RayenReza.Ibrahim Page : 67
d) (Ribbed slab)
e)
- -
‗ ‘ ‗ ‘
c) (Flat slab) :
-
(i)
(ii)
@RayenReza.Ibrahim Page : 68
-
ঐ
(ii) (Column capital) :
(Ribbed slab) :
- -
-
-
:
-
e) (RB slab) :
ঐ
@RayenReza.Ibrahim Page : 69
(Level) :
1. Road Level:
3. Parking Level:
@RayenReza.Ibrahim Page : 70
1‖-0‘ 2'-6
2'-0
2
। 2
1:6
3 18
(Floor) :
।
1. (Ground floor),
2. (Upper floor) :
# (Upper floor) :
(Component of floor) :
1. - (Floor base or sub-floor )
2. (Flooring or floor covering)
@RayenReza.Ibrahim Page : 71
1) - (Sub-floor) :
- -
2) (Floor covering) : -
@RayenReza.Ibrahim Page : 72
6. (Asphalt)
7.
8. (Concrete)
9. (Mosaic)
10. (Marble)
11. - (Rich concrete)
12. (Rubber)
13. —-
14. -
15. (Glass )
16. -
17. (Plastic or P.V.C.)
(Types of floors ) :
a) (Ground floor) :
b) (Basement floor) :
c) (Upper floor) : -
d) (Suspended floor) :
(Types of flooring) : -
1. (Mud flooring)
2. (Cement concrete flooring)
3. (Brick flooring)
4. (Mosaic flooring)
5. (Marble flooring)
6. (Timber flooring)
7. (Rubber flooring)
8. (Cork flooring)
9. (Plastic or P.V.C. flooring)
10.
11. (Muram flooring)
12. (Flag stone flooring)
13. (Terrazzo flooring)
14. (Tiled flooring)
15. (Granolithic flooring)
16. (Asphalt flooring)
17. (Linolium flooring)
18. (Glass flooring)
19. (Acid proof flooring)
(Initial cost) :
(Appearance) :
- (Cleanliness) :
@RayenReza.Ibrahim Page : 73
(Durability) :
(Damp resistance) :
(Sound insulation) :
(Thermal insulation) :
(Fire resistance) :
(Smoothness) :
(Hardness) :
1. :
(I-beem -
2.
3. -
4. -
5.
6.
7.
-
8.
9.
10. -
@RayenReza.Ibrahim Page : 74
(Describe the construction procedure of the following type of floors) :
===================
(Brick flooring) :
-
1.
2.
3.
4.
5.
a)
b)
1.
2.
3.
4.
1. -
2.
@RayenReza.Ibrahim Page : 75
(a) -
-
(b)
(c)
‚ ‚ ‚
1.
2.
3.
4.
5. -
1. -
2.
(Terrazzo flooring) :
(Decorative floor)- -
(separator)-
40%
-
@RayenReza.Ibrahim Page : 76
(Mosaic flooring) :
-
- -
- -
(Tiled flooring) :
(Marble flooring) : -
-
–
- -
8. (Timber flooring) :
।
a) (Strip floor covering) : -
@RayenReza.Ibrahim Page : 77
d) (Fabricated wood block) :
- -
-
(Asphalt flooring) :
a) (Asphalt tiles flooring)
b) (Asphalt mastic flooring)
c) (Asphalt mosaic flooring)
d) (Acid proof mastic flooring)
-
(b) (Asphalt mastic flooring) :
(Rubber flooring) :
1.
2.
3.
4.
5.
(Cork flooring) :
- (Boili
-
-
@RayenReza.Ibrahim Page : 78
(Glass flooring) :
-3
(Plastic or P. V. C. flooring): -
•
Epoxy pr -
-
-
(i) Self-levelling epoxy floors :
- -
@RayenReza.Ibrahim Page : 79
(i) Prepare the surface :
1. (Timber floor)
a. (Single floor)
b. (Double floor )
c. Framed floor )
2. - (Pre-cast concrete floor )
3. (Jack arch floor)
4. (R.C. C. floor)
5. (Ribbed or hollow tiled flooring)
6. (Filler joist floor)
7. (Flag-stone floor resting on steel joists)
===========
(Single floor) :
@RayenReza.Ibrahim Page : 80
#
1.
2.
3.
4.
1.
2.
3. -
4.
5.
(Double floor) : -
-
-
1.
2.
3.
4.
5. - -
:
1.
2.
3.
4.
(Framed floor) : -
-1 (Girder), 2 (Binder), 3 4
- N
@RayenReza.Ibrahim Page : 81
1.
2. -
3.
4.
1.
2.
3.
-
1.
2.
3.
4.
5.
6.
7.
8.
9. -
10.
1.
2.
3.
4.
5. -
(RCC Floor) :
@RayenReza.Ibrahim Page : 82
a) Simple slab flooring)
b) (Reinforced brick flooring)
c) (Beam slab flooring)
d)
(a)
-
-
(b)
(c)
(d)
-
-
(Drop panel)
1.
2.
3.
4.
5.
6.
7.
1.
2.
@RayenReza.Ibrahim Page : 83
1.
2.
3.
4.
5.
6.
1.
2.
- ‚
- -
1.
2.
3.
4.
1.
2.
3.
1)
2)
3)
4)
5)
@RayenReza.Ibrahim Page : 84
6) -
1) -
2)
(Hollow floor) :
1.
2.
3.
4.
5.
6.
1.
1)
2) -
3)
4)
5)
6)
7)
1)
2)
3)
-
1)
2)
3)
4)
@RayenReza.Ibrahim Page : 85
(Stair) :
# (Introduction) : -
,
,
- ,
90 . 1.5-1.8 - 10-12 3
2.1-2.3
# –
1.
2.
@RayenReza.Ibrahim Page : 86
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
'
(m) (Hand Rail) :
,
Hand rail
(n) (Baluster) :
@RayenReza.Ibrahim Page : 87
(o) (Balustrade) : ,
# (Types of steps) :
a) (Flier step)
b) (Curtail or scrol step)
c) (Bull nose step)
d) (Winder step)
e) (Dancing step)
f) (Commode step)
g) (Splayed step)
(b) : ,
Round ended step
(c) (Half round) ,
(d) (Commode step) : ,
2 3
(e) (Winder step) :
@RayenReza.Ibrahim Page : 88
(e) (Head Room) : (Luggage)
2.1 2.3
(f) (Materials) : ,
(g) (Landing) : (Flight)
(h) (Winder) : (Winder)
(i) (Balustrade) : (Open well)
1. (Timber stairs) : ,
2. (Stone stairs) :
# ,
1. (Rectangular steps)
2. (Spandril steps)
3. (Slab tread and riser steps)
4. (Cantilever tread slab steps)
5. (Builtup steps)
4. (Metal stairs) : , , ,
- ' - (I-section chanel)
(Stringer) . . (R.S Joist)
Mild steel, Cast iron, Rolled steel
5. . . . (RCC Stairs) : . . . , ,
, 1:2:4 , Reinforcement
Waist slab, step, railing - - (Cast-in-situ)
1.
@RayenReza.Ibrahim Page : 89
2. -
3. , ,
4.
5.
6. ,
7.
8.
9. (Framed structure) RCC stair
# . . .
a) (Stair with slab spanning longitudinally) :
. . (Mild steel bar)
c) : . . . . .
# -
=====
1. (Quarter turn stairs)
(i) (Newel quarter turn stairs)
(ii) (Geometrical quarter turn stairs)
2. (Half turn stairs)
(i) (Doglegged stair or Newel half turn stairs)
(ii) (Open newel half turn stairs)
(iii) (Geometrical half turn stairs)
3. (Three quarter turns tairs)
4. (Bifurcated stairs)
5. (Continuous or geometrical stairs)
(i) (Circular stairs)
(ii) (Spiral stairs)
(iii) (Helical stairs)
#
1) (Straight flight stairs) :
'
,
, ,
@RayenReza.Ibrahim Page : 90
2) (Newel quarter turn stairs) : 90° ,
(Winders)
,
3) (Geometrical quarter turn stairs) : -
-
4) - (Dog-legged stairs) : 180°
, '
5) (Open newel half turn stairs) : ,
-
6) (Geometrical half turn stairs) :
, ,
3. ( ) 40 45 ( )+ = 40 45
( ) 30 + 15 = 45
( ) 27.5 + 16 = 43.5
( ) 25 +17.5 = 42.5
@RayenReza.Ibrahim Page : 91
4. 14 30 2 1 :
( ) 15 × 28
( ) 16 x 26
( ) 17 × 24
-16 x 26
- 10 x 30
- 27 × 15 30 × 14
25 × 16
# (Design of stair) :
1.
2.
3. ,
4.
(a) -
1. =( / )
2. = -1
(b) -
1. +2× = 60
2. x = 400 450
3. + = 40 45
(c) -
1. 90
2. - 1.5 1.8.
(d) - - ।
# : -
25 40 ,
# ।
==============
# (American Standard) :
+ = 44 .
x = 400-450 .
# (IndianStandard) :
+2x =60 .
x = 400-410 .
# AcI :
AcI 15 18
# :
, R= , .
T= , .
S= , .
@RayenReza.Ibrahim Page : 92
= S√ x
# : W = 12R / ,
R=
W=
# –
-
# –
250 400
3 12
6-7
10-12
# :
, 30 . 14 . 25 . 12-13 .
75
10 95 100 10
125
, , 150
300
250 , 300
200 , 150
26 45 30 800 900
2100 - - -
1
250
2400
15
-
@RayenReza.Ibrahim Page : 93
(Lift and Escalator) :
(Lift) :
1. (Bottom clearence) :
2. (Buffer) :
3. (Car or case) :
4. (Controller) :
6. (Diverting pulley) :
7. (Door closer) :
8. (Encloser) :
9. (Guide rail) :
-
10. (Driving sheave) :
11. (Travel) :
12. (Top clearence) :
17. (Pit) : 0
18. (Over speed governor) :
@RayenReza.Ibrahim Page : 94
21. (Electro-mechanical lock) :
============
a) (Passenger lift) :
b) (Goods lift) :
c) (Service lift) :
d) (Platform lift) :
a) (Gearless lift) :
b) (Geared lift) :
c)
d)
@RayenReza.Ibrahim Page : 95
(Wall) :
( ) ( ) ,
, ,
, ,
# ,
(Weather resistance)
(Durability)
(Fire resistance)
(Thermal insulation)
(Sound insulation)
# , :
1.
2. -
1. : -
, ,
# :
(a)
(b)
(c)
(d)
(e) (115 , 225 )
(f)
2. - :
,
-
-
- 100 125
# - :
(a)
(b)
(c)
(d) (115 , 225 )
# , :
a)
b)
c)
@RayenReza.Ibrahim Page : 96
(a) :
,
,
(b) : , , ,
(c) :
# :
# :
==============================
1. :
। :
1.
2.
3.
2. : ,
3. :
4. :
,
5. : , ,
6. :
,
@RayenReza.Ibrahim Page : 97
7. : 3
8. :
# :
(Partition wall) :
========================
N -
-
-
@RayenReza.Ibrahim Page : 98
(Function of partition wall) :
-
(Brick partition)
(Glass partition)
(Concrete partition)
(Timber part
- (Straw-board partition )
====================
(Brick partition wall) :
@RayenReza.Ibrahim Page : 99
(Brick nogging partition) :
-
(Sill)—
(Head)–
(Stud)–
(Nogging picce)—
-
-
==================
-
-
(Glass partition) :
-
(Hollow block)
a)
b) - -
-
(Concrete partition) :
- - -
- - - - -
=============
- (inter-tie
===================
====================
-
-
=================
=================
(Cavity wall) :
। -
-
-
-
- -
b)
c) (Sound insulation) :
d) (Efflorescence prevention) :
e) (Economy) -
v v
1.
2.
3. -
4.
5.
6. -
1.
2.
3.
4.
5.
6.
-
ঐ
-
-
- -
-
7.
8.
9.
10. -
11.
# (Retaining Wall) :
# -
-
(i)
(ii)
(iii)
2
- -
(Back Fill)-
(Heel & Toe)-
Weep Hole)-
-
#
, 4% 5%
6-7
(Heel) (Toe)
6
(Angle of Repose) 33°42° 1.5:1
, Weep hole
(stem) ( ) 20-30
( ) , (Non-surcharge)
0.4 0.65 0.55 0.75
,
2
# . . . . . .
(a) (Base slab):
. . . = x x
= L × B × 'h
(b) (Stem):
. . . = x × ( )
=L×( ) × (H – h)
= L × × (H – h)
:
==================
#
1.
2.
a.
b.
3.
4.
5.
6.
7.
a.
b.
8.
9.
10.
11.
(Stretcher bond) :
(Header bond) :
3. :
2.
3.
4.
5.
6. ’
7.
8.
a)
b)
1.
2. - -
1.
2.
3.
1.
—
a)
b)
a.
b.
(Facing bond) :
(Raking bond) :
—
a)
b)
b) (Diagonal bond) :
-
1.
2. (Qu
3. -
1.
2. -
3.
- (Zig-zag bond) :
# :
-----------------------------------------------
# ।
1. Ordinary Brick Work : ,
10
# - -
1000 0.10 (1 )
, , 10
#
=====================
# (Selection of bricks): , - ,
HP
# (Wetting of bricks) : 24
, ,
;
,
# : ,
,
# : , / RCC [ 2- ‘
distance]
# : ,
, ,
‘ 1:4 1:5
‘ 1:6 1:5
1 1.5 ,
1
(Per-Pend) (Straight edge)
(Finished)
-
. : 45 1
:
- ,
, RCC
,
, ‘ ‘
: ‘ 4.5 ‘ 5
: ,
, , 4.5
: ‘ 12mm
: , 7 ,
: ,
, ;
(i)
(ii) ,
Allow ,
: , ,
: ,
: ,
RCC
: 90 ,
:5 12/13
,
,
: ,
: ,
: 7 14
# : :
4
,
3.
4.
5. 5
6. 7
(Composite masonry) :
- -
-
—
1.
2.
-
।
। —
-
- -
-
- -
-
1.
2.
3.
4. -
5.
6. -
7.
। -
1. (Horizontally)
2.
(Longitudinal stee -
-
- -
-
-
1.
2.
3.
(Purpose of a lintel) :
1.
2.
3. -
4.
। -
1.
2.
3.
4.
(d) (Intrados) : -
(e) (Soffit) :
-
(f) (Extrados) :
(g) (Back) : -
(h) (Crown) : -
(i) (Spandril) :
(o) (Pier) :
(p) (Hunch) :
(q) (Span) :
(r) (Rise) : -
(s) (Depth or height) :
(Mention the different type of arches according to their shape, center and
material)
===================
(According to shape)
(According to number of centres )
(According to materials of construction)
1. (Segmental arch)
2. (Semi-circular arch)
3. (Horse-shoe arch)
4. (Pointed arch)
5. (Venetian arch)
6. (Florentine arch)
7. (Relieving arch)
8. (Stilted arch)
9. - (Semi-Elliptical arch)
======================
(One-centred arch)
(i) (Segmental arch)
(ii) (Semi-circular arch)
(iii) - (Horse-shoe arch)
(iv) (Flat arch)
(v) (Stilted arch)
(vi) (Wheel or Bull's eye arch)
(Two-centred arch)
(i) (Blunt arch)
(ii) (Equilateral arch)
(iii) (Acute arch)
(iv) - (Semi-elliptical arch)
(Three-centred arch)
(i) (Elliptical arch)
(ii) (Parabolic arch)
(iii) (Pointed arch)
(Four-centred arch)
(Ovoid sewer arch)
(Venetian arch)
(Tudor arch)
====================
(Brick arch)
(i) (Rough arch)
(ii) - (Axed or rough cut arch)
(iii) (Gauged arch)
(iv) (Brick flat arch)
(Stone arch)
(i) (Rubble arch)
(ii) (Ashlar arch)
(Concrete arch)
(i) (Concrete block arch)
(ii) (Monolithic concrete arch)
b)
c) - -
d)
e)
f)
g)
h)
i) -
j)
k)
l)
a)
b)
c)
d)
e)
f)
g)
=======================
(i) (Brick arch) :
-
(ii) (Rough arch) :
― ‖
# ।
1.
2.
1) -
2)
1) -
- -
2) - -
(Lintel) :
-
1.
2.
3.
-
1.
2.
3.
4.
5.
6.
1.
2. –
3. -
4.
(Brick lintel) :
1.
2.
3.
4.
5.
(Stone lintel) :
(Steel lintel) :
(R.C.C. Lintel) :
1.
2.
3.
a)
b) -
c)
- –
(Prop
-
-
(Stability of an arch) :
1.
2.
3.
4.
5.
a)
b)
c) -
-
-
d)
a)
b) N
a)
b) -
#
a)
b)
(Arch) (Lintel)
3 - -
10
11
12
13
1. -
2.
3.
4.
-
-
20 25
।
1.
2.
3.
4.
5.
(Centering) :
(Shuttering) :
1)
2) -
3)
4)
(Stripping time) :
1 -
1.
2. (Sof
3.
ঐ
1000mm x 1200mm
1500mm
(Scaffolding) :
- (Types of Scaffolding) :
(Types of scaffolding) :
1. (Single or Brick layer's Scaffolding)
2. (Mason's or Double Scaffolding)
3. (Cantilever or Needle Scaffolding)
4. (Ladder Scaffolding)
5. Chimney Scaffolding)
6. (Suspended Scaffolding)
7. (Staging)
8. (Gantrys)
9. (Steel Scaffolding)
(Mason's Scaffolding) :
(Beam bear
1.
2.
3.
(Ladder Scaffolding) :
-
-
(Chimney Scaffolding) :
(Suspended Scaffolding) :
(Staging) : -
-
(Gantrys) : -
।
(Gantry with a traveller or Crane)
(Plat Form gantry)
b)
90
(Steel Scaffolding) :
1.
2.
3.
4.
5.
1.
2.
3.
b) (Ledgers) : -
c) (Putlogs) :
d) (Braces) :
e) - (Toe-board) : -
f) (Guard rail) :
g) (Raker) :
h) (Working platform) :
i) (Transoms) :
v k
- -
1.
2.
3.
—
1.
2.
3. 50 - 100
4.
-
1. (Adaptability) :
-
2. (Availabilitis) :
3. (Simplicity) :
4. (Interchangeability) :
5. (Ease to erection) :
6. (Scrap value) :
7. (Strength) :
8. (Resistance to fire) :
1. (Initial cost) : -
2. (Fittings) :
3. (Connections with timber) :
(Shoring) (Scaffolding)
1 1
2 2
3
3
(Room) :
1.
2.
3.
#
(Drawing room) ‚ ‚
(Bed room) ‚ ‚
(Kitchen) ‚ ‚
(Store) ‚ ‚
(Pantry) ‚ ---
(W.C) ‚ ---
(Bath) ‚ ---
(Verandah)
(Garage) ---
(Room):
-
-
-
-
–
-
-
(Room height):
-
(Thickness of -
-
-
-
(Thickness of -
-
-
- -
- RCC (1 : 2:4)
-
–
- RCC
-
-
-
-
—
– ‚
- ‚ ‚
- –
-
-
-
-
-1
-
-
-
A. (Plastering) : -
-
-
-
-
-
-
-
B. (Pointing) :
1:1
1:2 1:3
1. ঐ
2.
3.
1) (Background) : -
ঐ
2) (Blistering) :
3) (Cracking) :
4) (Crazing) :
5) (Dado) :
6)
7) (Dubbing coat) :
9) (Gauging) :
10) (Grinning) :
11) (Ground) : (P
12) (Hacking) :
13) (Keys) : -
-
14) (Laitance) :
15) (Peeling) :
16) (Straining) : -
(Types of plaster) :
-
a) (Lime plaster)
b) (Surki plaster)
c) (Lime-surki plaster)
d) (Cement plaster)
e) (Stucco plaster)
f) (Gypsum plaster)
g) (Mosaic or Terrazzo plaster)
h) (Moghal plaster)
i) (Chunam plaster)
j) (Lime punning or Neeru or lime putty)
k) (Sand rubbing)
l)
(Surki plaster) :
-
(Stucco plaster) :
।
1. (Scratch coat) :
2. (Brown coat) : -
3. (Finishing coat) :
-
a)
b)
c)
d)
e)
f)
g)
(Moghal plaster) :
(Chunam plaster) :
(Mud plaster) :
12. -
1) (Flush pointing) :
2) (Recessed pointing) :
4) (Beaded pointing) :
5) (Struck pointing) : -
6) (Tuck pointing) :
ঐ
-
8) Weathered pointing) :
-
19 0.75
12 0.50
R.C.C / 6 0.25
6 0.25
25.4 1.00
(Purpose of pointing) :
1.
2.
3.
4.
-
1.
2.
3.
4.
5.
6.
7.
8.
9.
-
1.
2.
1.
2.
3.
4.
5.
(Mention the common tools used for plastering and pointing work
with their functions) :
1. (Gauging trowel)
2. (Wooden float or metal float)
3. (Floating rule)
4.
(Pointe
-
Laying trowe
- -
-
– - -
(Process of pointing) :
==================
।
1. (Raking out of joints)
2. (Preparation of mortar)
3.
3) (Application of mortar) :
=====================
1.
2.
3.
4.
1.
2.
3. -
-
1.
2.
3.
4.
5.
1. (Blistering) :
2. (Cracking) : -
a)
b)
c)
d)
e) -
f)
g)
3. (Crazing) :
4. (Efflorescence) :
5. (Flaking) :
6. (Peeling) :
7. (Popping) :
8. (Rust stains) :
9. (Uneven surface) :
6.
7.
8.
(Acoustics tiles) :
- - -
(Rustic tiles) : -
-
-
-
।
=============================================
# -
=================
# Mortar Laying:- 5
N 1/2‘ 3/4‘
3/4
1 1‘
1.5
1/2
1/2‘
-
- 1
Curing:-
7-14 2
# -
=============
# [Dry Mortar]:-
# -
# -
90
7
100
# -
=======================
a) Blistering:-
b) Crazing:-
c) Cracking:-
4.
-
1.
2.
3.
D.
# (Curing) : , 6 24
# :-
1.
2.
3.
4. Abrasion
5.
# :-
1.
2.
3.
4.
5.
# :
1.
2. ,
(b) :
=========
# :
1.
2. , , ,
#
1.
2. ,
(c) :
# :
1.
2. -
(d) :
=========
# :
1.
2.
3.
# :
1.
2.
3.
(e) :
=========
# :
1.
2.
3.
# :
1.
2. ,
(f)
=========
# :
1.
2.
3. -
# :
1.
2. 22°c
# :
20 7
- 24 7
20 7
20 21
20 3
20 7
20 7
15 7
20 7
12 7
20 7
24 7
12 16
. . . 20 21
15 7
, 20 7
20 7
. . 20 7
20 14
24 7
24 7
3/4/5
6/7/8
3/4/5
6/7/8
L/4
L/3
# (ACI) -
As = 0.0025bd = 0.0025bt
As = 0.002bd = 0.002bt
As = 0.005bd
,b= ,
t= /
d= /
5 45
# ACI -
1. 180° 4 6.5 cm (2.5 inch)
2. 90° 12
# -
16mm (#5) 90° 6
20 mm, 22mm, 25mm (#6, #7, #8) 90° 12
25 mm (#8) 135° 6
f'c
Bar 32mm ∅ 28mm ∅ 25mm ∅ 22mm ∅ 20mm ∅ 16mm ∅ 12mm ∅ 10mm ∅ 8mm ∅
3500 ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘
Top Bar
(Horizontal)
3000 ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘
3500 ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘
Bottom Bar
(Horizontal)
3000 ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘
4000 ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘ ---
Vertical Bar
of Column
3500 ‘ ‘ ‘ ‘ ‘ ‘ ‘ ‘ ---
2.
3.
4.
N
5.
6. ‘
(Covering) :
—
1.
2. -
3. -
# :
Beam
(End covering) 5 (2 )
(Side covering) 5 (2 )
(Top covering) 5 (2 )
(Bottom covering) 5 (2 )
Column
(Side covering) 5 (2 )
(Top covering) 4 (1.6 )
(Bottom covering) 5 (2 )
Slab
(End covering) 5 (2 )
(Side covering) 5 (2 )
(Top & Bottom covering) 2 - 2.5 (0.8-1 )
Grade Beam
(End covering) 5 (2 )
(Side covering) 5 (2 )
(Top & Bottom covering) 5 - 7.5 (2-3 )
Septic Tank
Outer Side = 5 - 7.5 (2-3 )
Inner Side = 5 (2 )
Sunshade
(Side covering) 2.5 (1 )
(Top covering) 2.5 (1 )
(Bottom covering) 2.5 (1 )
(End covering) 2.5 (1 )
5 / 12.7
3 / 7.5
2 /5 16 18
1.5 /4 ( , ) : 14 18
0.75 /2 ( , ) 11
1.5 /4 ( ): ,
0.75 /2 6
0.5 / 1.5 5
( , ):8
1 / 2.5
( , ):9
2 /5
(Joints in structures) :
(Types of Joints) :
b. (Expansion Joints)
c. (Isolation Joints)
d. (Contraction Joints)
e. (Sliding Joints)
f.
1. (Expansion joint) :
(Wall) :
1.
2.
(Roof) : —
3.
(Frames)
- ‚ ---
2. (Contraction joint) :
-
(i) (Complete contraction joint)
(ii) (Partial contraction joint)
(iii)
3. (Construction joints) :
ঐ
(ii) (Beam) :
(iii) (Column) :
(iv) (Wall) : -
4. (Sliding joint) :
5. (Isolation joint) :
# (Painting) : (Paint)
, (Pigment) , (Binder)
, , , , ,
(Painting) , ,
# (Varnishing) : ( ) (Volative)
, , , ,
(Varnishing)
#
1.
2.
3.
4.
5. - ,
# (Ingredients of varnish) :
1. (Resins or reginous substances)
2. (Solvent)
3. (Driers)
#
i. (White lead)
ii. (Zinc white)
iii. (Titanium white)
iv. (Aluminium white)
v. (Red lead)
vi. (Iron oxide)
vii. (Antimony white)
viii. (Lithopone)
(viii) (Lithophone) :
a)
b) ,
c)
d) ,
a)
b) (Setting)
c)
d)
e)
f)
g)
#
a) (Baryet - Barium sulphate)
b) (Linthophone)
c) (Silica)
d) (Whiting)
e) (Gypsum)
f) (Magnesium silicate)
g) (Aluminium)
h) (Calcium carbonate)
i) (Charcoal)
j) (Talc)
k) (Diatomite)
# -
a)
b)
c)
d)
e)
f)
#
1. (Linseed oil) :
(a) (Raw linseed oil)
(b) (Pale boiled linseed oil)
(c) (Boiled linseed oil)
(d) (Double boiled linseed oil)
2. (Tung oil)
3. (Popy oil)
4. (Nut oil)
5. (Caster oil)
6. (Fish oil)
7. (Cotton seed oil)
8. (Soyabean oil)
1. (Linseed Oil) :
a)
b) (Flax seed)
c) ,
d) , ,
2. (Tung Oil) :
a)
b)
3. (Poppy Oil) :
a) (Poppy seed)
b)
c) ,
4. (Nut Oil) :
a) (Walnut seed)
b)
c)
5. (Caster Oil) :
a)
b) -
c)
6. (Fish Oil) :
a)
b)
8. (Soyobean Oil) :
a)
b)
1.
2. (Porous surface)
3.
4.
5.
5. (Drier) : , Vehicle
(Litharge) (Lead monoxide)
-
a)
b)
c)
d)
e)
# ।
1. (Litharge or Lead Monoxide)
2. - (Manganese Di-oxide)
3. (Lead accetate)
4. (Zinc Sulphate)
5. (Cobalt
6. (Manganese)
7. (Lead)
6. (Pigment) : , -
,
:
(i) (Natural colours) : (Ochres), (Umbers), (Iron oxide)
(ii) (Calcined colour) : (Lamp black), (Indian red), (Carbon black), (Red Lead)
(iii) (Precipitates) : (Prossion blue), (Chrome green), (Chrome yellow)
(iv) - ( (Lakes) : (China clay)
(v) (Metal powders) : , , ,
(Blue) : (Indigo blue), (Prossion blue), (Cobalt blue), (Ultra marine blue)
(White) : ,
: + + (5:3 : 1.5)
: + + + (0.25 : 2 : 0.25 : 1)
: + + + (1:1.5: 2:0.125)
: + + (2.5 : 1:0.125)
#
===================
1. (Resin) : , , , (Gurn dammer),
, (Lac or shellac) ,
2. (Solvent) : -
, ,
3. (Driers) : : (Litharge),
(White copper), (Lead acetate)
# (Defects in varnishing) : :
1. (Blistering) :
2. (Bloom) : (Dull patches)
3. (Sagging) : Sagging
4. (Fading) :
5. (Flaking) : (Poor adhesion)
6. (Flashing) : , (Glossy patches)
7. (Grinning) :
8. (Running) :
9. (Saponification) : (Soap patches)
10. (Wrinkling) :
1) :
(Wrinkling), (Fading)
2)
3)
(Knotting)
4)
(Bristle)
1. (Condition of surface)
2. (Quality of paint)
3. (Preparation of surface)
4. (Workmanship)
5. (Praperness of painting brush)
1)
(Wrinkling), (Fading)
2)
3)
(Knotting)
4)
5) :
(Bristle)
2. (Water paint) :
(
) - ,
,
3. (Aluminium paint) : , ,
, , , ,
,
#
a) (Weather resistance)
b) (High heat reflective)
c) (Water proof)
d) (Corrosion resistance)
e) (High electrical resistance)
f) (High covering capacity)
g) (Visibility in darkness )
h) (Better appearance) |
6. (Bituminous paint) : , , , ,
7. (Bronze paint) :
(Radiator)
8. (Cellulose paint) : , - , ,
, ,
' '
# (Types of varnish) :
a) (Oil vernish)
b) (Sprit varnish)
c) (Turpentine vernish)
d) (Water varnish)
e) (Asphalt vernish)
f) (Spar vernish)
g) (Flat vernish)
1. (Preparation of surface : 15
3 ,
2. (Knotting) : ,
,
# ,
(i) (Ordinary or size knotting) : 2 15 225 ,
(Knote) 10
3. (Priming) :
, ,
Row linseed oil = 0.5 litre Vehicle Row linseed oil = 2.25 litre Vehicle
4. (Stopping) : ,
, Stopping
( )
- - Hard stopping
5. (Under coating) :
6. (Finishing coat) :
,
( - ) ( - )
2. (Adhesive)
3. 3
4. ― '
3 ,5
5.
2. ' (Hydration)
(Primer)
,
,
(Permeable)
# (Process of varnishing) : ,
=======================
1. (Preparation of surface) : 15
,
2. (knotting) :
(i) : 2.5 15 225
(iii) : 24
3. (Stoping) :
, ,
(Stopping) ( )
4. (Coat of varnish) :
# ।
1. -
2. -
3.
4.
5.
# (White wash) :
1. (Stone lime)
2. (Gum or glue)
3. (Water)
4. (Slaked lime)
5. (Blue)
(c)
=======================
# (Distemper) : (Thinner)
50% 90%
4% 5% (Distempering)
# (Properties of distemper) :
1. (Oil bound washable paint), (Washable oil free distemper),
2.
3.
4.
5. (Porous surface)
6. (Colour)
(d)
============
# (oil based) (Water based) -
1 1
2 (Base) , ,
2 ,
3 3
# -
(a) (Base) : , ,
(b) (Carrier) : , ,
(c) (Thinner) : ,
(d) (Drier) : ,
(e) (Pigment) : , ,
# ।
(a) (Base) : ,
(b) (Carrier) :
(c) (Pigment) : , ,
(d)
1 - , , 1 , , , ,
2 2
3 3
8 , , ,
4 (Covering Power)
# (Procedure of application) :
=============================
(1) (White washing) : , , , , | (Blue) ( :
) ,
(Unslaked) (Slaked)
( ) 24
37 ( ) 250
4
(Blue) 1.3
4 ( )
(Capper sulphate) (Alum)
,
, , (Smoke)
(Yellow Earth)
, 15 , 60
500
# -
1.
2.
3. ,
4.
5.
6.
7.
8.
9. , ,
1. (Prepartion of Surface) : :
a) ,
b)
c)
d) , ,
e) 10
f) (1 to 50) 24
g)
3. (Applying Distemper) :
,
,
#
1.
2. ,
3.
4.
5. (Film) (Spray pistol)
b)
c)
d)
e) (Film)
f)
# (Coat)
,
, (Chalky) 24
,
# :
1.
2.
3.
4.
5. ,
6.
#
1.
2.
3.
.
4.
5. ,
6. (Fade) (Light shade)
1955
(Vinyl acetate) (Acrylate)
-
(Binder) 0.20
(Pigment) 0.50
(Other solids) 0.10
= 1.40
,
15 0.04
# :
1) (Application) : , , , , , -
2) (Base surface) :
4) (Colour of paint) :
#
1. Low shrink during cure
2. Excellent moisture resistance
3. Excellent chemical resistance
4. Good electrical properties
5. Increased mechanical and fatigue strength
6. Impact resistant
7. Long shelf life.
# :
1. General purpose adhesives
2. As the binder in cement and mortars
3. Rigid foams
4. Non-skid coatings
5. Solidifying sandy surfaces in oil drilling
6. Industrial coatings
7. Fiber reinforced plastics.
# (Resins) :
# (Additives)-
1. Easy of brushing, mould resistant, scuff resistance, drying and sag resistance.
2. Low odorless additives.
3. Low solvent additives.
4. Gives paint its smooth texture, driers, anti-setting agents, anti-skinning agents.
5. Enhance performance.
#
1. (Surface is clean) :
Liquid hand soap
2. (Add the epoxy) :
3. (Leave to dry) : 24
4. (Finishing) :
# -
/
# : 45
, , -
# :
45
,
# :
1 1 25
(Roof) :
(Introduction) :
-
(Classification of roof) : -
1.
2.
3.
a) (Shelled roof)
b) (Domed roof)
-
-
1. - - (Lean-to-roof)
2. (Gable roof)
3. (Hip roof)
4. (Gambrel roof)
5. (Mansard of curve roof)
6.
1) - -
2)
a) -
b)
c) (Trussed Roof) : -
C (Curved roof) :
1. (Shell roof)
2.
10 25 X 25
(Function of roof) :
1.
2.
3.
4.
2) (Weather resistance) :
3) (Heat or thermal insulation) :
4) (Fire resistance) :
5) (Sound insulation) :
6) (Damp proofing) :
- -
Mortise and Tenon join
2) (Purlin) :
(Gable w -
3) (Hip rafter) : -
4) (Valley rafter) : -
5) (Jack rafter) :
6) (Ridge piece) :
7) (Dragon tie) :
9) (Barge board) :
10) (Batten) :
13)
15) (Gutter) :
-
16) (Valley gutter) :
17) (Trimming) : - ঐ
18) (Template) :
19) (Span) :
20) (Verge) :
21) (Rise of roof) :
22) (Valley) : acute angle
23) (Principal rafter) :
(Compare the advan tages and limitations of that vodfover pitched roof):
==============
1.
2. -
3.
4.
5.
6. -
7.
8.
9.
-
a)
b)
c)
d)
e)
f)
g)
h)
1)
2) Mortice
‗
4)
5)
-
:
a)
b)
c)
d)
e) (Straining beam)
f)
g)
(Straining sill)
(Mansard truss) : -
-
-
(Composite truss) :
1. (Open truss )
2. (Bow string truss )
3. (Cantilever truss )
4. (Saw tooth truss )
5. (Scissors truss )
6. (North light truss )
7. (Arched rib truss and solid arched ribs)
8. (Hammer beam truss )
9. (Fink truss )
1.
2.
3.
4.
5.
6.
7.
8.
(Decking)
(Straw board)
(Aluminium alloy and steel decking
1. (Type of building)
2. (Type of roof frame work)
3. (Initial cost)
4. (Maintenance requirements)
5. (Fabrication facilities)
6. (Appearance and special features of the locality)
7. (Durability)
8. (Availability of the material)
9. (Climate of the locality)
10. (Weight of the roof covering)
11. (Slope of the roof)
12. (Heat insulation)
1 ) 1 : 40 1 : 80
2 1 : 40 1 : 60
3 1:6 1:8
4 1:3 1:8
5 1:2 1 : 2.5
6 1:1 1:2
81
(Rolled section) : -
4-8 21
48-72
4.5 7
4.5 14
6 14 14
6 21
A. : - ,
, - - ,
, ( )
40 100 , -
# :
1. -
2. -
3. -
4.
5.
6.
# :
1. -
2. ,
3.
4.
5.
(Timber)
(Steel section)
(Aluminium section)
(Concrete)
(Stone)
# -
(a)
57 x 76 ( )
57 x 114 ( )
(b)
57 x 57
57 x 102
3. ( )
4. , -
5.
6.
7. , ,
# :
= + (1.20 ) 2 1.80
# । -
# -
1. - (1.0 .x2 .) (1.10 .x2 .)
2. - (0.9 .×2 .) (1 .×2 .)
3. WC - (0.7 .x2 .) (0.8 .x2 .)
4. -( 2.25 .× 2.25 .) ( 2.25 .× 2.40 .)
# , , —
1.2 . x 2.0 .
1.2 . x 2.1 .
1.2 . x 2.25 .
- 10 DT 20
(a) (Frame):
(Enclosure)
(b) (Shutter) : , ,
, (Hinge)
(c) (Head) :
(d) (Horn) : (Head and sill)
10 15
(e) (Sill):
(f) (Jamb) :
(g) (Reveal) :
(h) (Style or stile):
(i) (Top rail) :
(j) (Lock rail) : , - ,
(k) (Bottom rail) :
(l) (Cross rail or intermediate rail):
(Frieze rail)
(m) (Panel) :
(n) (Mullion): ,
(o) (Transome): ,
(e)
1. , - -
1.
2.
3.
4.
5.
2. , -
1.
3. -
1.
2.
# :
1.
2. ,
3.
4.
5.
6.
7. (Timber beading)
8. 40
9. 10 15
#
#
1.
2.
3.
#
1. -
2.
3.
# ।
1) (Solid or laminated core type)
2) (Cellular core type)
3) (Hollow core type)
1) : , , ,
,
2.5 5 6
(Lock block)
(Hinge block)
2) 7.5 , 3.5
25 40%
3) : 7.5 , ,
2.5 500
#
1.
2.
3.
#
1.
2.
(Louvered) 45°
, ' :
45°
(Pivot) , -
, ,
# :
1. -
2.
3.
4.
5. -
# :
1.
2.
3.
# :
1.
2.
, , ,
20 30
, , , ,
#
1.
2. 3
' -
# (General specification) :
1. ,
2.
, ,
3. ,
4. 15 - 4
10 15
5. , ,
6. -
7. - 3 2 300
, ' -
8. 3
9. (Flat)
10. , ,
B. : -
# :
1. -
2.
3.
4.
# -
= 1/8 ( + )
10 – 20% (Opening)
30 40
20%
# :
1. : 1.10 1.20
2. : = 0.4 0.6 x
3. : (Width) = 0.4 to 9.6 x (Height) 90 ,
2.0
4. (Designation and sizes of doors) : (Width), (Type) (Height) (Symbol)
W = Window.
V = Ventilator
S = Single shutter
T = Double shutter
1. (Fixed windows)
2. (Pivoted windows)
3. (Double hung windows)
4. (Sliding windows)
5. (Casement windows)
6. (Sash windows)
7. (Louvered windows)
8. (Metal windows)
9. (Bay windows)
10. (Clerestorey windows)
11. (Corner windows)
12. (Dormer windows)
13. (Gable windows)
14. (Lantern windows)
15. (Skylights)
16. (Fanlights)
17. (Ventilators)
(c) (Head) :
(d) (Horn): (Head and sill) 10
15
(e) (Sill) :
(f) (Jamb):
(g) (Reveal) :
(h) (Style or stile):
(i) (Top rail):
(j) (Lock rail) : , -
(k) (Bottom rail) :
(l) (Cross rail or intermediate rail):
(Frieze rail)
(m) (Panel) :
(n) (Mullion): ,
(o) (Transome) : ,
# (Movement)
(a) (Fixed type) :
(b)
(c)
(d) ,
(e)
(f) :
(g) : '
(h) :
(c) : UPVC
#
1.
2.
3.
4.
5.
#
1. PVC
2. UPVC
(Venetian blind)
#
1.
2.
3.
4.
5.
6.
7. -
8.
'
(Chhajah)
(b) (Fanlight) :
(c) (Ventilator) : 30 50
,
(d) (Sunlight) :
-
(e)
, ,
,
(f) UPVC (UPVC channel window) : (Vinyl chloride)- UPVC
UPVC (Unplasticized Polyvinyl Chloride) , (Polyethylene) (Polypropylene)
UPVC- (Rigid PVC) PVC-
UPVC (Capping),
(Sliding track), (Edging trim) -
# UPVC :
1. Energy Saver
2. Thermal Insulator
3. Corrosion Resistance
4. Weather Proof
5. Water Proof Materials
6. Noise Insulation
7. Termite Resistance
8. Wind Resistance
9. High Durability
10. Great Contributor to Aesthetics
11. Low Maintenance.
' -
4.
5. -
6. (Finish)
7.
8.
, -
(Water Tank) :
1 :
a) (Plastic Water Tank) :
3
a) (Cylindrical Water Tanks) :
০০ ০ ০০০
:
a)
b) :
c) :
d) : -
e) :
g) :
h) :
i) :
(Saptic Tank) :
1.
2.
3.
1.
2.
3.
4.
5.
6.
7.
:
- -
-
-
:
-
# :
2 8
1:3:6 1:2:4
1:3 12
60 1
(Dampness of Building) :
(Introduction) :
(Condensation) :
(Miscellaneous causes) :
a)
b)
c)
d)
e)
।
1)
2) -
3)
4)
5)
6)
(Surface treatment) :
(Define efflorecence) :
=================
(Flexible materials) :
(i) (Hot bitumen or Hot asphalt )
(ii) (Bituminous or asphaltic felt)
(iii) (Bituminous sheet)
(iv) (Plastic sheet-Polythene sheet)
(v)
- (Semi-rigid materials) :
(i) (Combination of sheets and bituminous felts)
(ii) (Mastic asphalt)
(Rigid materials) :
(Stones)
(Cement concrete)
(Mortar)
(a)
(c)
-
(d)
(e) -
(f)
(g)
(h)
(i)
(j)
(a)
-
(b)
(c)
C PVC Felts) :
-
-
20 × 20 30 × 30 45 × 45
Wa
Damp proofing.
1)
2) —
1)
2)
3)
4)
5)
6)
7)
(Termite in Building) :
(Introduction) :
1. -
(Bridging) : -
(Cost) :
(Floor joint) :
(Site clearance) :
#
Chemical Concentration by weight
I. DDT 5%
II. BHC 0.5%
III. Aldrin 0.25%
IV. Heptachlor 0.25%
V. Chlordane 0.5%
(Site preparation)
(Soil treatment)
i. (Treatment of excavated foundation trenches)
ii. (Treatment of back fill soil)
iii. (Treatment of filling at plinth level)
iv. (Treatment of soil along the external periphery)
(Structural barrier)
(Site preparation) :
(Soil treatment) :
-1 :
-2 :
-3 :
-4 :
(Structural barriers) : -
-
(Post-construction treatment) :
-
1. (Inspection) :
1.
2.
3.
4. -
5.
1.
2.
3.
। ।
1. Concrete Jacketing of Columns
2. Steel Profile Jacketing of column
3. Addition of Shear Wall
4. Addition of extra Structural Member
5. Ferro-cement Jacketing
6. Fiber Reinforced Polymer Wrapping
:
1.
2.
1.
2.
3.
4.
5.
1.
2.
3.
1. - -
2.
# Ferro-cement Jacketing :
1.
2. (7500C for 48 hours)
3. 40-50
4.
:
1.
2.
3.
4.
1.
2.
3.
4. 30-50 1.5-2
5.
Adding Bracing
Wall thinckening
Mass reduction
Base Isolation
Mass Dampers
Footing Retrofitting
(Insulation of Building) :
, (Thermal insulation)
# :
1. ,
2. , ,
3. ,
4. ,
5.
# (Classification of noise) :
===========
(a) ৎ ' ।
1. (Outdoor noise) : : , , , ,
2. (Indoor noise) : - , , , ,
(b) ' ।
1. (Air borne noises or sounds) :
, , , (Key hole)
,
2. (Structure borne noise or impact noise) :
: , , ,
# (Reflection of sound) :
(Incidence angle)
2. (Convex)
3. (Flat surface) (Wave front)- (Spherical)
4.
5. -
6. ,
# (Reverberation) : ,
10
# (Sound absorption) :
# ।
1.
2.
3.
4. , ,
1.
2. (Absorb)
3. ,
(Transmission)
3. (Prevention of condensation) : ,
( )
4.
(Hot water system)-
a. (Conduction) : -
1. (Temperature difference between outside and inside surfaces),
2. (Thickness of solid medium),
3. (Area of exposed surface),
4. (Time for which heat flow takes place),
5. (Rate of heat transfer or conductivity of the medium)
6. (Density of the medium)
# (Important terms) :
==============
# (Thermal conductivity) : I°C , ,
K (Porosity), , ,
2
{(K.Cal cm)/(m h.degC)} K
# — Values of Thermal Conductivity (K) for different building materials and insulating materials :
# (Thermal resistivity) :
# (Thermal resistance) :
R
R= =
# (Surface Co-efficient) :
(Unity) ,
(Surface Coefficient) , , {(Kilo
calories)/(m2h.degC)}
# (Surface resistance) :
(Surface Coefficient) (Reciprocal)
RT = R1 + R2 + T3 ’ )
D= x 100
# (Radiation) : ,
(Absorb)
(Reflect)
# (Transmission of noise) : :
1. (Through air)
2. (By vibrations of structural members)
3. (Through structural members)
1. , , , , ,
60 ∞ 120 2.5
2. , , ,
1.2 4
3. : , ,
4. : 5 ,
7.5 9
5. : (Pulp of wood), (Lining)
7. : , ,
# :
1. (It should have high thermal resistance)
2. (It should be reasonably fire proof)
3. (It should be insect proof)
4. (It should be durable)
5. (It should be non-absorbant of moisture)
6. (It should cheaper)
7. (It should be readily available)
(Sound absorbing) -
1. , , , ,
2. - , , (Porosity) (Frequency)
, ,
3. -
4.
5. - (Cover) ,
6. (Acoustical condition)
,
7. ,
3.
4. , , , (Celotex) (Lining)
5. , , , ,
6. , , (Impact sound)-
7.
8. (Air plugs), (Head phones)
(b)
1. (When noise is produced in the room itself)
2. (When noise is air borne)
3. (When noise is structure borne)
2. -
(i) (Solid non-porous homogeneous partitions)
(ii) (Partition of porous materials)
(iii) (Double wall construction)
(iv) (Floating floor construction)
(v) (Suspended ceiling construction)
(vi) (Box type construction)
(vii) (Design of doors and windows)
(viii) (Scientific planning of building)
# -
1.
2.
3.
4. ,
5.
3. -
1. -
2. (Discontinuous construction) : Box type construction
Suspended ceiling Structural floor Structural floor Floating floor
3. (Insulation of machinery) : , ,
2.
3. (shining)
4.
5.
#
==============
(a) (Wall insulation) :
(Plumbing System) :
, ,
-
# (Plumbing system) :
, , ,
# - (Purpose of plumbing) : , ,
(Supply pipe) (Drainage pipe)
- , -
- -
# (Plumbing installation) : , -
,
(Stack) , (Sullage)
, , , ,
, (Sewer)
# , -
a) (Supply system)
b) (Fixture system)
c) (Drainage system)
, , ,
(b) (Fixture system) : - ,
, , ,
, -
, , ,
(Stack)
6. ,
7. ,
8. - ,
# (Fixtures) : ,
# :
1. (Wash basin)
2. (Sink)
3. (Bath tub)
3) (Cross) :
4) (Reducing elbow) :
5) (Reducing tee) :
6) (Y) : 120°
7) (Socket) : ,
8) (Plug) : -
9) (Nipple) :
10) (Union) :
11) (Bend) :
# :
=================
1. , - -
75
(Overflow slot)
2. (Sink) :
, , -
90
3. (Bathtub) :
# ' —
a)
b) (European type)
(a)
(b) (Commode)
(Seat) 35 65-75
' : (Flat)
-
1 - 1
: , ,ঐ , , ,
, , ,
2 2 , ,
3 3
4 4
# (Plumber's tools) : ,
, - , -
2. (Marking tools) :
a) (Wood pencil)
b) (Scriber)
c) (Divider)
d) (Chalk line )
e) (Compass)
3. (Testing tools) :
a) (Straight edge)
b) (Calipers)
c) (Tri square)
d) (Plumb bob)
e) (Spirit level)
4. (Cutting tools) :
a) (Chisel)
b) ' (Hacksaw)
2. (Dividers) : (Leg) —
3. (Spirit level) : , ,
4. (Hack saw) : , ‖ :
a) (Handle),
b) ' (Saw frame),
c) ' (Saw blade)
' , - -
'
250-300
5. (Pipe cutter) : - ‖
-
a) (Frame)
b) (Handle)
c) (Cutter wheel)
d) (Slide)
e) (Guide roller)
7. - (Die-stock) : (Cutter) -
12-100 -
9. (Tap) : - '
, - (Parallel) (Taper)
10. (Reamer) :
-
11. (Chisel) : -
150 . 450 . 12 . 25 .
13. (File) :
, — , , , ,
(Building Services) :
, , , , , -
, , ,
, , ,
, (Water supply) , ,
, ( )
,
, , , (W.C) ,
, , ,
-
:
1.
2.
Tar-Paper
3. -
4. - , ,
5. 20 25
(a) , ,
(b) ,
# :
1. (Switch) : (Circuit) ,
2. (Holder) : ,
3. (Ceilling Rose) :
, , 250
4. (Socket Outlet and Plug) : - , , , ,
5. (Regulator) : -
0.75
1.25 -
- -
- 1- , 100 , ,
-
# - -
1 7/0.64 , 250 , , . . .
2 - 3/0.036 , 250 , , . .
3 10 , 230 , . ,
4 . . 15 , 250 . . , . .
5 3 , 10 , 250 . . .
6 . . 2. , 1/0.044 , 250 ,
7 6 x4 x2
8 1 ,2 ,
9 1/2 3/4 1
11 1.5
12 4/3
13 16 , 4/3
14 4/3
15 4/3
16 4/3
17 4/3
18 4 . . . (S.W.G)
19 ---
20 ---
21 3- ,5 250
22 6 , 11/2
23 1 x4 x 11/2
24 6 x4 x 11/2
25 2
26 4/3
27 , 5- , 250
#
(Describe the process of
installation of mechanical ventilation and air-
conditioning system in building) :
===============
(A) (Ventilation) :
Ventilation ,
Ventilation
# :
1. ,
2. - (Undue
accumulation) ,
3.
,
4.
,
5. ,
6. ,
7. , ,
8. ,
9. ,
10. , ,
#
1. (Rate of fresh air change)
2. (Control on humidity)
3. (Quality of air)
4. (Temperature)
5. (Use of building)
1.
- ,
60
60 60
(Fan)
# (Air space) -
# :
(Kitchen) :
(Passages) :
# :
(b) , —
1. Assemble Halls, Auditorium, Bedroom, Classroom, Office, Domestic kitchen, Hospital wards, Factories 3-6
2. Bath room and Toilets 6-12
3. Cafes and restaurants 12-15
4. Cinema halls and Theatres 6-9
5. Garages 12-15
6. Common kitchen 6-9
# ।
0-25% (Very dry)
25%-50% (Dry)
50%-75% (Humid)
75%-100% (Very humid)
3. (Quality of air) : , ,
, - , - 0.5 .
0.5 . . . (Part per million) -
0.06% -
4. (Temperature) :
8 10°C
21.7°C 23.9°C , , , ‘
# (Systems of ventilation) :
=============
# । :
1. (Natural Ventilation)
1. : , : ,
, , , , ,
# : -
1. ,
(Lee ward side) (Outlet opening)-
2. (Inlet) (Outlet) ,
,
3. (Stack effect)
4. , ,
5. ,
6. (Short)
7. , ,
8. ,
9. -
10. (Ridge)
11. , ,
12. ,
13. ,
14. - 2
2. ( ) :
, , ,
,
# ।
1. (Extraction or Exhaust system)
2. (Supply or Plenum system)
3. (Balancing system)
1. (Blower)
, ঐ
, , , ,
2.
,
, , , ,
(Air cleaner)
(B) (Air-conditioning) : , , ,
, ,
# : :
1. ,
2. , : , , , ,
3. , , ,
4. , , ,
5. ,
# :
=============
# ' ।
1. (Comfort air-conditioning) :
2. ৎ (Industrial air-conditioning) :
,
# । :
1. (Summer air- conditioning) :
#
1. (Temperature control) : , (Comfortable zone)
20°C-23°C 18:C-22°C
21°C 22°C-
2. (Humidity control) : 40% 50% 50% 60% 40%
60%
3. (Air velocity control) : 6
9
4. (Air quality control) : , ,
1. (Room air-conditioner)
2. (Packaged unit)
3. (Central direct expansion plants)
2. : , , (Evaporator)
, , ,
(Cooling capacity) 10000 ( 9000 - / )
3. , ,
(Duct)
, , , , ,
(b) :
# : -
1. (Capital cost)
2. (Running and operating cost)
3. (Space for the location of the equipment)
4. (Confort or industrial) (Type of application)
5. (Type of control) - (Rigit or industrial)
6. (Acoustic consideration) : : , TV ,
(Causes of fire) :
1.
2.
3.
4. -
5.
6.
7.
8.
(Stone) :
-
# (Timber) :
500°C
# :
1.
2. ( )
3. ,
,
4.
5.
# (Steel) : ,
600°C , 33%
(Unprotected.) (Sag) , ,
# (Glass) :
, ,
# (Cast iron) :
(Asbestos) : (Fibre)
# (Plaster or mortar) : , -
# ,
#
- 4
6 ,
# ,
1
# 120
# 90
# 15 . . . 6
# :
a)
b)
c)
# (Components) :
a) (Walls and columns)
b) (Floors and roofs)
# : :
1. (Thick) ,
2. - ,
3. ,
4. . . . (R.C.C)-
5. , , , ,
6. . . . , 40 50
25 40 25
7. , - . . . , , , , ,
(Metal lalth)
8. (Cavity wall)
9. ( - )-
# (Escape element) :
1. , : , , ,
2.
3.
4.
5. .
6.
7.
8. 90
9.
# : :
1.
2. , . . .
3. . .
4. ,
5. , ,
6. , , , , , ,
7. , , ,
# :
1. '
2.
3.
4. (Wire-glass panel)
5. , ,
1. , 30 . . .
,
2. (Anchor)
3.
4. 20
,
, -
# :
a) (Smoke detector)
b) (Heat detector)
c) (Flame detector)
d) (Gas detector)
#
1.
2. ,
3.
4.
5.
# , -
a) Physical or Ionization smoke detector
b) Optical or Photoelectric smoke detector.
# , -
a) Electromechanical heat detector
b) Optomechanical heat detector
c) Electro pneumatic heat detector
d) Electronic (Thermistor) heat detector,
# (Fire alarm) : ,
, (Tone)
, ,
,
(Alarm)
#
1.
2. (Americium) (Atom)
3.
4.
5. -
,
#
a) Optical chamber
b) Cover
c) Case moulding
d) Photodiode (Transducer)
e) Infrared LED (Light Emitting Diode)
4.
5.
(Alarm)
# (Heat detector) : , , , ,
,
(Resistance) (Base
voltage) (Emiter volttage) , (Buzzer)
(Sound)
PROFILE
As a fresh civil engineer, I bring a blend of theoretical knowledge and practical skills ready to tackle
real-world challenges. With a solid foundation in structural analysis, project management, and design
CONTACT principles, I am eager to contribute to innovative solutions in the construction industry. My academic
achievements and internships have honed my ability to collaborate effectively in multidisciplinary
teams while adhering to strict timelines and budgets. I am passionate about sustainable practices and
Address:
strive to integrate them into every project I undertake. As I embark on my career journey, I am
Vill: Baishtila, P.O: Lakhaura,
committed to continuous learning and professional growth within the field of civil engineering.
P.S: Khadhimnagor, Upzilla: Sadar,
Dis: Sylhet, Country: Bangladesh.
Phone:
+880 14063 68135 EDUCATION
Email: Diploma in Civil Engineering.
Rayenreza.ibrahim@gmail.com Headway Engineering Institute.
July - 2020 / October - 2024
"Hands-on experience in structural analysis, construction management, and sustainable design, with
a focus on practical application and innovation."
SKILLS
Bachelor of Arts.
National University.
Structural Design Dakshin Surma Govt. College.
Structural Drawing October - 2019 / November - 2023
Cost Estimates "Dedicated BA Bangla student exploring language, literature, and culture, driven by curiosity and
Construction Projects commitment to learning and growth."
Site Development
Inspection Materials
Land Surveying
EXPERIENCE
Construction Management
Budget Management Internship of Civil Engineering.
Public Works Department, Sylhet.
Extra: June - 2024 / October - 2024
IT Knowledge "Dynamic Civil Engineering intern with a focus on practical application, problem-solving, and
MS Office contributing to sustainable infrastructure development."
Photoshop
Illustrator Computer Operator.
Data Entry Boisakhi Library & Stationery, Sylhet.
November - 2017 / Now
"I work part time in my shop along with my studies. Experienced in providing various online service."
SOCIAL
Facebook:
@RayenReza.Ibrahim
CERTIFICATIONS
Linkedin:
Digital Marketing.
@RayenReza.Ibrahim
Sheikh Kamal IT Training & Incubation Center.
Instagram:
February - 2024 / June – 2024
@RayenReza.Ibrahim
Graphics Design & Multimedia Programming.
Bangladesh Technical Education Board, Dhaka.
Whatsapp:
+880 16099 38307 January - 2022 / June – 2022
MS Office Application.
Facebook Page:
@Civil Engineering Youth Development Computer Academy.
January - 2019 / June - 2019