Fuel Pipe Micro Schedule
Fuel Pipe Micro Schedule
APPROVED ENDORSEMENT:
End Date : 02 / 07 / 2025 Pipe System Legend BESCON CONSULTING ENGINEERS PTE
TO COMPLY WITH SPEC
NO OBJECTION
&/OR DRAWINGS
Part 4 : Part 2 : Part 3 : LEGEND DESCRIPTION PIPE SIZE MATERIAL REJECTED REVISE & RESUBMIT
24/06/2025 23/06/2025 23/06/2025 NO RESUBMISSION
COMMENTS TO BE NOTED
-Positioning bracket and Pipe (Unskill worker & Supervisor) -To complete internal Joint -Positioning bracket and Pipe (Unskill worker & Supervisor) REQUIRED
25/06/2025 -To coordinating and position for outer bracket -Welding inner Layer (2 6G Welder, 2 4G Welder) FFP Fuel Filling Pipe 80/125 mm API PIPE Sch-40 REVIEW OF SHOP DRAWINGS IS ONLY FOR CONFORMITY WITH THE DESIGN
CONCEPT & INTENT OF THE INSTALLATION, SPECIFICATION & DRAWINGS.
-Positioning bracket and Pipe (Unskill worker & Supervisor) -Welding inner & outer Layer (2 6G Welder, 2 4G 24/06/2025 FRP-A Fuel Return Pipe A 100/150 mm
THE CONTRACTOR/SUB-CONTRACTOR SHALL NOT BE RELIEVED OF THEIR
API PIPE Sch-40 RESPONSIBILITY FOR ACCURACY OF DETAILS & DIMENSIONS OF
-Welding inner Layer (1 6G Welder, 2 4G Welder) Welder) -Welding inner & Outer Layer (2 6G Welder, 2 4G Welder) EQUIPMENT AND SPACE PROVISIONS/CONSTRAINTS, COORDINATION WITH
OTHER TRADES & SERVICES, FULL COMPLIANCE WITH THE
26/06/2025 24/06/2025 25/06/2025 FRP-B Fuel Return Pipe B 100/150 mm API PIPE Sch-40 REQUIREMENTS OF THE SPECIFICATION, ETC.
-Welding inner & outer layer (2 6G Welder, 2 4G Welder) -Welding outer layer (2 6G Welder, 2 4G Welder) -Welding Outer Layer (2 6G Welder, 2 4G Welder)
FSP-A Fuel Supply Pipe A 80/125 mm API PIPE Sch-40
27/06/2025 25/06/2025 26/06/2025 SIGN: DATE:
-Welding outer layer (2 6G Welder, 2 4G Welder) -Welding Outer layer (1 6G Welder) -Welding Outer Layer (2 6G Welder, 2 4G Welder) FSP-B Fuel Supply Pipe B 80/125 mm API PIPE Sch-40 M.A.N ARCHITECTS LLP
28/06/2025 -RT Test 27/06/2025 NO EXCEPTIONS TAKEN, MAY PROCEED
-Welding outer layer (2 6G Welder) FVP Fuel Vent Pipe 80/125 mm API PIPE Sch-40
788 788
-Welding Outer Layer (1 6G Welder) MAKE CORRECTIONS
NOTED, DO NOT RE-SUBMIT
REJECTED AND
RE-SUBMIT
26/06/2025 -RT Test LDCP Leak Detection Cable Pipe 50 mm API PIPE Sch-40 REVISE AND RE-SUBMIT OTHERS
29/06/2025 Haunching 813
Haunching 28/06/2025 813 813 813
788 788
SIGN: DATE:
E
1 2 A
TANK - 1 3
Haunching
TANK - 2 4 TANK - 3 5
TANK - 4 6 7
REFILLING POINT JOSEPH & ANG ENGINEERS
VENT PIPES
625
625
625
625
C
D TANK - 1 TANK - 2
UNDERGROUND FUEL TANK TANK - 3 TANK - 4 NO EXCEPTIONS TAKEN, MAY PROCEED
FVP
FVP 69000 MAKE CORRECTIONS REJECTED AND
Part 5 :
4000
2750
2750
2750
FVP FVP FVP FVP FVP RE-SUBMIT
1 RAMP UP NOTED, DO NOT RE-SUBMIT
FVP 3600 8400 FFP 10800 FFP 10800 FFP 10800 FFP 10800 10200 3600
26/06/2025 REVISE AND RE-SUBMIT OTHERS
IL-1:50
-Positioning bracket and Pipe (Unskill worker
FFP& Supervisor)
625
625
625
625
B
27/06/2025 FFP
FFP
5 SIGN: DATE:
FFP FSP-A
-Positioning bracket and Pipe (Unskill worker & Supervisor) FSP-A FRP-A
A 2 4G Welder) 4 FRP-B
3 FRP-B FRP-A 4 1 2 3 4 6
-Welding inner Layer (1 6G Welder, LDCP FSP-B 3 FSP-B NO. OF SUBMISSION 5
POWER & GENSET BLOCK 1 POWER & GENSET BLOCK 2
28/06/2025 POWER & GENSET BLOCK 2
UP
FVP
6
MP
FVP IL-1:50
-Welding inner & outer layer (2 6G Welder, 2 4G Welder) Part 1 : Done
150
IL-1:50
LDCP
-Welding outer layer (4 6G Welder)
FUTURE CHILLED
WATER PIPE SHAFT
IL-1:50
FUTURE CHILLED
WATER PIPE SHAFT
2 SL 4.20
FRP
SL 4.20
8700
150
FSP-B
-Welding outer layer (4 6G Welder) 2996 FUEL
4 welder inner joint FUEL
PIPE
1B
inner joint PIPE 0 Updated Refilling Vent pipe installation detail 30.04.25
20 joint 3days HR 1A
HR
outer 50 joint 4days
B
HR
HR
METER KIOSK
FUEL PUMP
ROOM B 30 joint 3days OWNER:
ST03 FUEL PUMPA/C PRODUCTION ROOM 5 ST Engineering Cloud And
HR
4200 N/V ROOM B 1 LV ROOM B A/C
IL-1:50
A/C PUMP ROOM -B M/V BATTERY ROOM 1 BATTERY ROOM 2 FUEL PUMP Data Centre Solutions Pte Ltd
1
A/C A/C FUEL PUMP
HDC3 PUMP ROOM -A
FL 4.20
BATTERY ROOM 3 BATTERY ROOM 4 PROJECT MANAGER :
STORE
(2M HT CABLE
A/C A/C
N/V
ISOLATION
ROOM
A/C outer 4 welder SECURITY
MECHANICAL & ELECTRICAL ENGINEER:
38400
SINK
ROOM 1
MOP
C 70 joint 6days inner joint N/V Bescon Consulting Engineers Pte
30 joint 3days Block 2 Joo Chiat Road
DOMESTIC BATTERY ROOM 7 BATTERY ROOM 8 Joo Chiat Complex
NeWATER WATER A/C A/C Singapore 420002
PUMP PUMP CONSUMER HT SWITCH ROOM A
ROOM ROOM
outer A/C
Tel: 6293 2611
LOADING BAY 2 LOADING STAGING/ BATTERY ROOM 12 50 joint 5days (2M HT CABLE
CHAMBER
150
DECK B UNPACKING/
RECEIVING AREA
A/C ROOM BELOW) ARCHITECT:
M/V
10200
LOADING BAY 1
TRANSFER
TANK STORE
STORAGE ROOM
STRUCTURAL ENGINEER:
1
A/C CORRIDOR 1
A/C DN
AE Joseph & Ang Engineers
SC2 BIN POINT 16 Arumugam Road
HR
D N/V
HR
HR BMS MAN TRAP BMS2 LTC Building D #07-02/03
SPRINKLER
1 Singapore 409961
HR
MEETING ROOM
A/C 5500 Tel: 6846 9371
ST02 FCC
100 100
N/V A/V
FL 4.20 FIRE FIGHTING
DOMESTIC
WATER GOODS LIFT LOBBY
LOBBY 1
A/C
NEW BUFFER TANK
MAIN CONTRACTOR:
TRANSFER M/V SL 4.20
TANK NAKANO SINGAPORE (PTE) LTD
TOILET 2 MV
N/V MAIN LOBBY NO. 1 COLEMAN STREET #10-03/04/05
9300
PANTRY
P
U
A/C
SUB-CONTRACTOR:
P
AM
GL2 GL1 NOC ROOM CONFERENCE ROOM
R
(EMERGENCY OPS ROOM) A/C
A/C 50
PEAK TOP ENGINEERING PTE LTD
FL2 FL1 (ELECTRICAL INSTALLATION SERVICES)
MAIN FOYER/DRIVEWAY
DROP OFF BLK 1 ANG MO KIO INDUSTRIAL PARK 2A
E R
AM #03-08 ANG MO KIO TECH 1
150
U
P SINGAPORE 568049
P
RAMP UP 1:15
AM
P
ACCESSIBLE
PROJECT:
U
P
TOILET
N/V
PROPOSED ADDITION AND & ALTERATION TO
EXISTING INDUSTRIAL DEVELOPMENT INVOLVING
THE ERECTION OF NEW 7-STOREY SINGLE USER
DATA CENTER WITH ANCILLARY FACILITIES ON LOT
02622C MK 06 AT 249 JALAN BOON LAY SINGAPORE
619523
(JURONG WEST PLANNING AREA)
GRASSCELLS
ER
ET T
SPRINKLER TANK A
RM MH
TE ER 1
W MB
DRAWN BY: CHECKED BY:
A
CH
AUNG ZAW
DR
T&
AN ER SCALE: DATE:
HY RINKL OOM
OW SP MP R AS SHOWN 24 MAR 2025
EL
KB PU
AN
NT
TIO
T EN
DE
SERVICE: REV:
H YD
R AN
TT
AN
K
FO 1
DRAWING NO.:
NKN/STEDC/MEP/FO/101