Gasco LPG Facility

Daily Report No.: Forecast:


Temperature 7C Humidity 78%

Monthly Reports
Date: 14/02/2012

February 2012
Time: 08:00-15:00

Rain showers or hail, possibly locally thundery in places at first, and with a moderate to rather strong West to Northwest wind becoming rather strong.

Employees at the site:


Total workers onsite: 25

Tanko
Site Management

1 Welder

2 Workers

Tanko
Heavy Machinery Plant

Crane + Operator 2 Concrete Mixers + Drivers Site Supervisor

Fork Lifter + Operator

Bonnici BrothersLtd.
Heavy Machinery Plant

1 Truck + Driver

2 Workers

Kosan Crisplant
Site Management

1 Welder

3 Workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying of concrete beneath kerb to make up levels (photos 1-2) 2) Distribution of kerbs (photo 3) 3) Laying and fixing of expansion joints in concrete flooring between Cylinder Filling Shed and Cylinder Storage Shed (photo 4)

Tanko
4) Installing LPG pipes in LPG Pump Room (photos 5-7)

Kosan Crisplant
5) Installing LPG pipes in Cylinder Filling Shed (photo 8)

iASLimited

Page1of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 1

Monthly Reports
Date: 14/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 14/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 14/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 14/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page2of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 1

Monthly Reports
Date: 14/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 14/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 14/02/2012 Contractor: Tanko

Photo No.: 6 Date: 14/02/2012 Contractor: Tanko

iASLimited

Page3of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 1

Monthly Reports
Date: 14/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 14/02/2012 Contractor: Tanko

Photo No.: 8 Date: 14/02/2012 Contractor: Kosan Crisplant

iASLimited

Page4of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 9C Humidity 66%

Monthly Reports
Date: 15/02/2012

February 2012
Time: 08:00-15:00

Rather cloudy with isolated showers and with a strong to very strong West Northwest wind.

Employees at the site:


Total workers onsite: 27

Tanko
Site Management

1 Welder

4 Workers

Tanko
Heavy Machinery Plant

Crane + Operator

Bonnici BrothersLtd.
Heavy Machinery Plant

1 Concrete Mixer + Driver

1 Truck + Driver

5 Workers

Kosan Crisplant
Site Management

Site Supervisor

1 Welder

3 Workers

Mekanika
Site Management

1 Van + Driver

8 workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying of concrete to admin block stairs (photos 1) 2) L i of kerbs (photos 2-3) Laying f k b ( h t 2 3)

Mekanika
3) Painting of compressed air pipes (photo 4)

4) Installing cables and compressed air pipe (photos 5-6) Tanko


5) Installing LPG pipes in LPG Pump Room (photos 7-8)

Kosan Crisplant
6) Installing LPG pipes in Cylinder Filling Shed (photos 9-10)

iASLimited

Page5of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 2

Monthly Reports
Date: 15/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 15/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 15/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 15/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page6of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 2

Monthly Reports
Date: 15/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 15/02/2012 Contractor: Mekanika

Photo No.: 5 Date: 15/02/2012 Contractor: Mekanika

Photo No.: 6 Date: 15/02/2012 Contractor: Mekanika

iASLimited

Page7of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 2

Monthly Reports
Date: 15/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 15/02/2012 Contractor: Tanko

Photo No.: 8 Date: 15/02/2012 Contractor: Tanko

Photo No.: 9 Date: 15/02/2012 Contractor: Kosan Crisplant

iASLimited

Page8of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 2

Monthly Reports
Date: 15/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 15/02/2012 Contractor: Kosan Crisplant

iASLimited

Page9of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 10C Humidity 83%

Monthly Reports
Date: 16/02/2012

February 2012
Time: 08:00-15:00

Partly cloudy becoming mainly fine, and with a light to moderate North to Northeast wind

Employees at the site:


Total workers onsite: 31

Tanko
Site Management

Site Supervisor

2 Welders

4 Workers

Tanko
Heavy Machinery Plant

Crane + Operator

Bonnici BrothersLtd.
Heavy Machinery Plant

1 Concrete Mixer + Driver

1 Truck + Driver

5 Workers

Kosan Crisplant
Site Management

Site Supervisor

1 Welder

5 Workers

Mekanika
Site Management

1 Van + Driver

8 workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying of concrete to make up levels (photos 1-3) Laying f k b ( h t 4 5) 2) L i of kerbs (photos 4-5) 3) Casting of concrete columns next to weigh bridge (photo 6)

Mekanika
4) Painting of compressed air pipes (photo 7)

5) Installing compressed air pipe next to Cylinder Filling Shed (photo 8) Tanko
6) Installing LPG pipes & tagging of valves (photo 9)

Kosan Crisplant
7) Installing LPG pipes & machinery in Cylinder Filling Shed (photo 10)

iASLimited

Page10of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 3

Monthly Reports
Date: 16/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 16/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 16/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 16/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page11of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 3

Monthly Reports
Date: 16/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 16/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 16/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 16/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page12of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 3

Monthly Reports
Date: 16/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 16/02/2012 Contractor: Mekanika

Photo No.: 8 Date: 16/02/2012 Contractor: Mekanika

Photo No.: 9 Date: 16/02/2012 Contractor: Tanko

iASLimited

Page13of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 3

Monthly Reports
Date: 16/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 16/02/2012 Contractor: Kamoy

iASLimited

Page14of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 11C Humidity 49%

Monthly Reports
Date: 17/02/2012

February 2012
Time: 08:00-15:00

Fine with some clouds and with a light mainly Westerly wind

Employees at the site:


Total workers onsite: 27

Tanko
Site Management

1 Welder

3 Workers

Tanko
Heavy Machinery Plant

Crane + Operator

Forklift + Operator

Bonnici BrothersLtd.
Heavy Machinery Plant

1 Concrete Mixer + Driver

1 Truck + Driver

5 Workers

Kosan Cisplant
Site Management

Site Supervisor

1 Welder

3 Workers

Mekanika
Site Management

1 Van + Driver

8 workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying of concrete to make up levels (photos 1) Laying f k b ( h t 2 3) 2) L i of kerbs (photos 2-3) 3) Laying and fixing of dowels at expansion joints in concrete flooring (photos 4-5)

Mekanika
4) Installing gas pipe for AC's in Administration Block (photos6-7) 5) Painting of LPG pipes (photo 8) 6) Backfilling of gas tank next to Administration Block with fine sand (photos 9-10)

Tanko
7) Installing LPG pipes (photos 11-12) 8) Tagging of LPG valves (photos 13-14)

Kosan Crisplant
9) Installing machinery in Cylinder Filling Shed (photo 15)

iASLimited

Page15of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 4

Monthly Reports
Date: 17/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 17/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 17/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 17/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page16of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 4

Monthly Reports
Date: 17/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 17/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 17/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 17/02/2012 Contractor: Mekanika

iASLimited

Page17of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 4

Monthly Reports
Date: 17/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 17/02/2012 Contractor: Mekanika

Photo No.: 8 Date: 17/02/2012 Contractor: Mekanika

Photo No.: 9 Date: 17/02/2012 Contractor: Mekanika

iASLimited

Page18of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 4

Monthly Reports
Date: 17/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 17/02/2012 Contractor: Mekanika

Photo No.: 11 Date: 17/02/2012 Contractor: Tanko

Photo No.: 12 Date: 17/02/2012 Contractor: Tanko

iASLimited

Page19of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 4

Monthly Reports
Date: 17/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 13 Date: 17/02/2012 Contractor: Tanko

Photo No.: 14 Date: 17/02/2012 Contractor: Tanko

Photo No.: 15 Date: 17/02/2012 Contractor: Kosan Crisplant

iASLimited

Page20of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 14C Humidity 61%

Monthly Reports
Date: 20/02/2012

February 2012
Time: 08:00-15:00

Cloudy with rain showers and with a light Easterly wind

Employees at the site:


Total workers onsite: 28

Tanko
Site Management

1 Welder

3 Workers

Tanko
Heavy Machinery Plant

Crane + Operator

Forklift + Operator

Bonnici Brothers Ltd.


Heavy Machinery Plant

9 Workers

Kosan Crisplant
Site Management

Site Supervisor

7 Workers

Mekanika
Site Management

5 Workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying of kerbs (photos 1-2) Removal of material to reduced levels (photo 3) 2) R l f t i lt d dl l ( h t 3) Laying and fixing of dowels at expansion joints in concrete flooring (photos 4-7)

Mekanika
4) Painting of fire fighting pipes (photos 8-9)

Tanko
5) Installing LPG pipes in LPG Pump Room (photos 10-12)

Kosan Crisplant
6) Installing machinery in Cylinder Filling Shed (photos 13-14)

iASLimited

Page21of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 5

Monthly Reports
Date: 20/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 20/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 20/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 20/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page22of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 5

Monthly Reports
Date: 20/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 20/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 20/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 20/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page23of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 5

Monthly Reports
Date: 20/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 20/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 8 Date: 20/02/2012 Contractor: Mekanika

Photo No.: 9 Date: 20/02/2012 Contractor: Mekanika

iASLimited

Page24of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 5

Monthly Reports
Date: 20/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 20/02/2012 Contractor: Tanko

Photo No.: 11 Date: 20/02/2012 Contractor: Tanko

Photo No.: 12 Date: 20/02/2012 Contractor: Tanko

iASLimited

Page25of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 5

Monthly Reports
Date: 20/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 13 Date: 20/02/2012 Contractor: Kosan Crisplant

Photo No.: 14 Date: 20/02/2012 Contractor: Kosan Crisplant

iASLimited

Page26of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 12C Humidity 95%

Monthly Reports
Date: 21/02/2012

February 2012
Time: 08:00-15:00

Rather cloudy with showers and with a rather strong Southeast wind

Employees at the site:


Total workers onsite: 15

Tanko
Heavy Machinery Plant

Crane

Forklift

Bonnici Brothers Ltd.


Heavy Machinery Plant

3 workers

Bonnici Brothers Ltd.


Heavy Machinery Plant

1 BOBCAT + Operator

1 Concrete 1 Excavator + Mixer + Driver Operator

Kosan Crisplant
Site Management

2 Site Supervisor

7 Workers

Mekanika
Site Management

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Provision of trench to accommodate sleeves and back filling with concrete (photo1) t ( h t 1) 2) Backfilling kerbs with concrete (photos 2-3)

Mekanika
No work due to increment weather

Tanko
No work due to increment weather

Kosan Crisplant
3) Installing machinery in Cylinder Filling Shed (photos 4-6)

iASLimited

Page27of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 6

Monthly Reports
Date: 21/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 21/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 21/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 21/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page28of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 6

Monthly Reports
Date: 21/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 21/02/2012 Contractor: Kosan Crisplant

Photo No.: 5 Date: 21/02/2012 Contractor: Kosan Crisplant

Photo No.: 6 Date: 21/02/2012 Contractor: Kosan Crisplant

iASLimited

Page29of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 11C Humidity 83%

Monthly Reports
Date: 22/02/2012

February 2012
Time: 08:00-15:00

Cloudy with showers and with a moderate to rather strong Southwest becoming Southeast wind

Employees at the site:


Total workers onsite: 36

Tanko
Site Management

Crane + Operator

Forklift + Operator

3 Workers

Bonnici Brothers Ltd.


Site Management

Land Surveyor + Assistant


(road levels)

Land Surveyor + Assistant


(Setting street lights)

Bonnici Brothers Ltd.


Heavy Machinery Plant

1 Concrete 1 Excavator + Mixer + Driver Operator

10 Workers

Kosan Crisplant
Site Management

2 Site Supervisors

6 Workers

Mekanika
Site Management

7 Workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying of concrete beneath kerb to make up levels (photo 1) 2) Laying of kerbs (photos 2-3) 3) Removal of material to reduce levels (photo 4) 4) Laying and fixing of reinforcement in concrete flooring between Cylinder Filling Shed and Cylinder Storage Shed (photos 5-7) 5) Setting out road markings (photo 8) 6) Setting out street lights (photo 9)

Mekanika
7) Painting of fire fighting pipes (photo10) 8) Installing cables (photo 11-12)

Tanko
9) Installing LPG Arm adjacent to weigh bridge (photos 13-14)

Kosan Crisplant
10) Installing machinery in Cylinder Filling Shed (photos 15-17)

iASLimited

Page30of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 7

Monthly Reports
Date: 22/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page31of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 7

Monthly Reports
Date: 22/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page32of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 7

Monthly Reports
Date: 22/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 8 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 9 Date: 22/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page33of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 7

Monthly Reports
Date: 22/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 22/02/2012 Contractor: Mekanika

Photo No.: 11 Date: 22/02/2012 Contractor: Mekanika

Photo No.: 12 Date: 22/02/2012 Contractor: Mekanika

iASLimited

Page34of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 7

Monthly Reports
Date: 22/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 13 Date: 22/02/2012 Contractor: Tanko

Photo No.: 14 Date: 22/02/2012 Contractor: Tanko

Photo No.: 15 Date: 22/02/2012 Contractor: Kosan Crisplant

iASLimited

Page35of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 7

Monthly Reports
Date: 22/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 16 Date: 22/02/2012 Contractor: Kosan Crisplant

Photo No.: 17 Date: 22/02/2012 Contractor: Kosan Crisplant

iASLimited

Page36of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 10C Humidity 87%

Monthly Reports
Date: 23/02/2012

February 2012
Time: 08:00-15:00

Mostly cloudy with rain showers, which may be locally thundery at times, becoming less frequent and with bright spells later on

Employees at the site:


Total workers onsite: 27

Tanko
Site Management

Site Supervisor

1 Welder

3 Workers

Tanko
Heavy Machinery Plant

Crane

Forklift

Bonnici BrothersLtd.
Heavy Machinery Plant

1 Crane + Operator

1 Trailer + Driver

10 Workers

Kosan Crisplant
Site Management

Site Supervisor

6 Workers

Mekanika
Site Management

1 Van + Driver

2 Workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying and fixing of reinforcement in concrete flooring between C li d Filling Shed and Cylinder Storage Shed (photo 1) Sh d ( h t Cylinder Filli Sh d d C li d St 2) Laying of kerbs (photos 2-3) 3) Laying of concrete beneath kerb to make up levels (photo 4-5) 4) Concrete flooring between Cylinder Filling Shed and Cylinder Storage Shed have been suspended due to increment weather

Mekanika
5) Checking compressed air pipe (photo 6)

Tanko
6) Installing LPG pipes in LPG Pump Room and LPG Arm next to weigh bridge (photos 7-8)

Kosan Crisplant
7) Installing machinery in Cylinder Filling Shed (photo 9)

Notes
8) Water leaks in Cylinder Filling Shed (photos 10-12) 9) Water leaks in Administration Block (photos 13-15) 10) Works have been temporary suspended in the morning due to increment weather

iASLimited

Page37of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 8

Monthly Reports
Date: 23/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 23/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 23/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 23/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page38of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 8

Monthly Reports
Date: 23/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 23/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 23/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 23/02/2012 Contractor: Mekanika

iASLimited

Page39of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 8

Monthly Reports
Date: 23/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 23/02/2012 Contractor: Tanko

Photo No.: 8 Date: 23/02/2012 Contractor: Tanko

Photo No.: 9 Date: 23/02/2012 Contractor: Kosan Crisplant

iASLimited

Page40of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 8

Monthly Reports
Date: 23/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 23/02/2012 Contractor: Notes

Photo No.: 11 Date: 23/02/2012 Contractor: Notes

Photo No.: 12 Date: 23/02/2012 Contractor: Notes

iASLimited

Page41of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 8

Monthly Reports
Date: 23/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 13 Date: 23/02/2012 Contractor: Notes

Photo No.: 14 Date: 23/02/2012 Contractor: Notes

Photo No.: 15 Date: 23/02/2012 Contractor: Notes

iASLimited

Page42of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 14C Humidity 70%

Monthly Reports
Date: 24/02/2012

February 2012
Time: 08:00-15:00

Sunny during the day and fine during the night with light mainly Northwest wind

Employees at the site:


Total workers onsite: 24

Tanko
Site Management

1 Welder

3 Workers

Tanko
Heavy Machinery Plant

Crane + Operator

Forklift + Operator

Bonnici BrothersLtd.
Heavy Machinery Plant

6 Workers

Kosan Crisplant
Site Management

Site Supervisor

6 Workers

Mekanika
Site Management

1 Van + Driver

4 workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying of kerbs (photo 1) Laying d fi i 2) L i and fixing of reinforcement in concrete flooring around f i f ti t fl i d Full Cylinder Storage Shed (photos 2-4) 3) Repair works in reservoir (photos 5-6)

Mekanika
3) Painting of light poles (photos 7-8) 4) Installing cables in Full Cylinder Storage Shed and Control Room (photos 9-10)

Tanko
5) Welding LPG pipes (photo 11-12)

Kosan Crisplant
6) Testing machinery in Cylinder Filling Shed (photo 13)

iASLimited

Page43of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 9

Monthly Reports
Date: 24/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 24/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 24/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 24/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page44of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 9

Monthly Reports
Date: 24/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 24/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 24/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 24/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page45of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 9

Monthly Reports
Date: 24/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 24/02/2012 Contractor: Mekanika

Photo No.: 8 Date: 24/02/2012 Contractor: Mekanika

Photo No.: 9 Date: 24/02/2012 Contractor: Mekanika

iASLimited

Page46of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 9

Monthly Reports
Date: 24/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 24/02/2012 Contractor: Mekanika

Photo No.: 11 Date: 24/02/2012 Contractor: Tanko

Photo No.: 12 Date: 24/02/2012 Contractor: Tanko

iASLimited

Page47of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 9

Monthly Reports
Date: 24/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 13 Date: 24/02/2012 Contractor: Kosan Crisplant

iASLimited

Page48of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 11C Humidity 77%

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

10

Partly to rather cloudy with the possibility of isolated showers at first, becoming mainly sunny

Employees at the site:


Total workers onsite: 29

Tanko
Site Management

1 Welder

4 Workers

Tanko
Heavy Machinery Plant

1 Crane + Operator 2 Concrete Mixers + Drivers

1 Forklift + Operator

Bonnici BrothersLtd.
Heavy Machinery Plant

1 Foreman

7 Workers

Kosan Crisplant
Site Management

Mekanika
Site Management

1 Van

11 Workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying of concrete flooring around Full Cylinder Storage Shed (photos 1 6) ( h t 1-6) 2) Laying of concrete beneath kerb to make up levels (photos 7-9) 3) Laying of kerbs (photo 10) 4) Removal of material to reduced elvels (photos 11-12)

Mekanika
5) Painting of compressed air pipe (Blue) (photos 13-14) 6) Replacing faulty joints in compressed air pipe (photo 15) 7) Installing switch board in Cylinder Filling Shed (photo 16) 8) Installing switch board in LPG Pump Room (photo 17) 9) Installing cables (photo 18) 10) Installing light fittings in Manifold Area (photos 19-20) 11) Installing cable trays for LPG gas sensors (photos 21-22)

Tanko
12) Bolting LPG pipes in place (photos 23-24) 13) Connecting LPG pipes to LPG Arm next to weigh bridge (photos 25-26) 14) Welding LPG pipes (photo 27)

iASLimited

Page49of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page50of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page51of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 8 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 9 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page52of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 11 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 12 Date: 27/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page53of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 13 Date: 27/02/2012 Contractor: Mekanika

Photo No.: 14 Date: 27/02/2012 Contractor: Mekanika

Photo No.: 15 Date: 27/02/2012 Contractor: Mekanika

iASLimited

Page54of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 16 Date: 27/02/2012 Contractor: Mekanika

Photo No.: 17 Date: 27/02/2012 Contractor: Mekanika

Photo No.: 18 Date: 27/02/2012 Contractor: Mekanika

iASLimited

Page55of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 19 Date: 27/02/2012 Contractor: Mekanika

Photo No.: 20 Date: 27/02/2012 Contractor: Mekanika

Photo No.: 21 Date: 27/02/2012 Contractor: Mekanika

iASLimited

Page56of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 22 Date: 27/02/2012 Contractor: Mekanika

Photo No.: 23 Date: 27/02/2012 Contractor: Tanko

Photo No.: 24 Date: 27/02/2012 Contractor: Tanko

iASLimited

Page57of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 10

Monthly Reports
Date: 27/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 25 Date: 27/02/2012 Contractor: Tanko

Photo No.: 26 Date: 27/02/2012 Contractor: Tanko

Photo No.: 27 Date: 27/02/2012 Contractor: Tanko

iASLimited

Page58of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 11C Humidity 47%

Monthly Reports
Date: 28/02/2012

February 2012
Time: 08:00-15:00

11

Mainly sunny becoming partly cloudy at times with a light to moderate Northwest wind

Employees at the site:


Total workers onsite: 32

Tanko

1 Welder

4 Workers

1 Crane + Operator

Tanko

1 Forklift + Operator 2 Concrete Mixers + Drivers

Bonnici BrothersLtd.

1 Crane + Operator

10 Workers

Kosan Crisplant

Mekanika

1 Van

11 Workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Laying and fixing of reinforcement in concrete flooring around Full C li d St F ll Cylinder Storage Shed (photos 1-2) Sh d ( h t 1 2) 2) Laying of concrete flooring around Full Cylinder Storage Shed (photos 3-6) 3) Laying of concrete beneath kerb to make up levels (photos 7-8) 4) Backfilling kerb with concrete (photo 9) 5) Laying of kerbs (photos 10-11) 6) Laying of reinforcement in front of administration block (photo 12)

Mekanika
7) Painting of compressed air pipes (photos 13-14) 8) Fixing of water valve (photo 15) 9) Installing cables above LPG Tanks (photos 16-18) 10) Installing light fittings in Manifold Area (photo 19)

Tanko
11) Fixing of ------- in manifold Area (photo 20) 12) Welding LPG pipes (photo 21)

iASLimited

Page59of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 11

Monthly Reports
Date: 28/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page60of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 11

Monthly Reports
Date: 28/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page61of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 11

Monthly Reports
Date: 28/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 8 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 9 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page62of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 11

Monthly Reports
Date: 28/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 11 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 12 Date: 28/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page63of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 11

Monthly Reports
Date: 28/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 13 Date: 28/02/2012 Contractor: Mekanika

Photo No.: 14 Date: 28/02/2012 Contractor: Mekanika

Photo No.: 15 Date: 28/02/2012 Contractor: Mekanika

iASLimited

Page64of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 11

Monthly Reports
Date: 28/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 16 Date: 28/02/2012 Contractor: Mekanika

Photo No.: 17 Date: 28/02/2012 Contractor: Mekanika

Photo No.: 18 Date: 28/02/2012 Contractor: Mekanika

iASLimited

Page65of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 11

Monthly Reports
Date: 28/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 19 Date: 28/02/2012 Contractor: Mekanika

Photo No.: 20 Date: 28/02/2012 Contractor: Tanko

Photo No.: 21 Date: 28/02/2012 Contractor: Tanko

iASLimited

Page66of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: Forecast:
Temperature 13C Humidity 56%

Monthly Reports
Date: 29/02/2012

February 2012
Time: 08:00-15:00

12

Sunny becoming partly cloudy with a moderate Northerly wind becoming light and variable

Employees at the site:


Total workers onsite: 27

Tanko

2 Welders

2 Workers

1 Crane + Operator

Tanko

1 Forklift + Operator 1 Concrete Mixer + Operator 2 Trucks + Drivers

Bonnici BrothersLtd.

5 Workers

Mekanika

1 Forklift

1 Site Manager

Mekanika

1 Foreman

1 Forklift

9 Workers

Performance level:
(See photos)

Bonnici Bros. Ltd.


1) Casting of concrete in front of Administration Block (photos 1-3.) 2) R Removal of kerb next to Full Cylinder Storage Shed (photos 4-5) l fk b t t F ll C li d St Sh d ( h t 4 5) 3) Preparing epansion joints in concrete flooring (photo 6)

Mekanika
4) Installing cables (photo 7) 5) Fixing cable tray next to Cylinder Filling Shed (photo 8) 6) Delivery of Fire & Gas Panel (photos 9-10)

Tanko
7) Welding LPG Pipes (photo 11)

iASLimited

Page67of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 12

Monthly Reports
Date: 29/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 1 Date: 29/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 2 Date: 29/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 3 Date: 29/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page68of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 12

Monthly Reports
Date: 29/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 4 Date: 29/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 5 Date: 29/02/2012 Contractor: Bonnici Bros. Ltd.

Photo No.: 6 Date: 29/02/2012 Contractor: Bonnici Bros. Ltd.

iASLimited

Page69of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 12

Monthly Reports
Date: 29/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 7 Date: 29/02/2012 Contractor: Mekanika

Photo No.: 8 Date: 29/02/2012 Contractor: Mekanika

Photo No.: 9 Date: 29/02/2012 Contractor: Mekanika

iASLimited

Page70of71

MichaelCutajar SiteCoordinator

Gasco LPG Facility


Daily Report No.: 12

Monthly Reports
Date: 29/02/2012

February 2012
Time: 08:00-15:00

Photo No.: 10 Date: 29/02/2012 Contractor: Mekanika

Photo No.: 11 Date: 29/02/2012 Contractor: Tanko

iASLimited

Page71of71

MichaelCutajar SiteCoordinator