Obtain scope of work -base and specific scope obtain blind list. Verify access, requirement of scaffolding, crane, insulation removal and conditions of fasteners. Verify Level III schedule and Level IV schedule. If any discrepancies in the job scope / duration / blind list sort it out.
Obtain scope of work -base and specific scope obtain blind list. Verify access, requirement of scaffolding, crane, insulation removal and conditions of fasteners. Verify Level III schedule and Level IV schedule. If any discrepancies in the job scope / duration / blind list sort it out.
Obtain scope of work -base and specific scope obtain blind list. Verify access, requirement of scaffolding, crane, insulation removal and conditions of fasteners. Verify Level III schedule and Level IV schedule. If any discrepancies in the job scope / duration / blind list sort it out.
Carry out site visit, study blind locations, verify access, requirement of scaffolding, crane, insulation removal and conditions of fasteners etc Access the job scope and finalize manpower, equipment and verify the resource deployment plan. verify Level III schedule and Level IV schedule If any discrepancies in the job scope/ duration/ blind list sort it out. Obtain final scope and signed blind list Obtain approval for temporary lay down Access the blind requirement and initiate action to procure unavailable blinds Shift all the blind from the blind yard and segregate equipment wise
PRE SHUTDOWN ACTIVITES Prepare rigging study for critical lifts, prepare method statements for each and every activity, prepare ITP, HIRA Compile shutdown package Initiate action to procure required spares, fasteners, gaskets etc and ensure availability of all spares before shutdown Finalize subcontract requirement and engage subcontractors Ensure availability of tested hoses for draining, purging and steaming out. Ensure availability of PICWS, man hole watcher, fire watcher and certified rigger.
PRE SHUTDOWN ACTIVITES Ensure availability of all tools and tackles (certified) Ensure all the lifting tools and tackles are certified and color coded Ensure availability of all materials, gaskets, spares Erect scaffolding in advance wherever required (external) Carry out tagging of all blind locations and valves (2 tag system to be followed for valves) Permits to be originated, reviewed and validated as per the scope of work. Remove insulation where ever required Shift all the required blinds to the location
PRE SHUTDOWN ACTIVITES Establish site lay down facility Mobilize all materials to site material container Shift all required tools to site tools container Ensure availability of necessary spools/ fitting to connect hoses Ensure availability of all necessary test fittings for exchangers Shift trays for fin fan coolers to location Upon permission from operation connect hoses for nitrogen and steam purging PRE SHUTDOWN ACTIVITES Mobilize all the required subcontractors at site Arrange all necessary PPE and consumables Ensure all the mobilized equipments meet the requirement of safety norms and approval, basic needs for equipments are Chalwyn valve, spark arrestor, battery switch, battery cover, third party certification for hoses, lifting tackles, third party certification for pressure gauges etc Ensure availability of sufficient quantity of suitable range of pressure gauges Ensure availability of required Qty of drums , pallets for catalyst handling works PRE SHUTDOWN ACTIVITES Shift all the drums with pallets to location If there is catalyst handling works establish the catalyst extraction system in place Ensure availability of SCBA, Breathing apparatus to carry out blinding etc, refilling facility Assist with operation for connecting the purging hoses, valve closing and CD/OD reversal
PRE SHUTDOWN ACTIVITES Obtain permit as per the scheduled job Validated permits shall be issued by shift controller Accepted by the contractor Accepted by PICWS Endorsed by asset operator 1 and 2 Tool box talk by supervisor and safety officer regarding job scope, hazards and control measures. Blinding as per the blind list and obtain isolation certificate. Manway open, ventilation and obtain gas test certificate Obtain confined space entry. Confined space attendant to be engaged for monitor the entry and exit timings SHUTDOWN ACTIVITIES SHUTDOWN ACTIVITIES
All the bottom nozzles to be covered with metal box to prevent foreign material entry. Offer preliminary inspection to QC and get recommendation. Erect internal scaffolding Based on QC recommendation and scope, complete all the activates Offer for final inspection and obtain box-up certificate from QC, process, maintenance and operation. Carry out equipment box-up, de-blinding and torquing Torquing witness by QC and maintenance Housekeeping
Assist with operation for start up activates Disconnect all hoses, restore the insulation and remove all external scaffolding Shift all containers, tools and equipment from the temporary lay down to permanent lay down. After successful commissioning obtain FAC from QC, planning, operation and maintenance Summit close out report