Observe the video in which two persons are
drilling holes on a part of unfinished chair
Carry out a method study
Suggest improvement options
Evaluate each option
10-08-2014 2
SELECT
RECORD
EXAMINE
DEVELOP
EVALUATE
DEFINE
INSTALL
MAINTAIN
10-08-2014 3
Process considered is drilling of holes
Factors considered during process selection:
Economic No. of units produced apprx 1000 units
are produces per day in 8 hr shift
Technological Type of machine being used hand
drill, jig
Human position and movement of worker adding
non-value activity
10-08-2014 4
Following activities are considered in the
selected process:

10-08-2014 5
Activity No. Person 1 Person 2
1 Picks up the job Holding the cover of jig
2 Places the job on jig Holding the cover of the jig
3 Holds the job in place Places the cover on the job
4 Upper cover is clamped Upper cover is clamped
5 Idle Picks up drill and drills 8 holes
6 Idle Changes the drill and drills 10
holes
7 Unclamping of cover Unclamping of cover
8 Idle Removes and holds the cover
9 Unloads the job Holds cover in hand
10 Places the job down and
moves to pick next job
Holding the cover in hand
Flow process chart is developed based on the activities.
Timings for each activity is classified

10-08-2014 6
Following options are suggested
1. Whole process can be done by single person.
Second person can do the same process separately,
thus increasing production
2. Single clamp jigs can be provided to reduce the
clamping time
3. Loading and unloading can be push + gravity
operated
4. Provide proper sitting/ standing facility
5. Hang the drills, thus eliminating need for movement
6. Provide facility for loading more than one job
10-08-2014 7
10-08-2014 8
Opn Objective Weightage
1 Decreasing labour cost. Increasing production
production rate.
0.3
2 Reduction in operation time clamping
operation
0.2
3 Reducing transportation time loading and
unloading AND reduced human effort
0.1
4 Comfort of operation 0.1
5 Reduce operation time drilling operation AND
AND reduce transportation time movement of
movement of drills
0.2
6 Increase production rate 0.1
Defining clearly the processes based on
selected improvement options
Installation of improvement options
Standardising and maintaining the improved
processes
10-08-2014 9
10-08-2014 10