Professional Documents
Culture Documents
Delayimpactanalysis Timeimpactanalysis 130708110922 Phpapp02
Delayimpactanalysis Timeimpactanalysis 130708110922 Phpapp02
Delayimpactanalysis Timeimpactanalysis 130708110922 Phpapp02
Disclaimer
Information contained within this presentation is for education purposes only.
How a programme or schedule is built, maintained and managed is the
responsibility of the owning organisation. Focus Planning Ltd accepted no
responsibility for changes made to programmes or schedules which are altered
as a result of reading slides contained within this presentation. The
configuration and settings of computer software are the responsibility of the
license holders and Focus Planning Ltd accept no liability for the configuration
used by the license holder.
Process Steps
In order to successfully identify the delay the following steps should be
followed;
Determine the
baseline schedule
Determine As-Built
data source
Review results
Communicate
Now the fragnet has been accepted by the project team it will need
incorporating in to the current schedule.
Going back to the current schedule take a new baseline to record the dates
per-fragnet. This baseline is for records purposes and does not need assigning
at this stage.
Now using the accepted fragnet, enter the delay activities in to the current
programme with the logic as agreed and link to the effected successors in the
schedule.
Now reduce the delay activities durations to zero days and re-schedule the
project. The Project Completion date should still remain the same as the new
activities have zero duration. As we assigned the baseline in Step 2 you can
check this is the case by adding the baseline bars in the Gantt Chart or by
adding the Variance BL Project Finish Date column to the activity table
(value should be zero)
Focus Planning Ltd
10
Re-schedule and you will see the bars from the fragnet increase and the remaining
activities push out moving the project completion date.
11
12
13
14