Professional Documents
Culture Documents
nodes .
Critical Path
Schwalbe
Problem-1
Tasks/Activiti
Time (Days)
A
B
C
D
E
F
G
H
I
2
3
4
1
2
5
7
2
3
es
Required
Predecessor
s
A
B
B
C
D,E
F,G
Problem-2
Tasks/Activiti
es
Time
(Months)
A
B
C
D
E
F
5
1
2
4
6
3
Required
Predecessor
s
B
A,C
A
D,E
1.
2.
Schedule Trade-offs
Example:
PERT weighted average =
8 workdays + 4 X 10 workdays + 24 workdays = 12
days
6
where:
optimistic time= 8 days
most likely time = 10 days
pessimistic time = 24 days
Therefore, youd use 12 days on the network diagram
instead of 10 when using PERT for the above example.
Problem on PERT
The following table gives details about the various activities of a project . Find
(a) The Critical path of the project and its expected duration . (b) the probability
that the project will be completed within 50 days .
Activity
Node
A
B
C
D
E
F
G
H
I
J
1-2
2-3
2-4
2-5
3-6
4-6
5-7
6-7
7-8
7-9
10
6
5
1
3
4
1
3
9
3
11
10
8
5
7
9
2
7
12
5
12
14
11
9
5
14
3
11
15
7