Professional Documents
Culture Documents
Management
Introduction
Zeneca Pharmaceuticals
Preclinical Testing
Investigational New Drug
Human Clinical Testing
Background
10
Defining a Project
11
Examples of Projects
Constructing highways,
bridges, tunnels and dams
Erecting skyscrapers, steel
mills, and homes
Organizing conferences
and conventions
Managing R&D projects
Running political
campaigns, war
operations, and
advertising campaigns
Chapter 11: Project Management
12
More Sophisticated
Technology
Better-Educated
Citizens
More Leisure Time
Increased Accountability
Higher Productivity
Faster Response to
Customers
Greater customization
for customers
Chapter 11: Project Management
13
14
15
16
17
Project Plans
18
19
20
21
22
23
Terminology
Activity
Event
Network
Path
Critical Path
Critical Activities
Chapter 11: Project Management
24
Inputs
25
Outputs
graphical representation of project
time to complete project
identification of critical path(s) and activities
activity and path slack
earliest and latest time each activity can be
started
earliest and latest time each activity can be
completed
26
Example
Activity Time Preceded By
A
10
-B
7
-C
5
A
D
13
A
E
4
B,C
F
12
D
G
14
E
Chapter 11: Project Management
27
Network Diagram
28
29
30
31
Path Slack
32
33
Inputs
Outputs
34
te
t o 4t m t p
6
t p to
35
Example
36
[5.5,
0.694]
1
[7.0,
0.444]
A
B
2 [10, 0.0]
[11.5, 0.913]
C [4.83,
0.250]
6
E
G
[4.33, 1.0]
[4.0,
0.111]
37
38
Path
Expected
Standard
Time
Variance Deviation
A-D-F
27
1.607
1.27
A-C-E-G
14.66
2.055
1.43
B-E-G
15.33
1.555
1.25
39
Probabilities of Completion
40
25 27
z
157
.
1.27
From standard normal table in Appendix A,
there is a 5.82% chance of completing
project on or before time 25.
Chapter 11: Project Management
41
5.82%
42
43
44
45
C
A
46
Activity
A
Mean (days)
32.1
Standard
Deviation
1.2
24.6
3.1
22.2
2.2
26.1
5.2
34.4
6.2
34.5
4.1
47
Activity
F
Minimum
Maximum
Path1 Path 2
(A-C-F) (B-D-F)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Path 3
(B-E)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Project
Finish Time
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
48
49
50
51
52
53
54
Variance Report
55
56
57
58
Introduction
59
60
61
Observations
62
Multitasking
63
64
student syndrome
early completions not reported
Chapter 11: Project Management
65
66
67
68
Project Buffer
Feeding Buffer
69
70
71
Copyright
Copyright John Wiley & Sons, Inc. All rights reserved.
Reproduction or translation of this work beyond that named in
Section 117 of the United States Copyright Act without the express
written consent of the copyright owner is unlawful. Requests for
further information should be addressed to the Permissions
Department, John Wiley & Sons, Inc. Adopters of the textbook are
granted permission to make back-up copies for their own use only,
to make copies for distribution to students of the course the
textbook is used in, and to modify this material to best suit their
instructional needs. Under no circumstances can copies be made
for resale. The Publisher assumes no responsibility for errors,
omissions, or damages, caused by the use of these programs or
from the use of the information contained herein.
72