Professional Documents
Culture Documents
Sub theme:
Reduce number of miss locations in connector #10 for Toyota Rear Door
Customer
REAR DOOR
ENGINE
YFA FLOOR
VERSO FLOOR
YFA IP
FRONT DOOR
Summary of activity
Team
meetin
g area
Study
Area
2500
2140
2000
100%
1825
80%
1500
1439
60%
1000
Quantity
40%
Percent
566
500
399366
290
239
168168129125
11911585 78
60 48 44
20%
15 8 4 2 1 1 1 1 1 1 1 1 1
0%
Facilities
6
120%
1244
1200
100%
1000
80%
800
We analyze deeper
all issues and get to
the conclusion that
the highest number
of defects are misslocation.
600
Quantity
482
400
Percent
40%
20%
200
102
0
60%
52 48
23 7
15 36 25 17 20
6 22 9
All defects
0%
0
points
Customer
2
points
1
point
Productivit
y
Defects
Customer
Total
Toyota
Suzuki
2
8
0
points
Line
Productivit
y
2
points
1
point
Defects
Customer
VERSO FLOOR
ENGINE 1.0
ENGINE 1.3
ENGINE 1.4
ENGINE 1.5
Total
2
1
1
2
2
1
10
120%
44
100%
40
80%
30
27
25
60%
20
17
15
12
10
40%
20%
5
0
30
25
Quantity
Miss-location
pareto byby
wires in
Misallocation
connector #10
wires
0%
120%
100%
20
80%
15
60%
10
40%
20%
0%
Percent
11
Steps to follow
WEEK 28
WEEK29
WEEK30
Actual
Resolved
WEEK31
WEEK32
WEEK35
WEEK3638
WEEK3840
1. THEME selection
2. Preparation of
activity plan
3. Clarification of
problem and target
settings
4. Understanding of
current conditions
5. Factor analysis
6. Countermeasures
development
7. Countermeasures
implementation
8. Confirmation of
effects
9. Standardization
10. Establishment of
control
11.Reporting
12
OK
NOK
13
Mislocation / connector
44
45
40
35
27
30
25
17
20
12
15
10
Connector
Total
10
Connector
20
Connector
270
Connector
271
#
#
#
#
5
0
14
Lead
Stor
e
Test
electric
Tapeback
1
Audit 2
Packing
Trolley
Marking
wires
Process Description
PB &
tube insertion
Gromme
t
Greasing
Audit 1
Assy + Clip
Tape-back
2
15
16
Intervie
w with
operator
s
Miss
location records
sheet
Miss-locations
from our
database
Rule of
insertion
17
The operator
is using CPG
for connector
#271
It doesn't
have CPG for
connector
#10
Wires are
very close
to each
other
The operator
does not use the
diagrams, the
operator works
by memories
18
19
Operator has
problems to identify
correct cavity
Operator does not
respect rule of
insertion.
The operator
holds incorrect
the connector
during insertion
20
1.097
Time
0.8
0.6
0.4
0.2
0
PB 1
PB 2
ASSY+CLIP
TEST ELECTRIC
OPERATION
TACT TIME = 1.097
TARGET = 410
82154-0D600 IS ALIKE 82154-0D620
MAX.
STATIO ACTUA NO. OUTPU
N
L TIME OPS. T
PB 1
1.341
336
PB 2
1.694
266
ASSY+
CLIP 0.967
130
621
TEST
ELECT
RIC 0.725
We have 2 Pb
21
Miss-location / code
20
18
18
14
15
11
7
10
5
0
OD600
OD620
OD630
OD700
OD710
OD750
22
Miss location/operators
4; 10%
A
6; 15%
12; 30%
7; 18%
11; 28%
B
C
D
E
23
Operator
take the
wrong
wire and
insert in
connector
Operator
did not
check
marking
after tube
insertion
Operator
guessed
which
lead to
insert
PB10/1 is
very difficult
because
operator must
look very
closely to see
lead colours
Standardiz
ation work
was not
finish
Take
away
operator
guessing
LEGEND
Problem
Process
Facts
Activity
Countermeasur
24
Operator
only lay-up
harness no
insertion
Other
operator
tapes
When
doesn't
check to
verify lead
colours
Marking
wires
LEGEND
Problem
Process
Facts
Activity
Countermeasur
25
Misslocation
on
connector
#10 wire
LA-P/LA-GR
Operator
takes the
wrong
wire and
insert in
connector
The
operator
does not
confirm
correct
insertion
Operator did
not read the
pre-block
diagram
The operator
hurries he
has to many
preparations.
Additional
training /
image
training
LEGEND
Problem
Process
Facts
Activity
Countermeasur
26
Miss-location
on connector
#10 wire
LA-P/LA-GR
The
operator
takes the
correctly
wire and
wrong
insert in
connector
The
operator
holds
incorrectly
connector
position
The wires
are mixed
after
grommet
attach
Installing
CPG for
connector # 10
LEGEND
Problem
Process
Facts
Activity
Countermeasur
27
Countermeasur
e Proposal
Implementati
on time
Effects for
Quality
Easy to
impleme
nt
Cost
Overall
11
Implementation new
Rule and standardization
10
Installing CPG for
connector #10
Retraining / image
training
1 points
2 points
3 point
10
Week
36
Week
37
Week
38
Week
39
Week
40
Week
40-44
29
Plan
Do
Check
Support for
marking wires
Action
30
Double check
on assy and
test electric for
connector # 10
Chec
k
Plan
Do
Action
31
Creating
visual aid
for the
operator of
the PB
The
operator
was
retraining
32
New work
instruction
Installing
CPG for connector #
10 next month
33
Week 28
7
120%
100%
80%
Quantity
60%
percent
3
40%
20%
1
0
0%
Misslocation (LA*P/LA*GR)
in connctor #10
Defects
Sum defect
Procente %
70% pro
34
Step 9: Standardization
Created a visual
aid for the preblock operator
using connector
#10.
A new work instruction had
been created for marking
wires on placing them in
PB.
35
36
Safety first
Thank you
for
your
attention!
37