1
Plan Cost
Management
Control
Costs
Estimate Costs
Determine
Budget
IAMPI 2014 pto
INPUT
TOOLS &
TECHNIQUES
OUTPUT
INPUTS
TOOLS &
TECHNIQUES
OUTPUTS
10
11
Cost estimate:
Costs are estimated for all resources that will be charged to the project
(ex: labor, materials, equipment, services, and facilities, inflation, cost of
financing, contingency costs, etc)
Include the identification and consideration of costing alternatives to
initiate and complete the project
A quantitative assessment of the likely costs for resources required to
complete the activity.
A prediction that is based on the information known at a given point in
time
Generally expressed in units of some currency
Should be reviewed and refined during the course of the project to reflect
additional detail as it becomes available and assumptions are tested
The accuracy of a project estimate will increase as the project progresses
through the project life cycle
12
IAMPI 2014 pto
13
14
15
Tahapan proyek, tipe estimasi dan metode
estimasi
16
17
18
IAMPI 2014 pto
19
20
W.B.S BANGUNAN GEDUNG
Project
BANGUNAN
GEDUNG
PERSIAPAN
Sub Project
FONDASI
SubNetwork
Activity
STRUKTUR
BAWAH
STRUKTUR
ATAS
STRUKTUR
BETON
PELAT
KOLOM
FINISHING
STRUKTUR
BAJA
BALOK
MACHANICAL
ELEKTRICAL
W.B.S BANGUNAN GEDUNG
Activity
BALOK
Sub Activity
BEKISTING
Resources
Material
Breakdown
PEMBETONAN
TENAGA KERJA
PC
MATERIAL
PASIR
PEMBESIAN
PERALATAN
KERIKIL
IAMPI 2014 pto
23
Faktor
Indikator
Lokasi
Kondisi perekonomian setempat, Aksesibilitas Daya Dukung
Tanah, Zonasi Gempa, Topografi, dll
Desain
Total Luas Lantai , Ketinggian Gedung, Jumlah Lantai, Jarak
antar Lantai, Panjang Keliling, Bentuk Bangunan, dll
Kualitas Bangunan
Tipe Penutup Lantai, Plafond, Finishing Dinding, Material Pintu &
jendela
Konstruksi
Kelengkapan Dokumen saat ditender, tipe Tender & Kontrak,
sistim pembayaran, metode konstruksi
Waktu
Tahun pembangunan, Durasi, Inflasi
24
INPUT
TOOLS &
TECHNIQUES
OUTPUT
25
26
27
28
Anggaran Biaya Langsung
Anggaran biaya langsung untuk pelaksanaan harus
Kontraktor
dirinci untuk keperluan operasional :
Upah
: terdiri dari pek. Galian, timbunan, pasangan,
cor beton, penulangan, form work, dst
Material : terdiri dari material beton, pasir, bata,
batu kali, semen, kayu, tegel, dst
Alat
: terdiri dari depresiasi, bbm / pelumas,
perbaikan, alat sewa, dst .
Subkon : terdiri dari subkon A , subkon B, dst .
Persiapan : terdiri dari pek. Basecamp , jalan kerja ,
dewatering , dst
Overhead: terdiri dari gaji pegawai , honor , dst
Rincian Anggaran Biaya Upah
No
Jenis Pekerjaan
1.
2.
3.
4.
5.
6.
7.
8
9.
Galian
Timbunan
Pas. Batu kali
Pas. Batu bata
Beton bertulang
Lantai
Kuda-Kuda
Penutup Atap
Dst
Total Biaya Upah
Satuan
Pek.
M3
M3
M3
M2
M3
M2
M3
M2
Harga
Satuan
Pek
(Rp)
Kuantitas pekerjaan
Fondasi
Struktur
Finish-ing
Jumlah
Jumlah
Harga
( Rp )
Rincian Anggaran Biaya Bahan
No
Jenis Pekerjaan
1.
2.
3.
4.
5.
6.
7.
8
9.
Galian
Timbunan
Pas. Batu kali
Pas. Batu bata
Beton bertulang
Lantai
Kuda-Kuda
Penutup Atap
Dst
Satuan
Pek.
M3
M3
M3
M2
M3
M2
M3
M2
Jumlah
Harga
satuan
Jumlah Harga
Jenis dan Kuantitas bahan
Seme
n
Pasir
Bt.
kali
Bt
Bata
Besi
beton
Kayu
Tege
l
Ds
t
Rincian Anggaran Biaya Material
Satuan
No
Jenis Material
1.
2.
3.
4.
5.
6.
7.
8
9.
Semen
Batu Kali
Pasir
Batu pecah
Batu Bata
Tegel
Kayu
Kosen
Dst
Harga
Satuan
(Rp)
Kuantitas material
Fondasi
Struktur
Finish
-ing
Zak
M3
M3
M3
bh
bh
M3
M3
Total Biaya Material
Jumlah
Jumlah
Harga
( Rp )
Rincian Anggaran Biaya Alat
No Jenis Alat
1.
2.
3.
4.
5.
6.
Jam Harga
oper Sewa
asi
Alat Sendiri
BBM
Oli
Perba
ikan
Mob/
De- Jumlah
mob
Buldozer
Excavator
T. Crane
D. Truck
Pompa
Dst
Jumlah biaya Alat
Rincian Anggaran Biaya Subkontraktor
No
Jenis
Pekerjaan
1.
2.
3.
4.
5.
6.
7.
8
9.
Galian
Timbunan
Pas. Batu kali
Pas. Batu
bata
Beton
bertulang
Lantai
Kuda-Kuda
Penutup Atap
Dst
Jumlah
Vol.
Pek
.
Budget
Pek (Rp)
Subkon A
Vol.
pek
Harga
Subkon
Sbkon B
Vol.
pek
Harga
Subkon
Kel.
Sub.Kel
Rekap Cost Budget
Kontraktor
PEMBEBANAN
Rp.
Keterangan
BIAYA LANGSUNG PROYEK
II.
1.
BAHAN / MATERIAL
2.
UPAH
3.
ALAT
4.
SUBKONTRAK
5.
PERSIAPAN / PENYELESAIAN
6.
OVERHEAD LAPANGAN
SUB TOTAL
KEWAJIBAN PAJAK
III
1.
PPN ( 10% )
2.
PPH
SUB TOTAL
BIAYA TIDAK LANGSUNG
IV
1.
OVERHEAD PUSAT / CABANG/ PERW.
2.
PENYUSUSTAN AKTIVA TETAP
SDUB TOTAL
LABA / RUGI PROYEK
TOTAL
35
KODE PEMBUKUAN (CONTROL ACCOUNT)
Secara keseluruhan semua bukti transaksi
dibukukan dan diberikan peng-kode-an
Tidak ada standar dlm pemberian kode,
setiap Perusahaan dapat membuat sendiri.
Contoh untuk bahasan peng-kode-an, sbb:
Kode Kelompok
Pendapatan :
I
Biaya Langsung :
II
Pajak :
III
Biaya tidak langsung
:
IV
KODE UNSUR BIAYA LANGSUNG
Dari contoh bahasan diatas, kode biaya langsung (II) dirinci lagi menjadi, subkelompok:
Jenis Biaya
Kode Subkelompok
(1) Biaya bahan
II . 1
(2) Biaya Upah
II . 2
(3) Biaya Alat
II . 3
(4) Biaya Subkon
II . 4
(5) Biaya Pers/Penyel.
II . 5
(6) Biaya Overhead Lap. :
II . 6
KODE JENIS TIAP UNSUR B.L
Untuk keperluan tindakan dari Management,
diperlukan kode jenis dari tiap subkelompok
(1) Kode Sub kelompok Bahan ( II . 1 )
- Semen
: II . 1 . 1
- Pasir
: II . 1 . 2
- Batu pecah
: II . 1 . 3
- Besi beton
: II . 1 . 4
- Dan seterusnya
: II . 1 . n
INPUT
TOOLS &
TECHNIQUES
OUTPUT
39
40
41
42
43
Konsep Earned Value
Term
Definition
Planned Value (PV)
Akumulasi anggaran biaya yang dialokasikan berdasarkan
rencana kerja yang telah disusun terhadap waktu
Actual Cost (AC)
Realisasi akumulasi biaya aktual yang telah dikeluarkan untuk
penyelesaian pekerjaan menurut laporan keuangan dalam
periode tertentu
Earned Value (EV)
Akumulasi dari progres pekerjaan yang diekspresikan
berdasarkan budget yang dialokasikan untuk melaksanakan
pekerjaan
Cost Variance (CV) =
EV - AC
Ukuran kinerja biaya berdasarkan selisih antara nilai EV - AC
Schedule Variance (SV)
= EV - PV
Ukuran kinerja waktu berdasarkan selisih antara nilai EV - PV
Cost Performance
Index (CPI) = EV/AC
Ukuran efisiensi biaya dari sumberdaya yang dialokasikan
berdasarkan rasio EV/AC
Schedule Performance
Index (SPI) = EV/PV
Ukuran efisiensi waktu berdasarkan rasio EV/AC
44
Performance Measure
45
Forecasting
Term
Definition
Budget At Completion
(BAC)
Adalah total PV untuk menyelesaikan seluruh pekerjaan
Estimate At Completion
(EAC)
Total biaya yang diperlukan untuk meyelesaikan seluruh
pekerjaan yang diekspresikan sebagai total biaya aktual sampai
dengan saat ini dan estimasi untuk menyelesaikan
EAC = BAC/CPI
EAC Alt 1, If the CPI is expected to be the same for the
remainder of the project
EAC = AC + BAC EV
EAC Alt 2, If future work will be accomplished at the planned
rate
EAC = AC + Bottom-up
ETC
EAC Alt 3, If the initial plan is no longer valid
EAC = AC + [(BAC
EV)/(CPI x SPI)]
EAC Alt 4, If both the CPI and SPI influence the remaining work
ECD = Actual Time +
(Planned Time Actual
Time)/SPI
Estimate Completion Date
46
Earned Value: Graphical
Representation
47
CASE STUDY: Hasil Monitoring Proyek Akhir
Bulan ke 3
Kegiatan
Anggaran
Biaya
Realisasi
Biaya
4000
5000
3000
3000
6000
4000
5000
2500
8000
1000
Kegiatan sdh dilaksanakan
Kegiatan belum dilaksanakan
Earned Value Analysis
Term
Value
Planned Value (PV)
14.000
Actual Cost (AC)
15.500
Earned Value (EV)
11.000
Cost Variance (CV) = EV - AC
-4.500
Schedule Variance (SV) = EV - PV
-3.000
Cost Performance Index (CPI) = EV/AC
0,709 < 1
Schedule Performance Index (SPI) = EV/PV
0,786 < 1
Budget At Completion (BAC)
26.000
BAC = 4000 + 3000 + 6000 + 5000 + 8000 = 26.000
PV = 4000 + 3000 + (4/8)x(6000) + (4/10)x(5000) + (2/8)x(8000) = 14.000
EV = 4000+ (5/6)x(3000)+(2/8)x(6000)+(6/10)x(5000)+(0/8)x(8000) =
11.000
AC = 5000 + 3000 + 4000 + 2500 + 1000 =15.500
49
Forecasting
Term
Definition
Value
EAC = BAC/CPI
EAC Alt 1, If the CPI is expected to be the
same for the remainder of the project
36.671
EAC = AC + BAC EV
EAC Alt 2, If future work will be
accomplished at the planned rate
30.500
EAC = AC + Bottom-up
ETC
EAC Alt 3, If the initial plan is no longer
valid, and new estimate for remaining work
15.500 +
20.000 (est) =
35.500
EAC = AC + [(BAC EV)/
(CPI x SPI)]
EAC Alt 4, If both the CPI and SPI influence
the remaining work
42.417
ECD = Actual Time +
(Remaining Time)/SPI
Estimate Completion Date
6,82 months
Pelaksanaan pekerjaan terlambat dan realisasi biaya melebihi
anggaran
Range EAC = 30.500 sd 42.417
ECD = 6.82 months
50
Projected
Slippage
GRAFIK EARNED VALUE
Reporting
Cut Off Date
31200
28600
Projected
Overrun
26000
23400
AC
20800
18200
PV
15600
13000
10400
7800
EV
5200
2600
0
6
6.82
51
MEKANISME COST CONTROL
COST
BUDGET
PENGADAAN &
KONSTRUKSI
REALISASI
BIAYA
TINDAKAN
PERBAIKAN
ANALISIS
PENYIMPANGAN.
SESUAI
BUDGET
EVALUASI
BIAYA
DOKUMENTASI
OVER
BUDGET
Referensi:
1.Project Management Institute (PMI), A Guide to project
Management Body Of Knowledge, PMBOK Guide 5th Edition, 2013
2.Ikatan Ahli Manajemen Proyek Indonesia (IAMPI), Pelatihan
Sertifikasi Manajemen Proyek, Materi Project Cost Management,
2014
3.Asiyanto, MBA, IPM, Ir, Construction Project Cost Management",
PT. Pradnya Paramita Jakarta, 2005.
4.DellIsola, M.D., Architects Essentials of Cost Management,
John Wiley & Sons Inc, 2002
53
Terima Kasih
54