INTRODUCTION TO THE SAPP
SAPP installed capacity is 61,859 MW. Available capacity stands at 52,589 MW.
The Operating Capacity stands at 46,910 MW.
ORGANISATION STRUCTURE OF SAPP
Operating Sub-Committee (OSC).
Operating Sub-Committee (OSC).
Operating Sub-Committee (OSC) is responsible for telecommunication,
measurement and control (TMC) and operations of the SAPP Grid.
Has a formal SAPP Operating Guidelines, which is followed by all his
members.
Automatic generation control (AGC) has been successfully installed and
operates in the 'tie line" bias mode under normal operating conditions.
Frequency Control: Target of at least 90% within the frequency band
of 49.95Hz and 50.05Hz.
Implementation of facilities called Demand Response (Implemented in
Eskom South Africa.)
Initially some energy trading was conducted by OSC till MSC was
formed.
Planning Sub-Committee (PSC).
Planning Sub-Committee (PSC).
SAPP has developed its own set of transmission as well as generation
planning criteria.
System is planned for N-1 Contingencies.
Network Condition Voltage Limit.
Healthy System 0.95-1.05 pu
After N-1 Contingencies before 0.90-1.05pu
corrective actions
After N-1 Contingencies after 0.95-1.05 pu
corrective actions