Chapter 10 Facility Layout

Operations Management
by
R. Dan Reid & Nada R. Sanders
4th Edition Wiley 2010

Wiley 2010 1
Learning Objectives
Define layout planning and explain its
importance
Identify and describe different types of
layouts
Compare process layouts & product
layouts
Describe the steps involved in designing a
process layout

Wiley 2010 2
Learning Objectives cont
Describe the steps involved in designing a
product layout
Explain the advantages of hybrid layouts
Define the meaning of group technology
(cell) layouts

Wiley 2010 3
What Is Layout Planning?
Layout planning is deciding the best physical arrangement of
all resources within a facility
Facility resource arrangement can significantly affect
productivity
Two broad categories of operations:
Intermittent processing systems low volume of many different
products
Continuous processing systems high volume of a few
standardized products

Wiley 2010 4
Types of Layouts
Four basic layout types consisting of:
Process layouts - Group similar resources together
Product layouts - Designed to produce a specific
product efficiently
Hybrid layouts - Combine aspects of both process
and product layouts
Fixed-Position layouts - Product is two large to
move; e.g. a building

Wiley 2010 5
Process Layouts
Process layout unique characteristics include:

Resources used are general purpose


Facilities are less capital intensive
Facilities are more labor intensive
Resources have greater flexibility
Processing rates are slower
Material handling costs are higher

Wiley 2010 6
Process Layouts cont

Scheduling resources & work flow is more


complex
Space requirements are higher

Wiley 2010 7
Product Layouts
Product layout unique characteristics are:
Resources are specialized
Facilities are capital intensive
Processing rates are faster
Material handling costs are lower
Space requirements for inventory storage are
lower
Flexibility is low relative to the market
Wiley 2010 8
Process vs. Product Layouts
Here are the characteristic differences between a process
and product layout.

Wiley 2010 9
Hybrid Layouts
Combine elements of both product &
process layouts
Maintain some of the efficiencies of product
layouts
Maintain some of the flexibility of process
layouts
Examples:
Group technology & manufacturing cells
Grocery stores

Wiley 2010 10
Fixed-Position Layout
Used when product is large
Product is difficult or impossible to move,
i.e. very large or fixed
All resources must be brought to the site
Scheduling of crews and resources is a
challenge

Wiley 2010 11
Designing Process Layouts
Step 1: Gather information:
Space needed, space available, identify closeness
measures
Step 2: Develop alternative block plans:
Using trial-and-error or decision support tools
Step 3: Develop a detailed layout:
Consider exact sizes/shapes of departments and
work centers including aisles and stairways
Tools like drawings, 3-D models, and CAD software
are available to facilitate this process

Wiley 2010 12
Special Cases of Process
Layouts
A number of unique process layouts require
special attention. We will look at two of
these:
Warehouse layouts

Office Layouts

Wiley 2010 13
Warehouse Layouts
Warehouse Layout Considerations:
Primary decision is where to locate each
department relative to the dock
Departments can be organized to minimize ld
totals
Departments of unequal size require modification
of the typical ld calculations to include a
calculation of the ratio of trips to area
needed
The usage of Crossdocking modifies the
traditional warehouse layouts; more docks, less
storage space, and less order picking

Wiley 2010 14
Office Layouts
Office Layout Considerations:
Almost half of US workforce works in an office
environment
Human interaction and communication are the primary
factors in designing office layouts
Layouts need to account for physical environment and
psychological needs of the organization
One key layout trade-off is between proximity and
privacy
Open concept offices promote understanding & trust
Flexible layouts incorporating office landscaping help
to solve the privacy issue in open office environments
Wiley 2010 15
Designing Product Layouts
Designing product layouts requires
consideration of:
Sequence of tasks to be performed by each
workstation
Logical order
Speed considerations line balancing

Wiley 2010 16
Designing Product Layouts
cont
Step 1: Identify tasks & immediate predecessors
Step 2: Determine output rate
Step 3: Determine cycle time
Step 4: Compute the Theoretical Minimum number of
Stations
Step 5: Assign tasks to workstations (balance the
line)
Step 6: Compute efficiency, idle time & balance delay

Wiley 2010 17
Step 1: Identify Tasks &
Immediate Predecessors
Example 10.4 Vicki's Pizzeria and the Precedence Diagram
Immediate Task Time
Work Element Task Description Predecessor (seconds
A Roll dough None 50
B Place on cardboard backing A 5
C Sprinkle cheese B 25
D Spread Sauce C 15
E Add pepperoni D 12
F Add sausage D 10
G Add mushrooms D 15
H Shrinkwrap pizza E,F,G 18
I Pack in box H 15
Total task time 165

Wiley 2010 18
Layout Calculations
Step 2: Determine output rate
Vicki needs to produce 60 pizzas per hour
Step 3: Determine cycle time
The amount of time each workstation is allowed to

complete its tasks


available time sec./day 60 min/hr x 60 sec/min
Cycle time (sec./unit ) 60 sec./unit
desired output units/hr 60 units/hr

Limited by the bottleneck task (the longest task in a


process):
available time 3600 sec./hr.
Maximum output 72 units/hr, or pizzas per hour
bottleneck task time 50 sec./unit
Wiley 2010 19
Layout Calculations cont
Step 4: Compute the theoretical minimum
number of stations
TM = number of stations needed to
achieve 100% efficiency (every second is
used)

TM
task times 165 seconds
2.75, or 3 stations
cycle time 60 sec/station

Always round up (no partial workstations)


Serves as a lower bound for our analysis
Wiley 2010 20
Layout Calculations cont
Step 5: Assign tasks to workstations
Start at the first station & choose the longest eligible task following
precedence relationships
Continue adding the longest eligible task that fits without going over the
desired cycle time
When no additional tasks can be added within the desired cycle time, begin
assigning tasks to the next workstation until finished
Workstation Eligible task Task Selected Task time Idle time
A A 50 10
1
B B 5 5
C C 25 35
2 D D 15 20
E, F, G G 15 5
E, F E 12 48
F F 10 38
3
H H 18 20
I Wiley
I 2010 15 5 21
Last Layout Calculation
Step 6: Compute efficiency and balance delay
Efficiency (%) is the ratio of total productive

time divided by total time

Efficiency (%)
t

165 sec.
100 91.7%
NC 3 stations x 60 sec.

Balance delay (%) is the amount by which the


line falls short of 100%

Balance delay 100% 91.7% 8.3%

Wiley 2010 22
Other Product Layout Considerations
Shape of the line (S, U, O, L):
Share resources, enhance communication & visibility,
impact location of loading & unloading

Paced versus Un-paced lines


Paced lines use an automatically enforced cycle time

Number of Product Models produced


Single
Mixed-model lines

Wiley 2010 23
Group Technology (CELL)
Layouts
One of the most popular hybrid layouts uses Group
Technology (GT) and a cellular layout
GT has the advantage of bringing the efficiencies of a
product layout to a process layout environment

Wiley 2010 24
Process Flows before the Use of GT Cells

Wiley 2010 25
Process Flows after the Use of GT Cells

Wiley 2010 26
Facility Layout Across the
Organization
Layout planning is organizationally important
for an efficient operations
Marketing is affected by layout especially
when clients come to the site
Human resources is affected as layout impacts
people
Finance is involved as layout changes can be
costly endeavors

Wiley 2010 27
Facility Layout within OM:
How it all fits together
Layout decisions are directly related to issues of product
design and process selection (Ch 3).
Job design, as process layouts tend to require greater
worker skills than do product layouts (Ch 11).
Degree of automation, as product layouts tend to be
more capital intensive and use more automation
compared to process layouts (Ch 3).
Layout decisions are also affected by implementation of
just-in-time (JIT) systems, which dictate a line flow and
the use of group technology (GT) cells (Ch 7).
As layout decisions specify the flow of goods through the
facility, they impact all other aspects of operations
management.
Wiley 2010 28
Chapter 10 Highlights
Layout planning is deciding on the best physical
arrangement of all resources that consumes space within a
facility. Proper layout planning is highly important for the
efficient running of a business. Otherwise, there can be
much wasted time and energy, as well as confusion.

There are four basic types of layouts: process, product,


hybrid, and fixed position. Process layouts group
resources based on similar processes. Product layouts
arrange resources in straight-line fashion. Hybrid layouts
combine elements of both process and product layouts.
Fixed-position layouts occur when the product is larger
and cannot be moved.

Wiley 2010 29
Chapter 10 Highlights cont
Process layouts provide much flexibility and allow for the
production of many products with differing characteristics.
Product layouts, on the other hand, provide greater
efficiency when producing one type of product.

The steps for designing process layouts are (1) gather


information about space needs, space availability, and
closeness requirements of departments; (2) developing a
block plan or schematic of the layout; and (3) developing a
detailed layout.

Wiley 2010 30
Chapter 10 Highlights cont
The steps for designing an product layout are (1) identify
tasks that need to be performed and their immediate
predecessors; (2) determine output rate; (3) determine
cycle time; (4) computing the theoretical minimum number
of work stations, (5) assigning tasks to workstations; and
(6) computing efficiency and balance delay.
Hybrids layouts have advantages over other layout types
because they combine elements of both process and
product layouts to increase efficiency.

Wiley 2010 31
Chapter 10 Highlights cont
An example of hybrid layouts is group technology or cell
layouts. Group technology is the process of crating
groupings of products based on similar processing
requirements. Cells are created for each grouping of
products, resulting in a more orderly flow of products
through the facility.

Wiley 2010 32
Wiley 2010 33
Wiley 2010 34
Wiley 2010 35
Wiley 2010 36
Wiley 2010 37
Chapter 10 Homework Hints
10.8: Assign sites based on number of
trips (refer to Example 10.2). There is no
strategy regarding which side of the aisle
to assignjust nearness to the dock.
10.16: Follow the steps. This is a product
layout (assembly line balancing). The
book has an example on pages 360-366,
which is also on the slides covered in class.
Sample Problem10.7

dock aisle

Department Category Trips to/from


dock
1 Sports t-shirts 50
2 Mens t-shirts 63
3 Womens t-shirts 35
4 Childrens t-shirts 55
5 Fashion t-shirts 48
6 Undershirts 60
Sample Problem 10.15
Task Imm. predecessor Task time (sec)
A None 55
B A 30
C A 22
D B 35
E B, C 50
F C 15
G F 5
H G 10
TOTAL 222

Draw precedence diagram


Determine cycle timedemand = 50 units/hr
Theoretical minimum no. of work stations
Assign tasks to workstations using cycle time
Efficiency and balance delay of line?
Bottleneck?
Maximum output?