Professional Documents
Culture Documents
KEY-DATE SCHEDULE
Project Highway Bridge Project No. 7908-05
scheduled required actual
No. operation
start finish start finish start finish
1 Move in June 25 June 29 June 14 June 16
2 Excavation July 30 July 7 July 19 August 3
3 footing No.1 July 6 July 14 July 9 July 19
4 footing No.2 July 9 July 20 July 22 July 30
5 Abutment No.1 July 20 July 30 July 20 July 30
6 Abutment No.2 August 2 August 12 August 2 August 12
7 Backfill August 2 August 17 August 10 August 20
8 Deck August 17 August30 August 17 August 30
9 Cleanup September 8 September 10 September 8 September 10
Scheduled Scheduled
Activity Scheduled Free Float Actual Start Actual
Activity Duration Completion
Number Start Date (w orking Days) Date Comletion Date
(w orking Days) Date
Desirable Feasible
BAR CHARTS
- A widely used method for recording job progress for the day to
day time management
- An excellent medium for recording progress information and
current time status for individual
Activities.
- Not a proper tool for evaluating the overall time status of the
project or for planning corrective measures.
DR. SAMIA ALI
PROGRESS MEASUREMENT PROJECT TIME MANAGEMENT
WEEKLY PROGRESS REPORTS
- A common procedure in the construction industry.
- Must include procurement, materials delivery information as will
as the measurement of physical progress.
- Chose a cutoff date, to be selected to serve both time
management and labor cost accounting TUS. “THR. IS PAY
DAY”
WEEKLY PROGRESS REPORT
Project Highway Bridge Week ending Wednesday, July 21 (working day 27)
Job No. 7908-05 Prepared by Ahmed Khalid
Activity Date Date Working days to
Recent complete
Activity number Started completed complete
Deliver abut. Steel 110 - July 15 100 0
deliver deck steel 115 - - - 13
Drive piles, abut. No.2 130 - - 80 2
Strip footing no.1 150 July 15 July 15 100 0
Forms &steel, abut. No. 1 160 july 16 July 21 100 0
Deliver girders 260 - - - 10
The estimated time to Accomplish activity 290, Deck forms & steel,
5
has been revised upward from 4 to 6 working days.
DR. SAMIA ALI
PROGRESS MEASUREMENT PROJECT TIME MANAGEMENT
Progress Analysis
Concerned primarily with determining the effect of the latest
information on the project completion date and any milestone
goals.
signs of danger
1-Activities fall appreciably behind L.S. schedule .
2- Resource availability delays.
3- Realizing that time durations of future activities have been
materially underestimated.
4- Change logic becomes necessary.
Information needed :
1. New activities to be added.
2. Existing activities to be deleted.
3. Changes in the resource availability and delivery dates.
4. Changes in the job logic .
5. New estimate of the time required to finish unfinished activities.
6. Changes in the scope of work.
Present
date
0
TIME
Good for :
. affording a quick grasp of the overall
time condition for owner , A/E, top management.
Limited effectiveness in:
. Presenting time status of the construction project
. No assistance in solving time slippage problems