Team : 8

Audience : Client (Vedanta Aluminium)


Culture : Corporate
Participants : Managers, Department
Heads.
Purpose : Alternative solution for ROB
1 by proposing RE Wall.
Proposal of RE Wall for ROB 1

Abhishek Pandey (Project Incharge)


Sashi Shekhar Das (Construction Manager)
An Overview

Challenges at ROB 1

Technical Solution & Benefits

Construction Methodology

Commercial Implication

Way forward
Challenges at ROB 1

Land Issue
No space for Construction Activity
Unavailability of Suitable Soil
Poor Soil Condition for foundations
Local Problem
Land Boundary
Technical Solution

Modification of Approaches by providing


Reinforced Mechanically stabilized Earthwork
(MSE)

o Space Constraints.
o Cost Effectiveness.
o Flexible .
o Use of Flyash as
backfill material.
o Suitable for sites with poor foundation soils and
seismically active areas.
Method of Construction

Casting of reinforced facia panels


Site Preparation
Laying of foundation bed
Placing RE panels over EPDM pad & their
alignment
Held in position using wooden blocks, bolts & nuts
Stretching linear metallic high adherence soil
reinforcing strips/ladders
Laying of Granular back fill in 200mm layer
Spreading & Compaction
Strength & Stability are derived from the frictional
interaction between granular back fill & the
reinforcement strap
Construction Photos
Commercial Implication

Increase in Cost by 20%-30%


(Impact of ~2-3 Cr.)
Significant cost saving in Land
Purchase (~ 30 Cr.)
Extension of Time by 3 Months.
Way Forward

Submission of Techno Commercial


Offer
Review & Approval of Techno
Commercial Offer

Amendment of Contract