The document discusses adapted lift slab technology for bridge construction. It outlines some of the challenges with traditional methods like cofferdams and open caissons. It then provides details on how adapted lift slab technology works in a step-by-step process, including preparing a temporary system, sinking a pile cap, inserting supporting frames, and eventually lifting the pile cap into its permanent position. Adapted lift slab technology aims to provide a safer and more efficient alternative to building bridge foundations underwater.
Original Description:
presentation about bridges supports in water, it's methodology and some pictures for illustration.
The document discusses adapted lift slab technology for bridge construction. It outlines some of the challenges with traditional methods like cofferdams and open caissons. It then provides details on how adapted lift slab technology works in a step-by-step process, including preparing a temporary system, sinking a pile cap, inserting supporting frames, and eventually lifting the pile cap into its permanent position. Adapted lift slab technology aims to provide a safer and more efficient alternative to building bridge foundations underwater.
The document discusses adapted lift slab technology for bridge construction. It outlines some of the challenges with traditional methods like cofferdams and open caissons. It then provides details on how adapted lift slab technology works in a step-by-step process, including preparing a temporary system, sinking a pile cap, inserting supporting frames, and eventually lifting the pile cap into its permanent position. Adapted lift slab technology aims to provide a safer and more efficient alternative to building bridge foundations underwater.
Cofferdams Steel sheet piling Very expensive Open caissons and process of grabbing underwater Pneumatic caissons unhygienic working conditions Bridges used this technology in Egypt
Rod El Farag Bridge
Luxor Bride El-Moneeb Bridge Mit Ghamr-Zifta Bridge Sherbeen Bridge Adapted Lift Slab technology Step by Step
Preparation temporary System casting and sinking the pile cap
Steel casing 150 Cm Compacted Sand 120 cm PC for supporting frames Main Girder Secondary beams Adapted Lift Slab technology Step by Step
Sealant which is necessary to seal the space Anchorage of Screw bars
Between casing and pile caps Adapted Lift Slab technology Step by Step
Inserting Supporting Frames
Reinforcement for bottom and side of pile cap Adapted Lift Slab technology Step by Step
Pouring bottom and around working rooms
Hydraulic jacks are mounted on the supporting Frames Any insulation work for pile cap is performed Adapted Lift Slab technology Step by Step
Control system in installed
to provide lowering and lifting with the same rate Adapted Lift Slab technology Step by Step
Sinking Pile cap to River bed
Top of pile Cap 50 cm above water surface Column Reinforcement Adapted Lift Slab technology Step by Step Adapted Lift Slab technology Step by Step
Lifting pile cap and removing Sinking pile cap to permanent position temporary platform