Adapted lift slab technology

Main challenge is cutting off water seepage


Cofferdams Steel sheet piling Very expensive
Open caissons and process of grabbing underwater
Pneumatic caissons unhygienic working conditions
Bridges used this technology in Egypt

Rod El Farag Bridge


Luxor Bride
El-Moneeb Bridge
Mit Ghamr-Zifta Bridge
Sherbeen Bridge
Adapted Lift Slab technology Step by Step

Preparation temporary System casting and sinking the pile cap


Steel casing
150 Cm Compacted Sand
120 cm PC
for supporting frames
Main Girder
Secondary beams
Adapted Lift Slab technology Step by Step

Sealant which is necessary to seal the space Anchorage of Screw bars


Between casing and pile caps
Adapted Lift Slab technology Step by Step

Inserting Supporting Frames


Reinforcement for bottom and side of pile cap
Adapted Lift Slab technology Step by Step

Pouring bottom and around working rooms


Hydraulic jacks are mounted on the supporting Frames
Any insulation work for pile cap is performed
Adapted Lift Slab technology Step by Step

Control system in installed


to provide lowering and lifting with the same rate
Adapted Lift Slab technology Step by Step

Sinking Pile cap to River bed


Top of pile Cap 50 cm above water surface
Column Reinforcement
Adapted Lift Slab technology Step by Step
Adapted Lift Slab technology Step by Step

Lifting pile cap and removing Sinking pile cap to permanent position
temporary platform