Professional Documents
Culture Documents
Status and Acceptability of Concrete Gravity Dam in Culaba
Status and Acceptability of Concrete Gravity Dam in Culaba
In Partial Fulfillment
Of the Requirements of the Course
Research Report
Improved
Concrete Gravity Dam in Culaba
(Development Plan)
Research Locale
The study was conducted in Brgy. Virginia,
Sitio Spillway, Culaba, Biliran.
Research Subject
The subjects of this study involved Municipal
Planning and Development Officers of the
Municipality and residents of Brgy. Virginia,Sitio
Spillway, Culaba, Biliran.
Table 2.1
Distribution of Respondents
Frequency Percentage
Respondents
(f) (%)
LGU- Culaba 2 4
Brgy. Virginia, Sitio
48 96
Spillway
Total 50 100
Research Instrument
The major instrument used in gathering the
data was research-made questionnaire to serve
as the basis in answering the questions that
best specify the data asked. The questionnaire
has two parts. The first part consist the profile of
the concrete gravity dam that is being answered
by the Local Government Unit. The second part
consists of the respondents answer.
Data Gathering Procedure
To produce the needed data, the
researchers first wrote a letter of request to the
Municipal Engineer of Culaba to conduct interview
and have a site visit to the structure and to the
residents of Brgy.Virginia for the purpose of
collecting the needed data. After that, the
researchers distribute the questionnaire. Data
were collected, tallied and analyze, interpret and
presented in Tables.
Data Scoring
The scoring was done using simple tabulation
of data gathered. Part two of the questionnaire was
the acceptability of the respondents to concrete
gravity dam by simple scoring from four, three, two
and one, which implies four as very acceptable,
three as acceptable, two as less acceptable, and
one as not acceptable.
Table 2
Profile of the Concrete Gravity Dam
1.Structural Design
1.1.Length· 10 meters
1.2.Span· 16 meters
1.3 Horizontal Spacing of re-bar· 0.25 meter
1.4 Vertical Spacing of re-bars· 0.25 meter
1.5.Diameter of re-bars in footing· 12 mm.
2.Water Capacity in terms of cubic meter
· 5-6 cubic meters
3.Number of years in operation
· more than 10 years
4.Present Physical condition
· cracks and damaged areas were already seen on the structure due to natural
disasters.
5. Source of funding
· National Irrigation Administration
6.Contractor
· Joji Construction Enterprises
7.Maintenance system
· None
As shown in Table 2, the profile of the
concrete gravity dam had a length of 10 meters
and a span of 16 meters. A spacing of 0.25
meters for the vertical and horizontal re-bars was
also used with a 12 mm. diameter re-bars for the
footing.
The concrete gravity dam can hold up an
amount of 5 to 6 cubic meters of water, and had
been operating for more than 10 years already.
Due to natural disasters, cracks and a damaged
portion had already been found present on the
dam.
The project was constructed by Joji
Construction Enterprises, funded by National
Irrigation Administration. Since the project
was not handled by the Local Government
Unit of Culaba, the LGU-Officials could not
take the maintenance of the structure.
Degree of Acceptability
of the Concrete Gravity Dam
to the Respondents.
This section deals with the degree of the
acceptability of the respondents in the
construction of the concrete gravity dam.
Table below shows the degree of
acceptability of the fifty (50) respondents as
they are interviewed during the formulation of
data.
Table 3
Acceptability of Concrete Gravity Dam
4 3 2 1
Acceptability of
concrete VeryAccept Acceptable Less NotAccept WM Description
gravity dam able Acceptable able
1.Structural
Design of
30 10 8 2 3.4 Acceptable
concrete
gravity dam
2. Quality of the
concrete 10 23 12 5 2.8 Acceptable
gravity dam
3. Span of
construction of Very
40 5 5 O 3.7
concrete Acceptable
gravity dam
4.Water
20 20 2 8 3.0 Acceptable
capacity
5. Maintenance
Not
of the concrete 0 0 0 50 1.0
Acceptable
gravity dam
Average Weighted Mean 2.8 Acceptable
As displayed in Table 3, the rate of
acceptance for the structural design, quality, and
water capacity of the concrete gravity dam were all
found to be acceptable, with rated values of 3.4,
2.8, and 3.0, respectively.
For the span of the concrete gravity dam it was
rated to have a 3.7 value, which implies very
acceptable to the respondents, but for the
maintenance of the concrete gravity dam the
results was not acceptable. And for the overall
average weighted mean value for the acceptability
of the dam, it was found to be acceptable with a 2.8
rated value.
Problems met by Respondents
to the Concrete Gravity Dam
These were the dominant problems of the
respondents on the structure, as they enumerate
the problems in the project during ordinary and
rainy days.
Ordinary Days. 1.) Inadequate supply of
water, 2.)There were livestock placed near at the
structure.
Rainy Days. 1.) Over flowing water on river
banks that reaches the irrigation system causes
diversion of flow. 2.) There were no barriers that
would block the debris from the opening.
Suggestion of the Local
Government Unit of
Culaba For the
Improvement of the Structure
Summary of Findings
From the data gathered, analyzed and
presented, the following findings evolved after a
thorough examination of the data through the different
statistical analysis employed.
The findings are presented below:
Profile of the Concrete Gravity Dam. The
structure was funded by the National Irrigation
Administration and had been constructed by
Joji Construction Enterprises. Due to lack of
maintenance agency that holds the structure’s
preservation, cracks and damaged areas were
not yet repaired.
Degree of Acceptability of the Concrete
Gravity Dam to the Respondents. The study
found that the acceptance of the concrete
gravity dam in Culaba, was rated a value of 2.8
which implies acceptable.
Problems met by the Respondents. The study
found that the problems of the respondents on the
structure in terms of ordinary days was the
inadequacy of supplied water to rice fields and
livestock’s were placed near at the structure.
While during rainy days the problems on the
overflowing water on river banks reaches the
irrigation system causing diversion of flow and also
there are no barriers that blocks the debris from the
opening.
Suggestion of LGU- Culaba Engineering Staff
.The study found that the Local Government Unit
of Culaba, suggests that in order to improve the
structure, there must be an agency that will hold
the maintenance and repair of the existing
damages on the dam, and also as times goes by,
rice fields do increases its area. Hence,
enlargement on the opening of the gate way were
found to be necessary.
Conclusions
In the light of the findings of the study the
following conclusion were drawn:
The length and span of the structure was good,
but its entire structural design was poor, because the
dam was fractured.
The maintenance system of the concrete
gravity dam was poor, because there were no
agencies that maintain the structure.
The degree of acceptability of the respondents
to the structure was considered as good as it results
acceptable in the computation.
There were problems encountered during
ordinary and rainy days these were inadequacy of
supplied water and livestock being placed near at the
structure. While in rainy days the problems
encountered were over flowing of water on river
banks and the lack of barriers that would block the
debris from the opening of the dam structure.
Recommendations
In the consonance with the findings and
conclusion of the study, the following
recommendation are forwarded:
1. Create a group or a program that will handle
the maintenance for the betterment of the
structure.
2. The agency must have immediate action for the
repair of the fractured areas in the structure.
3. If possible enlarge the opening in the gate way
so that it can supply large volume of water to the
irrigation system.
Development Plan for the
Improvement of the
Concrete Gravity Dam
The Table shows the development plan for the concrete gravity dam in
Culaba.
Table 4
Development Plan
Proposed Activity/
Persons Involved Source of Funding
Action taken
Repair on the
LGU-Culaba
damage part of the
Engineering Staff National Irrigation
concrete dam
Enlarge the irrigation LGU-Culaba Administration (NIA)
system Engineering Staff Local Government Unit
Funds
Monthly inspection LGU-Culaba
Department of Interior
and cleanup for the Maintenance
Local Government Funds
maintenance of the Personnel and
dam Barangay
Thank you so much!!