Professional Documents
Culture Documents
MANAGEMENT
What is A Project?
A temporary endeavor undertaken to create a
unique product, service, or result
(PMBOK, Third Edition)
Temporary
Progressive Unique
Elaboration Deliverable
OVERVIEW
Four Basic Type of Project
Project
Work CRAFT INTELECT
Product
PHYSICAL
Physical-Craft Physical-Intellect
(VISIBLE)
Project Management
Process menurut
PMBOK@ Guide
2000 Edition
Third
OVERVIEW
Time
Scope
Quality
PROJECT TIME MANAGEMENT
Activity Definition
Activity Sequencing
Activity Resources Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
PROJECT TIME MANAGEMENT
1. Activity Definition
6. Schedule Control
2. Activity Sequencing
3. Activity Resource Estimating
4. Activity Duration Estimating
5. Schedule Development
PROCESS FLOW DIAGRAM
1. ACTIVITY DEFINITION
q Enterprise environmental
q Decomposition q Activity list
factors q Templates q Activity attributes
q Organizational process assets q Rolling wave planning q Milestone list
q Project scope statement q Expert judgment q Requested changes
q Work breakdown structure q Planning component
q WBS dictionary
q Project management plan
ACTIVITY DEFINITION :
TOOLS & TECHNIQUE
Defining the schedule activities involves identifying
and documenting the work that is planned to be
performed
1. Decomposition WBS
2. Templates
3. Rolling Wave Planning (Progressive Elaboration Planning
where the work to be accomplished in the near term is planned in
detail at a low level of WBS, the work far in the future is planned for
WBS components that are at relatively high level of the WBS)
4. Expert Judgment
5. Planning Component
2. ACTIVITY SEQUENCING
LAGS
Inserted waiting time between task
For example: You must wait three days after pouring
concrete before you can construct the frame for a house
Relationship : FS + 3: 3 days of Lag
LEADS
Designated number of time of periods subtracted from start
or finish the activity.
For example: Activity B start 2 days before the activity A
Complete
Relationship : FS-2 : 2 days of lead
Arrow Diagramming Method (ADM)
or Activity On Arrow (AOA) (1/2)
Draft Drawing
A30
20 days
Initial
Design Final Design
A10 A20 A50 A60
10 days 10 days
Run Simulation
A40
15 days
LS LF LS LF
Activity Name Activity Name
Duration Duration
ES EF ES EF
Internal or outsource
Material
Direct: hardware or software
Subcontract
Information
RESOURCES ESTIMATING
Inputs
Resources Requirement
-Number of resources that will be assigned
-Sometimes, too many resources will reduce productivity
Resources Capabilities
-Level of skill, knowledge and experience (seniority)
Etc
ACTIVITY DURATION ESTIMATING :
TOOLS & TECHNIQUE
1. Fast Tracking
Doing critical path task in parallel that were originally
planned in series
Fast Tracking often results in rework, usually increases
risk and requires more attention to communications
2. Crashing
Moving resources from non critical tasks or adding
extra resources to the task from outside project.
Crashing almost result in increased costs.
SCHEDULE DEVELOPMENT :
TOOLS & TECHNIQUE (3/3)
RESORCE LEVELING
Leveling lets schedule and cost slip in favor of having a
stable number of resources each month
Allocate scarce resources to critical path activities first
D
12
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 5
15
G
5
6
Arrow Diagramming Method (ADM) -
Example (3/7)
Forward-Pass Algorithm
D
12
0 10 18 24 32 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 18 5
15
G
5
6
18
Arrow Diagramming Method (ADM) -
Example (5/7)
Backward-Pass algorithm
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 18 19 5
15
G
5
6
18 18
Arrow Diagramming Method (ADM) -
Example (6/7)
Calculating float
2 2
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
0 0 0 0 4 4 0 0 0 0
4 F
B 18 19 5 1 1
15
3 3 G
5 Note:
6
18 18 0 0 FF TF
Arrow Diagramming Method (ADM) -
Example (7/7)
Critical path
2 2
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
0 0 0 0 4 4 0 0 0 0
4 F
B 18 19 5 1 1
15
3 3 G
5 Note:
6
18 18 0 0 Critical activity
SCHEDULE CHARTS
Milestone Charts
Similar to bar charts but only show major events. Milestone have no
duration. Milestone charts are good tools for reporting to management
and customer
Flowcharts
Depict workflow and process flow through a system. Used for quality or
engineering.
Network Diagram
Shows how the project tasks will flow from beginning to end. Used for
planning, organizing, controlling, crashing, and fast tracking the project
SCHEDULE CHARTS
BART (GANT) CHART
Project Management software makes an attempt to draw
lines between tasks on a Gantt chart to show
interdependencies. However, Gantt charts do not show
task interdependencies or resources assigned. A Gantt
chart looks similar to this:
September
ID Task Name Durations Start Finish
01-Sep 08-Sep 15-Sep 22-Sep 29-Sep
1 Start 0 1-Sep-06 1-Sep-06
2D 4 1-Sep-06 4-Sep-06
3A 6 1-Sep-06 6-Sep-06
4C 7 3-Sep-06 9-Sep-06
5B 8 2-Sep-06 9-Sep-06
6E 12 10-Sep-06 21-Sep-06
7 Finish 0 21-Sep-06 21-Sep-06
BART (GANT) CHART
SCHEDULE LEVELS
6. SCHEDULE CONTROL
Controlling changes to the project schedule which includes determining
the current status of the project schedule, influencing the factors that
create schedule changes, determining that the project schedule has
changed, and managing the actual changes.
Inputs Tools & Techniques Outputs