HOUSE CONSTRUCTION

SCHEDULE – PHASE 3
VILLAS DEL PUEBLO
V-THE VILLAS REALTY AND DEVELOPMENT CORP.
DETAILS:

• SELLING PERIOD: JULY 18 – JUN 21


PHASE 3 A PHASE 3 B
• CONSTRUCTION PERIOD: JULY 19 – FEB 22

• READY FOR CONSTRUCTION: JULY 2019


OCT 19 - MAR 20 BATCH 1 BATCH BATCH 8 DRAINAGE TARGET EARLIEST
JULY – DEC 19 2 FEB – JUL 20 MOVE-IN AS PER

MAR – AUG 20
BATCH 4

DP TERM

BATCH 9
BATCH 3 AUG 19 BATCH 1 – FEB 20
BATCH 10
SEP 19 – – JAN
APR – SEP 20
FEB 20 20 BATCH 2 – MAY 20
BATCH 5
BATCH 11 BATCH 3 – JUNE 20
DEC 19 – MAY 20

NOV 19 – APR
JAN – JUN 20

MAY – OCT 20
20 BATCH 4 – MAR 20
BATCH 7

BATCH 6

BATCH 5 – SEP 20

OCT 20 – MAR 21
JULY – DEC

SEP 20 – FEB 21
BATCH 13

BATCH 6 – AUG 20
BATCH 14
AUG 20 –
JAN 21

BATCH 15

BATCH 16

BATCH 18
20

DEC 20 –
BATCH 7 – AUG 20

MAY 21

BATCH
DEC 21
JULY –

20
MODEL HOUSES
SUPERIOR : JAN – MAY 19
LARA : FEB – JUNE 19
FIONA : MAR – JULY 19
KYLA: APR – AUG 19
PHASE 3 EXECUTIVE1 :
CONSOLIDATE
READY FOR CONSTRUCTION: JULY 2019 JUN – OCT 19
SUBDIVIDE
DETAILS:

• Total number of houses to be constructed: 139 units

• Total number of house construction batches: BATCH 3 – JUNE 20


27 batches
BATCH 4 – MAR 20
BATCH 5 – SEP 20
• Total number of houses to be constructed BATCH 6 – AUG 20
prior to Batch 1: 5 units (MODEL HOUSES)
BATCH 7 – AUG 20

• Average number of sales in Phase 3 per month: 5 units

• Average number of houses to be constructed


per batch: 5 units
HOUSE CONSTRUCTION
SCHEDULE – PHASE 4
VILLAS DEL PUEBLO
V-THE VILLAS REALTY AND DEVELOPMENT CORP.
DETAILS:

• SELLING PERIOD: OCT 2018 – DEC 2020

• CONSTRUCTION PERIOD: JULY 2019 – MARCH 2021

• READY FOR CONSTRUCTION: JULY 2019


TARGET EARLIEST
MOVE-IN AS PER
DP TERM

BATCH 1 – MAY 20
BATCH 2 – JUNE 20
BATCH 3 – MAY 20
BATCH 4 – not earlier than
BATCH 11 BATCH 9 Nov 20
MAY – OCT 20 MAR – AUG 20 BATCH 5 – JULY 20
BATCH 6 – JUNE 20
BATCH 7 – JULY 20
BATCH 8 – not earlier than
Nov 20
DETAILS:

• Total number of houses to be constructed: 80 units


BATCH 3 – JUNE 20
• Total number of house construction batches: 17 batches
BATCH 4 – MAR 20
BATCH 5 – SEP 20
• Total number of houses to be constructed BATCH 6 – AUG 20
prior to Batch 1: BATCH 7 – AUG 20

• Average number of sales in Phase 4 per month: 4 units

• Average number of houses to be constructed


per batch: 5 units