Professional Documents
Culture Documents
1) DIRECT LAYING
2) DRAW-IN-SYSTEM
3) SOLID-SYSTEM
DIRECT LAYING
IN DIRECT LAYING METHOD, THE
CABLES WITH STEEL TAPE OR WIRE
ARMOURING ARE LAID DIRECTLY AS
THEY AFFORD EXCELLENT
PROTECTION FROM MECHANICAL
INJURY. THIS METHOD OF THE LAYING
UNDERGROUND CABLES IS SIMPLE
AND CHEAP AND IN MUCH USE. IN THIS
METHOD OF LAYING, A TRENCH ABOUT
1.5 M DEEP AND 45CM WIDE IS DUG
THROUGH OUT THE ROUTE OF THE
CABLE. THE TRENCH IS COVERED
WITH A LAYER OF FINE SAND AND THE
CABLE IS LAID OVER THIS SAND BED.
THE PURPOSE OF SAND IS TO
PREVENT THE ENTRY OF MOISTURE
FROM THE GROUND AND THUS PROTECTS THE CABLE FROM
DECAY. AFTER THE LAYING OF THE CABLE IN THE TRENCH, IT IS
COVERED WITH ANOTHER LAYER OF SAND OF ABOUT 10 CM
THICKNESS, CARE BEING TAKEN THAT NO SHARP STONE SHOULD
COME IN DIRECT CONTACT WITH THE CABLE. THEN A SINGLE
LAYER OF BRICKS OR TILES IS LAID TO PROTECT THE CABLE
FROM PROTECTED BY WOODEN PLANKS OR CONCRETE SLAB.
WHEN MORE THAN ONE CABLE IS TO BE LAID IN THE SAME
TRENCH, HORIZONTAL OR VERTICAL INTERAXIAL SPACING AT
LEAST 30CM IS PROVIDED IN ORDER TO REDUCE THE EFFECT OF
MUTUAL HEATING AND ALSO TO ENSURE THAT FAULT OCCURING
IN ANY ONE CABLE DOES NOT DAMAGE THE ADJACENT CABLE.
THE CABLES WHICH ARE TO BE LAID BY THIS WAY MUST HAVE
SERVING OF BITUMINISED PAPER AND HESSIAN TAPE, SO AS TO
PROVIDE PROTECTION AGAINST CORROSION AND ELECTROLYSIS.
DRAW-IN SYSTEM
IN CONGETSED PLACES, WHERE
EXCAVATION IS EXPENSIVE AND
INCONVENIENT, THE DRAW-IN SYSTEM
IS OFTEN USED. IN THIS METHOD, A
LINE OF CONDUITS OR DUCTS ARE OF
THE GLAZED STONEWARE CEMENT
OR CONCRETE. AFTER LAYING
CONDUITS OR DUCTS, THE CABLES
ARE PUT INTO THE POSITION FROM
MAN-HOLES OR BRICK PITS SPACED
AT REGULAR INTERVALS. FIGURE
SHOWS SECTION THROUGH FOUR
WAY UNDERGROUND DUCT LINE.
THREE OF THE DUCTS CARRY
TRANSMISSION CABLES AND THE
FOURTH DUCT CARRIES RELY
PROTECTION CONNECTION, PILOT
WIRES.
SOLID SYSTEM
IN THIS METHOD OF LAYING OF THE CABLES, TRENCHES
ALONG THE ROUTE ARE MADE AS IN DIRECT LAYING SYSTEM.
TROUGHS OF CHINA CLAY, EARTHEN WIRE, TREATED WOOD,
CAST IRON, STONEWARE OR ASPHALT ARE PLACED IN A ROW
AND THE CABLE IS LAID OUT IN THESE TROUGHS. AFTER THE
CABLE IS LAID IN POSITIONS, THE TROUGHING IS FILLED WITH
A BITUMINIOUS OR ASPHALT COMPOUND AND COVERED OVER.
CABLES LAID IN THIS MANNER ARE USUALLY PLAIN LEAD
COVERED, AS THE TROUGHING AFFORDS GOOD MECHANICAL
PROTECTION.
COMPARISON BETWEEN
UNDERGROUND & OVERHEAD SYSTEM
COMPARISON BETWEEN UNDERGROUND
& OVERHEAD SYSTEM CONT..