PERANCANGAN DRAINASE

PERUMAHAN

Oleh :
VIKI SATRIA
1301021044

Pembimbing : REVALIN HERDIANTO, ST.,M.Sc.,PhD


BAB I PENDAHULUAN
Latar Belakang

Maksud dan Tujuan

Batasan Masalah

Ruang Lingkup Penulisann

Sistematika Laporan
BAB II TINJAUAN PUSTAKA
Sejarah Perkembangan Drainase
1. Definisi Drainase
2. Jenis Drainase
3. Pola Jaringan Drainase
4.
Fungsi Saluran Drainase
5. Perencanaan Drainase
6.
Kriteria Hidrologi
7.
Kriteria Hidrolis
8.
DATA PERENCANAAN
Curah Hujan
No. Tahun GANGGO
RAO SONTANG
MUDIK
1 1982 92.50 92.50 109.70
2 1983 90.40 114.00 186.40
3 1984 56.00 85.30 147.40
4 1985 96.60 74.90 107.40
5 1986 94.00 52.40 142.90
6 1987 158.00 84.60 132.30
7 1988 184.20 65.00 129.60
8 1989 220.00 71.60 93.10
9 1990 175.00 160.00 115.80
10 1991 232.00 120.00 117.50
11 1992 176.00 61.00 91.00
12 1993 156.00 82.00 99.00
13 1994 125.00 65.00 108.00
14 1995 187.00 0.00 105.00
15 1996 132.00 93.00 104.00
16 1997 123.00 93.00 102.00
17 1998 129.00 61.50 120.00
18 1999 124.00 64.50 143.00
19 2000 183.00 80.20 112.00
20 2001 129.00 77.00 125.00
21 2002 167.00 90.80 148.00
22 2003 140.00 67.50 89.00
Data Analisa Debit Limbah Hujan
Kemiringan daerah limpasan adalah 2 %
Nd perumahan adalah 0,02, Nd Beton 0,013 & Nd lapangan rumput adalah 0,4
C Perumahan 0,75, C Lapangan Rumput 0,3 & C Beton 0,8
Kecepatan aliran di daerah limpasan adalah 0,6 m/dtk
Data Untuk Menghitung Debit Limbah Domestik
Jumlah anggota keluarga/ rumah adalah 5 orang
Pertumbuhan penduduk adalah 4 % per tahun
Periode desain 10 tahun
Limbah buangan domestik 101,52 liter/org/hari
Data Saluran
Penampang yang digunakan adalah penampang persegi
Kemiringan saluran 0,5%
Nilai kekasaran saluran 0,013 ( beton diaci )
Arah Aliran
Karena peta kontur tidak ada, sehingga arah aliran ditentukan sendiri oleh penulis
Curah Hujan
No. Tahun GANGGO Xi
RAO SONTANG
MUDIK
a. Curah Hujan Rata-rata 1 1982 92.50 92.50 109.70 98.23
2 1983 90.40 114.00 186.40 130.27
Metoda Aljabar 3 1984 56.00 85.30 147.40 96.23
P1 + P2 + P3 + ⋯ + Pn 4 1985 96.60 74.90 107.40 92.97

P= 5 1986 94.00 52.40 142.90 96.43

n 6 1987 158.00 84.60 132.30 124.97


n
σi=1 Pi 7 1988 184.20 65.00 129.60 126.27

= 8 1989 220.00 71.60 93.10 128.23


n 9 1990 175.00 160.00 115.80 150.27
Contoh tahun 1982 : 10 1991 232.00 120.00 117.50 156.50

92.50 + 92.50 + 109.70 11 1992 176.00 61.00 91.00 109.33


P= 12 1993 156.00 82.00 99.00 112.33
3 13
14
1994
1995
125.00
187.00
65.00
0.00
108.00
105.00
99.33
97.33
P = 98.2 mm/hari. 15 1996 132.00 93.00 104.00 109.67

16 1997 123.00 93.00 102.00 106.00

17 1998 129.00 61.50 120.00 103.50


18 1999 124.00 64.50 143.00 110.50
19 2000 183.00 80.20 112.00 125.07
20 2001 129.00 77.00 125.00 110.33
21 2002 167.00 90.80 148.00 135.27
22 2003 140.00 67.50 89.00 98.83
23 2004 70.00 88.00 94.00 84.00
 2601.87
XRata-Rata 113.12
b. Parameter Statistik
 Nilai rata-rata

x
 x  2601,18  113,12
n 23
 Menentukan standar deviasi (S)

SD 
 ( x  x) 2


7598,00
 18,58
n 1 23  1
 Menentukan Koefisien Variasi
S 18,58
cv    0,16
x 113,12
 Menentukan Koefisien Kemencengan
n. ( x  x) 3 23 x101284,31
Cs    0,79
(n  1).(n  2) S 3 22 x 21x18,583

 Menentukan Koefisien Kurtosis


n 2 . ( x  x) 4 232 x7136026,18
CK    3,43
(n  1).(n  2).(n  3) D 4 22 x 21x 20 x18,584
Tabel 3.4 Parameter Statistik Untuk Menentukan Jenis Distribusi

No Distribusi Persyaratan Hasil Hitungan

(X̅±S) = 68.27 % 78.26%


(X̅±S) = 95.44 % 91.30%
1 Normal
Cs = 0 0.79
Ck = 3 3.43
Cs = 1.14 0.79
2 Gumbel
Ck = 5.4 3.43
3 Log person III Selain dari nilai diatas
Dari tabel 3.4 dapat dilihat bahwa jenis distribusi yang memenuhi
persyaratan adalah log person III.
c. Histogram Curah Hujan
Interval (mm/hari) Frekuensi (n)

Xmaksimum = 156.50 mm/hari 84 – 98 6


Xminimum = 84.00 mm/hari
Jumlah data (n) = 23 99 – 113 9
Jumlah kelas (k) = 1 + 3.3 logn
= 1 + 3.3 log 23 114 – 128 3
= 5.49 ≈ 5 kelas
Range = Xmaksimum-Xminimum 129 – 143 3
= 156.50 – 84.00
= 72.50 144 – 158 2
Interval = 15
Jumlah 23

Frekuensi (n)
10

4 Frekuensi (n)

0
84 – 98 99 – 113 114 – 128 129 – 143 144 – 158
d. Uji Chi Kuadrat berdasarkan Histogram Curah Hujan
Interval Minimu Frekuensi Batas Titik Koefeisie (Oi-Ei)^2/
Maksimum Y Ei
Hujan m (Oi) Bawah Z nZ Ei
84 – 98 98 84 6 84.5 -0.81 0.2090
0.1508 3.47 1.85
-1.57 0.0582
99 – 113 113 99 9 98.5 -0.01 0.4960
0.2724 6.27 1.19
-0.76 0.2236
114 – 128 127 114 3 113.5 0.75 0.7734
0.2535 5.83 1.37
0.05 0.5199
129 – 143 143 129 3 128.5 1.61 0.9463
0.1412 3.25 0.02
0.86 0.8051
144 – 158 158 144 2 143.5 2.42 0.9922
0.0407 0.94 1.21
1.66 0.9515
Jumlah 5.64

Xh2 = ∑(Oi-Ei)2/Ei = 5.64


Berdasarkan nilai D, maka didapat nilai Xh2 5 % = 5.9910
Xh2< X2 95 % → 5.64< 5.9910
Jadi hipotesa diterima dan data curah hujan dapat digunakan untuk perhitungan selanjutnya.
Lihat tabel: 2.3 untuk nilai derajat kepercayaan
a derajat kepercayaan
dk
0,995 0,99 0,975 0,95 0,05 0,025 0,01 0,005
1 0.0000393 0.000157 0.000982 0.00393 3.8410 5.0240 6.6350 7.8790
2 0.0100 0.0201 0.0506 0.1030 5.9910 7.7380 9.2100 10.5970
3 0.0170 0.1150 0.0506 0.3520 7.8150 9.3480 11.3450 12.8380
4 0.2070 0.2970 0.0506 0.7110 7.4880 11.1430 13.2770 14.8600
5 0.4120 0.5540 0.0506 1.1450 11.0700 12.8320 15.0860 16.7500
6 0.6760 0.8720 0.0506 1.6350 12.5920 14.4490 16.8120 18.5480
7 0.9890 1.2390 0.0506 2.1670 14.0670 16.0130 18.4750 20.2780
8 1.3440 1.6460 0.0506 2.7330 15.5070 17.5350 20.0900 21.9550
9 1.7350 2.0880 0.0506 3.3250 16.9190 19.0230 21.6660 23.5890
10 2.1560 2.5580 0.0506 3.9400 18.3070 20.4830 23.2090 25.1880
11 2.6030 3.0530 0.0506 4.5750 19.6750 21.9200 24.7250 26.7570
12 3.0740 3.5710 0.0506 5.2260 21.0260 23.3370 26.7120 28.3000
13 3.5650 4.1070 0.0506 5.8920 22.3620 24.7360 27.6880 29.8190
14 3.0750 4.6600 0.0506 6.5710 23.6850 26.1190 29.1410 31.3190
15 4.6015 5.2290 0.0506 7.2610 24.9960 27.4880 30.5780 32.8010
16 5.1420 5.8120 0.0506 7.9620 26.2960 28.8450 32.0000 34.2670
17 5.6970 6.4080 0.0506 8.6720 27.5870 30.1910 33.4090 35.7180
18 6.2650 7.0150 0.0506 9.3900 28.8690 31.5260 34.8050 37.1560
19 6.8440 7.6330 0.0506 10.1170 30.1440 32.8520 36.1910 38.5820
20 7.4340 8.2600 0.0506 10.8510 31.4100 34.1700 37.5660 39.9970
21 8.0340 8.8970 0.0506 11.5910 32.6710 35.4790 38.9320 41.4010
22 8.6430 9.5420 0.0506 12.3880 39.2400 36.7810 40.2890 42.7960
23 9.2600 10.1960 0.0506 13.0910 36.1720 38.0760 41.6380 44.1810
24 9.8860 10.8560 0.0506 13.8480 36.4150 39.3640 42.9800 45.5580
25 10.5200 11.5640 0.0506 14.6110 37.6520 40.6460 44.3140 46.9280
26 11.1600 12.1980 0.0506 15.3790 38.8850 41.9230 45.6420 48.2900
27 11.8080 12.8790 0.0506 16.1510 40.1130 43.1940 46.9630 49.6450
28 12.4610 13.5650 0.0506 16.9280 41.3370 44.4610 48.2780 50.9930
29 13.1210 14.2560 0.0506 17.7080 42.5570 45.7220 49.5880 52.3360
30 13.7870 14.9530 0.0506 18.4930 43.7730 46.9790 50.8920 53.6720
e. Menentukan curah hujan rencana periode ulang No. Periode Ulang, T Peluang KT
1. Distribusi Normal 2, 5, 10 tahun tahun

x 
1. 1,001 0,999 -3,05
Curah Hujan Rata-Rata = 2601,87
x  113,12 2. 1,005 0,995 -2,58
n 23
 ( x  x) 2 3. 1,010 0,990 -2,33
7598,00
Standar Deviasi = SD    18,58
n 1 23 4. 1,050 0,950 -1,64

5. 1,110 0,900 -1,28


Periode Desain :
6. 1,250 0,800 -0,84
Xt = X + K T . S
7. 1,330 0,750 -0,67
Periode ulang 2 tahun
KT = 0 (tabel 2.5) 8. 1,430 0,700 -0,52

Xt = 113.12 + 0 ∗ 18.58 9. 1,670 0,600 -0,25


Xt = 113.12 mm/hari 10. 2,000 0,500 0
Periode ulang 5 tahun 11. 2,500 0,400 0,25
KT = 0.84
12. 3,330 0,300 0,52
Xt = 113.12 + 0.84 ∗ 18.58
13. 4,000 0,250 0,67
Xt = 128.73 mm/hari
Periode ulang 10 tahun 14. 5,000 0,200 0,84

KT = 1.28 15. 10,000 0,100 1,28


Xt = 113.12 + 1.28 ∗ 18.50 16. 20,000 0,050 1,64
𝑋𝑡 = 136.90 𝑚𝑚/ℎ𝑎𝑟𝑖
17 50,000 0,020 2,05
e. Menentukan curah hujan rencana periode ulang
2. Distribusi Log Person III 2, 5, 10 tahun Koefisi
PERIODE ULANG (TAHUN)

Curah Hujan Rata-Rata =


x
 log x  47,11  2,05 en
Cs
2 5 10 25 50
PELUANG (%)
100 200 1000

n 23 50 20 10 4 2 1 0,5 0,1
Standar Deviasi =  (log x  log x) 2
0,10450
S
n 1   0,07 3,0 -0,396 0,420 1,180 2,278 3,152 4,051 4,970 7,250
23 2,5 -0,360 0,516 1,250 2,626 3,304 3,845 4,652 6,600
Koefisien Kemencengan 2,2 -0,330 0,574 1,284 2,240 2,097 3,705 4,444 6,200
G = 0.5 2,0 0,307 0,609 1,302 2,219 2,912 3,605 4,298 5,910
Periode Desain : 1,8 -0,282 0,643 1,318 2,193 2,484 3,499 4,147 5,660
LogXT = Log X + K. S 1,6 -0,254 0,675 1,329 2,163 2,780 3,388 3,990 5,390
Periode ulang 2 tahun 1,4 -0,225 0,705 1,337 2,168 2,706 3,271 3,828 5,110
K = -0.083 (tabel 2.7) 1,2 -0,195 0,732 1,340 2,087 2,626 3,149 3,661 4,820
LogX T = 2.05 + (−0.083 ∗ 0.07) 1,0 -0,164 0,758 1,340 2,043 2,542 3,022 3,489 4,540
LogX T = 2.04 0,9 -0,148 0,769 1,339 2,018 2,498 3,957 3,401 4,395
XT =110.28mm/hari 0,8 -0,132 0,780 1,336 1,998 2,453 3,891 3,312 4,250
Periode ulang 5 tahun 0,7 -0,116 0,790 1,333 1,967 2,407 2,824 3,223 4,105
K = 0.806 0,6 -0,099 0,800 1,328 1,939 2,359 2,755 3,132 3,960
LogX T = 2.05 + 0.806 ∗ 0.07 0,5 -0,083 0,806 1,323 1,910 2,311 2,686 3,014 3,815
LogX T = 2.11
0,4 -0,066 0,816 1,317 1,880 2,261 2,615 2,949 3,670
XT = 126.99 mm/hari
0,3 -0,050 0,824 1,309 1,490 2,211 2,544 2,856 3,525
Periode ulang 10 tahun
0,2 -0,033 0,830 1,301 1,818 2,159 2,472 2,763 3,380
K = 1.323
0,1 -0,017 0,836 1,292 1,785 2,107 2,400 2,670 3,235
LogX T = 2.05 + 1.323 ∗ 0.07
0,0 0,000 0,842 1,282 1,751 2,054 2,326 2,576 3,090
LogX T = 2.14
-0,1 0,017 0,846 1,270 1,716 2,000 2,252 2,482 2,950
XT = 137.85 mm/hari
e. Menentukan curah hujan rencana periode ulang
2. Distribusi Gumbell 2, 5, 10 tahun
Curah Hujan Rata-Rata = x
x  2601,87
 113,12
n 23
Tabel Yn
Standar Deviasi = SD 
 ( x  x) 2

7598,00
 18,58
n 1 23
Periode Desain :
Yn = 0,5283 (tabel 2.8) Xtr = Xഥ + K. S
Y −Y
Sn = 1,0811 (tabel 2.9) K = Tr n
Sn
Periode ulang 2 tahun
YTr = 0.3668 (lihat tabel 2.8)
Xtr = 113.12 + (−0.15 ∗ 18.58)
Xtr = 110.35 mm/hari
Periode ulang 5 tahun
YTr = 1.5004 (lihat tabel 2.8)
Xtr = 113.12 + 0.90 ∗ 18.58
Xtr = 129.83 mm/hari
Periode ulang 10 tahun
YTr = 2.2510 (lihat tabel 2.8)
Xtr = 113.12 + 1.59 ∗ 18.58
Xtr = 142.74 mm/hari
Tabel Sn
N Sn N Sn N Sn N Sn
10 0,9496 34 1,1255 58 1,1721 82 1,1953
11 0,9676 35 1,1286 59 1,1734 83 1,1959
12 0,9833 36 1,1313 60 1,1747 84 1,1967
13 0,9971 37 1,1339 61 1,1759 85 1,1973
14 1,0095 38 1,1363 62 1,177 86 1,87
15 1,0206 39 1,1388 63 1,1782 87 1,1987
16 1,0316 40 1,1413 64 1,1793 88 1,1994
17 1,0411 41 1,1436 65 1,1803 89 1,2001
18 1,0493 42 1,1458 66 1,1814 90 1,2007
19 1,0565 43 1,148 67 1,1824 91 1,2013
20 1,0628 44 1,1499 68 1,1834 92 1,202
21 1,0696 45 1,1519 69 1,1844 93 1,2026
22 1,0754 46 1,1538 70 1,1854 94 1,2032
23 1,0811 47 1,1557 71 1,1854 95 1,2038
24 1,0864 48 1,1574 72 1,1873 96 1,2044
25 1,0915 49 1,159 73 1,1881 97 1,2049
26 1,0861 50 1,1607 74 1,189 98 1,2055
27 1,1004 51 1,1623 75 1,1898 99 1,206
28 1,1047 52 1,1638 76 1,1906 100 1,2065
29 1,0860 53 1,1658 77 1,1915
30 1,1124 54 1,1667 78 1,1923
31 1,1159 55 1,1681 79 1,193
32 1,1193 56 1,1696 80 1,1938
33 1,1226 57 1,1708 81 1,1945
Menghitung
f. Menentukan nilai to, td dan
Debit Menghitung nilai to Jalan dan
tc bahu Jalan
2 nd 1
Contoh titik 1 : to Bahu Jalan = (3 x 3.28 x L x s
)6

Daerah A ke titik 1 2 0.013 1


1 = ( x 3.28 x 0.5 x )6
2 nd  6 3 0.03
to    3,28  Lo  
3 So  = 0.66 menit
2 nd 1
1 to Jalan Utama = (3 x 3.28 x L x )6
s
2 0,4 
6
to    3,28  28,81   2,37
0,02 
2 0.013 1
3 = (3 x 3.28 x 2.5 x 0.02
)6

Saluran 1-3 Tc = to + td
= 0.89 menit

L = 2,37 + 0,5 2 nd 1
td  = 2,87 menit
to Jalan Komplek = (3 x 3.28 x L x s
)6
Vx60
= 0,0479 jam 2 0.013 1
= ( x 3.28 x 1. 75 x )6
3 0.02
ld 18
td    0,5 = 0.84 menit
vx60 0,6 x60
Menghitung Intensitas
Untuk menghitung Intensitas Hujan menggunakan rumus Mononobe :
2/3
𝑅24 24
𝐼=
24 𝑇𝑐
Ket : R24 = Curah hujan maksimum dalam 24 jam (mm)
(Untuk hitungan dipakai Metode Log Person III periode ulang 10 tahun, yaitu =
137.85 mm/hari)

2/3
137.85 24
𝐼=
24 𝑇𝑐

2/3
137.85 24
𝐼=
24 0.0479

I = 362.48 mm/jam

I = 0.0001007 m/detik
Menghitung Debit

C=
C Perumahan xAPerumahan   C Jalan xAJalan   (C Bahu xABahu )
A
A = (AJalan+ABahuJalan+APerumahan)
• Saluran 1-3
Luas Jalan = Panjang × Lebar C = 0,8
= 18 m × 1,75 m = 31,5 m2
Luas Bahu Jalan = Panjang × Lebar C = 0,8
= 18 m × 0,5 m = 9 m2
Luas Lapangan = Panjang × Lebar C = 0,3
= 22,5 m × 18 m = 504 m2
Luas Saluran 2-1 = 373,5 m2 C = 0,76627

0,8 × 31,5 + 0,8 × 9 + 0,3 × 504 + (0,76627 × 373,5)


𝐶=
31,5 + 9 + 504 + 373,5
C = 0,53736
Q =C xIxA
Q = 0,53736 x 0,0001007 x 819
Q = 0,04431 m3/detik
Menghitung Limbah Domestik
Jumlah penduduk pada akhir periode ulang :
= Jumlah penduduk x (1 + pertumbuhan penduduk)periode ulang

Saluran 1-3

Q limbah domestik saluran 1-3 adalah = Q limbah domestic saluran 2-1 +


Q Limbah Lapangan Rumput

Limbah domestik = 0 + 1.7 x 10-5 m3/dtk

= 1.7 x 10-5 m3/dtk


g. Menghitung Dimensi
Keterangan :
F = tinggi ambang bebas (cm)
h = Kedalaman saluran (cm)
b = lebar saluran (cm)

Alternatif lain untuk mencari dimensi saluran :


C = Koeffisien
- Untuk Q < 0,6 m3/s ; C = 0,17
- Untuk Q > 8 m3/s ; C = 0,24
- 0,6 ≤ Q ≤ 8 m3/s → C = 0,17 ≤ C ≤ 0,23

b=2h h = b/2 R = h/2


Qtotal = 0,0443 m3/det
S = 0,005; C = 0,17; n = 0,013
Lebar Tinggi Tinggi Jagaan Air F = 20 cm

F= C × h h = 20 cm
3ൗ
4 4 × 2. Q. n 2
b= b = 0,17 × 0,151
3 h=
S ൗ4 2
= 0,160 m
0,302
= = 16,0 cm ≈ 20 cm
3ൗ 2 b = 30 cm
4 4 × 2 × 0,0443 × 0,013 2
= 3ൗ = 0,151 m
0,005 4
= 15,1 cm ≈ 20 cm
= 0,302 m = 30,2 cm ≈ 30 cm

Kecepatan Rata-Rata :
1 2 1
V = n × R Τ3 × S Τ2
2
1 h Τ3 1
V= × 2 × S Τ2
n
2
1 0,151 Τ3 1
V= × × 0,005 Τ2
0,013 2
V = 0,97 m/det
h. Dimensi Curb Inlet
Data : Panjang Jalan : 198 m
Lebar Jalan :5m
Lebar Bahu Jalan : 0,5 m
Kemiringan Melintang Jalan :2%
Kemiringan Bahu Jalan :3%
C Jalan : 0,8
Menghitung tc:
Menentukan Jarak Antar Curb Inlet: To Beton = 0,89 menit
D
280
S
280
0,02  7,92m
To Bahu Jalan = 0,66 menit
W 5 To Memanjang = 1,08 menit
To total = 0.89 + 0.66 + 1.08 menit
Jumlah Curb Inlet: = 2.63 menit
𝑃𝑎𝑛𝑗𝑎𝑛𝑔 𝐽𝑎𝑙𝑎𝑛
= 𝐽𝑎𝑟𝑎𝑘 𝐴𝑛𝑡𝑎𝑟 𝐼𝑛𝑙𝑒𝑡 = 0.0438 jam
198
= 7.92 = 25 buah
Menghitung Intensitas :
2/3
Luas Daerah Untuk 1 curb Inlet 137.85 24
𝐼=
=½WxD 24 𝑇𝑐
2
= 2.5 x 7.92 137.85 24 3
= 19,80 m2 𝐼=
24 0.0438
𝐼 = 384.61 𝑚𝑚/𝑗𝑎𝑚
𝐼 = 0.000107 𝑚/𝑑𝑒𝑡𝑖𝑘
Menghitung Debit 1 Curb Inlet

=𝐶𝑥𝐼𝑥𝐴
= 0.8 x 0.000107 x 19.80
= 1.69488 𝑥 10−3 𝑚3 /𝑑𝑒𝑡𝑖𝑘

Tinggi Genangan Air

Y = 0.046 ( D x I )0.5 x ( ½ )0.2


= 0.046 ( 7920 x 384.61 )0.5 x ( ½ )0.2
= 69.89 mm
= 6.99 cm ≈ 7 cm

Tinggi bukaan inlet = 10 cm


Lebar curb inlet
h = Y – ( 0.5 d )
= 7 – ( 0.5 x 10 )
= 2 cm = 0.02 m
𝑄 0,002
L= 3ൗ = 3ൗ
𝐶𝑤 .ℎ 2 3,1 𝑥0,02 2
= 0.23 m = 23 cm
Jadi, dimensi untuk masing – masing Curb Inlet adalah
d = 10 cm
L = 23 cm

10 cm

23 cm

Penampang Curb Inlet Jalan Utama

10 cm

12 cm

Penampang Curb Inlet Jalan Komplek


i. Dimensi Gutter Inlet
Data:
Panjang Jalan : 198 m
Lebar Jalan :5m
Lebar bahu jalan : 0,5 m
Kemiringan melintang jalan :2% Debit ( Q )
Kemiringan memanjang jalan :3% 1 2
𝑄 = 𝑛 × 𝐴 × 𝑅3 × 𝑠 2
1

Jarak antar gutter inlet : 30 m 1 2 1


𝑄 = 0,013 × 0,15 × (0,06)3 × 0,032 = 0,306
Luas Penampang Basah
𝑑 Kecepatan
𝐴=𝐿𝑥𝑑𝑥 𝑄
𝑆 𝑉=
0,1 𝐴
𝐴 = 0,3 𝑥 0,1𝑥 = 0,15 𝑚2 0,306
0,02 𝑉= = 2,04 𝑚/𝑑𝑒𝑡𝑖𝑘
Keliling Penampang Basah 0,15
𝑃 = 𝐿 + (2 × 𝑑) Panjang kisi – kisi minimum
1
𝑃 = 0,3 + 2 × 0,1 = 0,5 𝑚 1
𝑋 = × 𝑉 × 𝑦2
2
Jari-jari Hidrolis 1 1
𝐴 𝑋 = × 2,04 × 0,12 = 0,32 𝑚
𝑅= 2
𝑃 Jadi L = 30 cm
0,03 d = 10 cm
𝑅= = 0,06 𝑚
0,5 X = 32 cm ≈ 40 cm
PENUTUP
Kesimpulan Saran
• Untuk menghitung debit di saluran durasi tidak • Dalam merencanakan drainase komplek perumahan,
mempengaruhi intensitas karena tidak punya lahan, kita harus mengetahui data-data yang diperlukan
melainkan cuma tempat lewat debit yang di hulunya. dalam perencanaan, seperti data curah hujan, data
Kalau dimasukkan nilai td mempengaruhi intensitas, limbah buangan domestik dan topografi dari suatu
maka penampang yang di hilir semakin kecil dari daerah yang akan kita buat drainase.
hulunya karena nilai t nya panjang. • Buat sketsa saluran rencana terlebih dahulu sebelum
• Q yang lewat di saluran itu tidak mesti gabungan Q di melakukan pengolahan data.
hulunya, karena waktu tempuhnya berbeda. “Jadi • Dalam menganalisa waktu konsentrasi (Tc),
debit itu melewati saluran yang sama diwaktu yang Intensitas (I), dan debit (Q) diperlukan ketelitian
berbeda”. untuk mendapatkan dimensi yang ekonomis.
• Desain di saluran ini adalah untuk menampung debit
puncak, bukan debit total. Desain ini adalah desain
real, belum ada pembulatan.