PROJECT DEFINITION
a) Superintendent
b) Engineer
c) Supervisor
d) SHE Officer
e) QA / QC Officer
f) Vendors / Overseers
g) Vendor / Overseer Supervisor
h) Surveyor
i) Workers
DIVISI GEDUNG 1
INTRODUCTION ABOUT AL-FORM
1. Accuracy
Ease of assembly to casting are 5 days in
comparison to construction using conventional
formwork about 7-8 days.
DIVISI GEDUNG 1
2. quality
doesn’t really need repairs,because of the
delicacy and the quality of the panel
DIVISI GEDUNG 1
4. Mobility
Increasing the formwork to the next level can
be done through shipping the material box and
above without using a crane.
Day
NO. Work Item
1 2 3 4 5
1 Cast Plate
2 Marking
DIVISI GEDUNG 1
DIVISI GEDUNG 1
3. Installation of Vertical Element Kicker
The installation of kickers is used to ensure
the position of the panel (elevation) will be the
same for each area.
Installing kickers uses electric welding
equipment, so it is important to ensure that the
PPE used as Apron is available. the equipment
used has been tagged according to quarterly
colors and there is no puddle around the
equipment which can cause short-circuiting.
DIVISI GEDUNG 1
DIVISI GEDUNG 1
4. Vertical Reinforcement
In the Pollux Batam project, the corridor wall
area that initially used light brick with the
Kumkang method was changed to a cast wall with
the following method.
Ensure that workers do the installation of
reinforcement using gloves, this is to avoid the
occurrence of injuries due to scratched sharp
edges. When carrying out reinforcement lifting to
the area, the bond must be ensured, the tagline is
ready.
DIVISI GEDUNG 1
Wiremesh M5
DIVISI GEDUNG 1
5. Provision of Formwork Oil and Panel Mounting
The provision of formwork oil is intended so
that when the release of concrete formwork does
not stick to the Kumkang formwork. After that a
new vertical structure can be installed with the
Panel with a note that the ME Item has entered
first
DIVISI GEDUNG 1
Wedge Pin
Pipa Conduit ME
DIVISI GEDUNG 1
6. Installation of Beams & Shoring Structure
Panels
The position of the beam panel installation is
adjusted to the approved Shop Drawing because
there are several beams with varying dimensions,
so the installation of the panel must be adjusted
to its position according to the image. Shoring
Distance = 1.2 m
DIVISI GEDUNG 1
1200 mm 1200 mm 1200 mm
Proping Head
SHORING
DIVISI GEDUNG 1
7. Installation of Floor Plate Panels
After the beam plate and shoring are
installed, the next step is to install the floor slab
with the position in accordance with the
determined shop drawings.
DIVISI GEDUNG 1
9. Installation of floor plate reinforcement
Before the installation of plate reinforcement,
the panel was given formwork oil and concrete
decking
DIVISI GEDUNG 1
10. Vertical Casting
After all reinforcement is completed, vertical
casting is done first, the Vertical casting method
uses Cast Bucket.
DIVISI GEDUNG 1
11. Casting of Plate Elements and Beams
After all the vertical elements are cast, then
the vertical element is then casting, which is the
beam and plate with the casting area according to
the zone below, the estimated casting for each
zone is below.
DIVISI GEDUNG 1
12. Unloading the Panel
Vertical Panel Dismantling is done one day
after casting, for horizontal elements, namely
plates and beams are carried out 2 days after
casting provided that shoring is done. Demolition
Shoring is done after casting the top 3 floors or
about 15 days after casting the area.
DIVISI GEDUNG 1
4th Floor Pouring
5 days
Shoring
3rd Floor
2nd Floor
10 days
Striking
S t a r t P o i n t F l o o r ( K u m k a n g )
DIVISI GEDUNG 1
QUALITY MANAGEMENT
A. Quality Assurance
1. Ensure that approved work methods are available and work is
carried out in accordance with work methods, contract
documents and document vendors
2. The work method must be known by everyone involved in the
work
3. Providing an Inspection Test Plan (ITP) and ensuring that
internal preparations for work preparation have been fulfilled
before work is carried out
4. Identify all materials, tools, procedures, resources and
management to achieve good work
DIVISI GEDUNG 1
B. Quality Control
DIVISI GEDUNG 1
K3 MANAGEMENT
DIVISI GEDUNG 1
5. Special things that require attention:
- Material placement
- Examination of transportation access
- Lifting equipment does not experience overload
- Use slings in good condition, planned length, and in
accordance with the load lifted
- Attention is directed specifically to chemical
material (admixture), give a special place with
special marks
- Every supporting material must have an MSDS
DIVISI GEDUNG 1
6. Work protection equipment that must be used
is:
- Helmet
- Safety shoe
- Safety glove
- Full body harness
- Safety vest
- Safety glasses
DIVISI GEDUNG 1
THANK YOU