You are on page 1of 57

Project Management:

A Managerial Approach 4/e

By Jack R. Meredith and Samuel J. Mantel, Jr.

Published by John Wiley & Sons, Inc.

Presentation prepared by RTBM WebGroup


Project Management
A Managerial Approach

Chapter 8

Scheduling
Scheduling
A schedule is the conversion of a
project action plan into an operating
timetable
It serves as the basis for monitoring
and controlling project activity
Taken together with the plan and
budget, it is probably the major tool
for the management of projects
Chapter 8-1
Scheduling
In a project environment, the
scheduling function is more important
than it would be in an ongoing
operation
Projects lack the continuity of day-to-
day operations and often present much
more complex problems of
coordination
Chapter 8-2
Scheduling
The basic approach of all scheduling
techniques is to form a network of
activity and event relationships
This network should graphically portray
the sequential relations between the
tasks in a project
Tasks that must precede or follow
other tasks are then clearly identified,
in time as well as function
Chapter 8-3
Scheduling
Such networks are a powerful tool for
planning and controlling a project and
have the following benefits:
It is a consistent framework for planning,
scheduling, monitoring, and controlling the
project
It illustrates the interdependence of all
tasks, work packages, and work elements
It denotes the times when specific
individuals must be available for work on a
given task Chapter 8-4
Scheduling
Network benefits (cont.):
It aids in ensuring that the proper
communications take place between
departments and functions
It determines an expected project completion
date
It identifies so-called critical activities that, if
delayed, will delay the project completion time
It identifies activities with slack that can be
delayed for specific periods without penalty
Chapter 8-5
Scheduling
Network benefits (cont.):
It determines the dates on which tasks may be
started - or must be started if the project is to
stay on schedule
It illustrates which tasks must be coordinated
to avoid resource timing conflicts
It illustrates which tasks may run, or must be
run, in parallel to achieve the predetermined
project completion date
It relieves some interpersonal conflict by clearly
showing task dependencies Chapter 8-6
Network Techniques:
PERT and CPM
With the exception of Gantt charts, the most
common approach to scheduling is the use of
network techniques such as PERT and CPM
The Program Evaluation and Review
Technique was developed by the U.S. Navy in
1958
The Critical Path Method was developed by
DuPont, Inc during the same time period

Chapter 8-7
Network Techniques:
PERT and CPM
PERT has been primarily used for
research and development projects
CPM was designed for construction
projects and has been generally
embraced by the construction industry
The two methods are quite similar and
are often combined for educational
presentation
Chapter 8-8
Terminology
 Activity - A specific task or set of tasks that
are required by the project, use up resources,
and take time to complete
 Event - The result of completing one or more
activities. An identifiable end state occurring
at a particular time. Events use no resources.
 Network - The combination of all activities
and events define the project and the activity
precedence relationships

Chapter 8-9
Terminology
Path - The series of connected activities
(or intermediate events) between any two
events in a network
Critical - Activities, events, or paths
which, if delayed, will delay the
completion of the project. A project’s
critical path is understood to mean that
sequence of critical activities that connect
the project’s start event to its finish event
Chapter 8-10
Terminology
An activity can be in any of these conditions:
It may have a successor(s) but no
predecessor(s) - starts a network
It may have a predecessor(s) but no
successor(s) - ends a network
It may have both predecessor(s) and
successor(s) - in the middle of a network
The interconnections depend on the
technological relationships described in the
action plan Chapter 8-11
Drawing Networks
Activity-on-Arrow (AOA) networks use arrows
to represent activities while nodes stand for
events
Activity-on-Node (AON) networks use nodes
to represent activities with arrows to show
precedence relationships
The choice between AOA and AON
representation is largely a matter of personal
preference

Chapter 8-12
Drawing Networks

Chapter 8-13
Gantt Charts

 The Gantt chart shows planned and actual progress


for a number of tasks displayed against a horizontal
time scale
 It is an effective and easy-to-read method of
indicating the actual current status for each set of
tasks compared to the planned progress for each
item of the set
 It can be helpful in expediting, sequencing, and
reallocating resources among tasks
 Gantt charts usually do not show technical
dependencies
Chapter 8-14
Scheduling

Chapter 8-15
Gantt Charts
There are several advantages to the use of
Gantt charts:
Even though they may contain a great deal of
information, they are easily understood
While they may require frequent updating, they
are easy to maintain
Gantt charts provide a clear picture of the
current state of a project
They are easy to construct
Chapter 8-16
Summary

Scheduling is particularly important to


projects because of the complex
coordination problems
The network approach to scheduling offers
a number of specific advantages of special
value for projects
Critical project tasks typically constitute
fewer than 10 percent of all the project
tasks
Chapter 8-17
Summary
Although research indicates technological
performance is not significantly affected by
the use of PERT/CPM, there did seem to be a
significantly lower probability of cost and
schedule overruns
Network techniques can adopt either an
activity-on-node or activity-on-arc framework
without significantly altering the analysis

Chapter 8-18
Summary
Networks are usually constructed from
left to right, indicating activity
precedence and event times as the
network is constructed
Gantt charts are closely related to
network diagrams, but are more easily
understood and provide a clearer
picture of the current state of the
project
Chapter 8-19
Scheduling

Questions?
Scheduling

Picture Files
Scheduling

Figure 8-1
Scheduling

Figure 8-2
Scheduling

Figure 8-3
Scheduling

Figure 8-5
Scheduling

Figure 8-6
Scheduling

Figure 8-7
Scheduling

Figure 8-8
Scheduling

Figure 8-9
Scheduling

Figure 8-10
Scheduling

Figure 8-11
Scheduling

Figure 8-12
Scheduling

Figure 8-13
Scheduling

Figure 8-14
Scheduling

Figure 8-15
Scheduling

Figure 8-16
Scheduling

Figure 8-17
Scheduling

Figure 8-20
Scheduling

Figure 8-21
Scheduling

Figure 8-22
Scheduling

Figure 8-23
Scheduling

Figure 8-24
Scheduling

Figure 8-25
Scheduling

Figure 8-26
Scheduling

Figure 8-27
Scheduling

Figure 8-28
Scheduling

Figure 8-30
Scheduling

Table Files
Scheduling
Scheduling
Scheduling
Scheduling
Scheduling
Scheduling
Copyright © 2000 John Wiley & Sons, Inc. All rights
reserved. Reproduction or translation of this work
beyond that permitted in Section 117 of the 1976 United
States Copyright Act without the express written
permission of the copyright owner is unlawful. Request
for further information should be addressed to the
Permissions Department, John Wiley & Sons, Inc. The
purchaser may make back-up copies for his/her own use
only and not for distribution or resale. The Publisher
assumes no responsibility for errors, omissions, or
damages, caused by the use of these programs or from
the use of the information contained herein.

You might also like