MANAGING HARD ROCK’S ROCKFEST

By Group 6
Rishabh
Vishal Klandria
Suraj Chaudhary
Shree Khandelwal
Shaloo Nidhi Minz
Sonika
The Rockfest

▰ The Hard Rock Café plans the annual event ‘Rockfest’


▰ Chris Tomasso, Hard Rock Vice President looks after the project
▰ 9 month planning horizon
▰ Attended by over 100,000 fans
▰ It is imperative to rely on project management techniques and
software to manage the project
▰ Consists of 26 activities out of which 10 are identified as major tasks
by Tomasso

2
PATH TIME (WEEKS)

A-B-Y-Z 22

A-B-Q-R-O 25

A-B-Q-R-S 21

A-B-P 30

A-B-H-I-J 28

A-B-D-E-F-G-O 34

A-B-D-L-M 26

A-C-K-L-M 23

A-C-N 16

A-T-U-X-S 28

A-T-V-W 22
3
Critical Path

▰ As maximum time for any of the paths is 34 weeks, that path is selected as
critical path
▰ This path is A-B-D-E-F-G-O

4
Precedence Diagram

5
Slack Time =Late Start-Early Start
=Late Finish-Early Finish
Activity Activity Early Start Early Finish Late Start Late Finish Slack
Time
A 7 0 7 0 7 0

B 3 7 10 7 10 0

C 3 7 10 18 21 11

D 5 10 15 10 15 0

E 6 15 21 15 21 0

F 4 21 25 21 25 0

G 2 25 27 25 27 0

H 4 10 14 16 20 6 6

I 4 14 18 20 24 6
Continued
Activity Activity Early Start Early Finish Late Start Late Finish Slack
Time
J 10 18 28 24 34 6

K 2 10 12 21 23 11

L 3 15 18 23 26 8

M 8 18 26 26 34 8

N 6 10 16 28 34 18

O 7 27 34 27 34 0

P 20 10 30 14 34 4

Q 4 10 14 19 23 9

R 4 14 18 23 27 9
7
Continued
Activity Activity Early Start Early Finish Late Start Late Finish Slack
Time
S 3 25 28 31 34 6

T 4 7 11 13 17 6

U 6 11 17 17 23 6

V 7 11 18 23 30 12

W 4 18 22 30 34 12

X 8 17 25 23 31 6

Y 6 10 16 22 28 12

Z 6 16 22 28 34 12

8
Activities with Slack >8 weeks

Slack > 8 weeks for the following activities:


• C
• K
• L
• M
• N
• Q
• R
• V
• W
• Y
• Z
9
Major Challenges Faced

Having good coordination among people Since projects like these go on for a long time,
performing different activities/processes to keeping up the dedication and motivation of
carry out the project efficiently the staff throughout the project is important

All the critical processes need to be taken


Ensuring security and safety especially when special care of and necessary measures and
thousands of fans are gathering in one place back up should be planned beforehand so as to
complete the project on time