Professional Documents
Culture Documents
Management System
(EVMS)
February 7, 2
Project Management
Terms - IV
Project -
• A temporary endeavor
• To create a unique product or service.
Program -
• A group of related projects - e.g. DSR,
VSCS, URET, STARS, ...as part of NAS
• Managed in a coordinated way - ACT-
200 Coordinating
• Usually include elements of ongoing
operations
February 7, 6
Earned Value Management
System (EVMS) - I
EV - Tool for Measuring Project
Performance
Compares work actually accomplished
to work planned to determine if cost
& schedule performance is as planned
EV is an Early Warning System
Helps management make proactive
decisions to keep projects on course
February 7, 7
Earned Value Management
System (EVMS) - II
EV Integrates Cost, Scope &
Schedule measurements
EV Involves Calculating 3 key values
for each activity
• Budget - BCWS
• Actual Cost - ACWP
• Earned Value/Physical Progress - BCWP
Basis for variance analysis
February 7, 8
Planning for EVMS - I
Create a work breakdown structure
Organize work into discrete work
packages and activities
Allocate a budget to each of the activities
Develop a schedule and Assign resources
to accomplish each activity on the
schedule
Be sure to include all work in the schedule
February 7, 9
Planning for EVMS - II
Award performance credit for physical %
complete using any of these methods
0-100
• Short duration tasks < 160 hours
• EV is Zero until activity is complete
50-100
• Duration less than 600 hours
• 50% at start of activity & 50% at completion
February 7, 10
Planning for EVMS - III
Interim milestone;
• Duration less than 600 hours
• Based on completed milestone for task
Level of Effort (LOE)
• Long duration & consistent tasks
• Difficult to measure - no deliverables
• Measured by duration of time used e.g. 10
weeks support is 50% complete at 5 weeks
February 7, 11
Tracking & Analysis
Each update cycle/Reporting Period
• Monthly or Bi-Monthly
• Obtain physical % complete for each task
• Calculate EV for each task
• Sum up EV for all tasks as project EV
• Calculate actual expenditure for actual
work completed during the period
• Compare the Cumulative EV to Actual
expenditure
February 7, 12
Elements of EV Analysis - I
Performance indices relate value of
work performed to dollar spent. e.g. CPI
= 0.65 means that for every dollar
spent, actual value of the work
performed is $0.65.
Cumulative CPI used to forecast project
cost at completion (also slide 17)
Cumulative SPI used to forecast project
completion date (also slide 17)
February 7, 13
Elements of EV Analysis -
II
Cost Variance - Difference between
budgeted cost of work scheduled &
actual cost of work performed
• CV = BCWP - ACWP
Schedule Variance - Difference between
budgeted cost of work scheduled &
actual cost of work performed
• SV = BCWP - BCWS
February 7, 14
Elements of EV Analysis -
II
SPI - BCWP/BCWS
SPI => 1.0, Project Schedule
performing as planned or better
SPI < 1.0, Project not performing
as planned - needs help
February 7, 15
Elements of EV Analysis -
III
CPI - BCWP/ACWP
CPI => 1.0, Project Cost performing
as planned or better
CPI < 1.0, Project Cost not
performing as planned - needs help
% Over/Under Budget - CAC - BCWS
February 7, 16
Project Cost & Schedule
Forecast Methods
Estimate at Completion (EAC) is
total cost to complete an activity,
work package, or a project
expressed as::
• EAC = Actuals-to-date + Estimate to
complete (ETC)
Cost EAC - BAC/CPI
Schedule EAC - BAC/SPI
February 7, 17
EV Reporting
Interpret the results of the
calculations - Slides 8 - 11
Take or recommend corrective
action as necessary
February 7, 18
Conclusion
EVMS provides management with an
effective
• tool for program planning and control
• early warning system for program mgt.
EV Integrates Cost, Quality, &
Schedule objectives when
appropriately implemented
Must a baseline for measurements,
and control at the start of project.
February 7, 19
References
Project Management Institute (PMI), 1996.
A Guide to the Project Management Body
of Knowledge (the PMBOKTM Guide) -
Ray W. Stratton, 1999. Improving SPI and
CPI Calculations on LOE Heavy Programs,
Proceedings of the 30th Annual PMI
Seminars & Symposium
Fleming and Koppeman, 1996. Earned
Value Project Management.
February 7, 20
Thank you for Listening