Professional Documents
Culture Documents
Value Management
Earned Value Management is a methodology
used to measure and communicate the real
physical progress of a project taking into
account the work complete, the time taken and
the costs incurred to complete that work.
Term Formula
Earned Value Budgeted Cost of Work Performed (BCWP) =
budgeted cost of task X % complete
Cost Variance CV=BCWP-ACWP (actual cost of work performed)
Schedule Variance SV=BCWP-BCWS (budgeted cost of work
scheduled)
Cost Performance Index CPI=BCWP/ACWP
Schedule Performance Index SPI = BCWP/BCWS
90,000
80,000
70,000
60,000 BCWS
50,000
$
ACWP
40,000
30,000
BWCP
20,000
10,000
-
1 2 3 4 5 6 7 8 9 10 11 12
Month
If the costs are incurred linearly in proportion to activity completion, find out the
I)Budgeted Cost of Work Scheduled (BCWS)
II)Budgeted Cost of Work Performed (BCWP)
III)Cost Variance
IV)Cost Performance Index (CPI)
Schedule Performance Index (SPI)
Jan 2011 Project Control - Earned Value Management System, Slide 36 of 37
By Prof. Nadpurohit
Jan 2011 Project Control - Earned Value Management System, Slide 37 of 37
By Prof. Nadpurohit
Why Earned Value Analysis??
• You can’t tell what your true cost variance
is because you don’t know where you are
relative to schedule
– Suppose you are behind schedule but also
you have spent less than what the schedule
has called for. Are you really under budget?