DRY DOCKING

• THE MAJOR EVENT

• PREPARING THE VESSEL FOR THE NEXT 30MONTHS

• COST
DRYDOCKING
MAINTENANCE
ALTERNATIVES

•CREW
• TRAVELLING SQUADS
• SHORE ASSISTANCE
• COMPARE WITH SHIPYARD
• HEAVY WORK INVOLVING HIGH LIFTS
TRANSPORTATION
• LOWEST COST
DRYDOCKING
SPECIFICATION

• MOST IMPORTANT DOCUMENT

• TERMS/CONDITIONS

• DESCRIPTION OF ALL JOBS

• COMPILING THE SPECIFICATIONS AS


EARLY AS POSSIBLE
DRYDOCKING
FLOW CHART

REPAIR LIST FROM VESSEL


LIST OF SURVEYS

VISIT TO THE VESSEL BY SUPT.


VERIFICATION OF LIST

ENQUIRY TO SHIPYARDS

EVALUATION OF QUATIONS/
NEGOTIATIONS/
SELECTION OF YARD
ORDERING OF SERVICES
AND SPARES

VERIFICATION OF REPAIR LIST

NOMINATION OF AGENT

DRYDOCKING/VERIFICATION
OF WORK DONE

SHIPYARD BILL
NEGOTIATION AND
SETTLEMENT
DRYDOCKING
SUCCESS FACTORS

• KNOWING THE VESSEL

• GOOD AND COMPLETE


SPECIFICATION

• PLANNING

• CONTROLLING THE YARD

• ADEQUATE RESOURCES
DRYDOCKING
THE SUCCESSFULL DD

• THE SPECIFICATION TO COVER BETWEEN 80-90%


OF ALL WORK

• NO MAJOR EXTRA COST

• WITHIN THE STIPULATED TIME AND ESTIMATED


COST
DRYDOCKING
PREPARATION FOR
ENTRY

• VESSEL TO BE FREE FOR HOT WORK AND


ENCLOSED PLACES TO BE VENTILATED AS
REQUIRED

• BUNKERS / F.WATER / BALLAST ETC. BE SUITABLY


DISTRIBUTED TO ACHIEVE SUGGESTED TRIM.

• WORKS IN SPECIFICATION IDENTIFIED / MARKED.

•SUPERVISION DUTIES DECIDED AND AGREED TO.


DRYDOCKING SURVEYS
• A LIST OF ALL ITEMS TO BE SURVEYED IS KEPT READY

• LIST OF ALL CERTIFICATES EXPIRING IS READY

• LIST OF CONDITIONS OF CLASS TO BE DEALT WITH IS CLEAR

• LIST OF NEW APPLICABLE REGULATIONS TO BE ATTENDED TO IS


AVAILABLE.

• MODIFICATIONS /FABRICATIONS IF ANY AS PER NEW


REGULATIONS SHOULD ALREADY BE IN THE SCOPE OF REPAIRS

• LIASE WITH THE SURVEYOR AND AGREE ON THE SCOPE


OF INSPECTIONS / DURATION OF INSPECTIONS.

• TO KEEP SURVEYOR INFORMED ABOUTTHE DOCKING SURVEYS


AND GET A LIST OF RECOMMENDATIONS AT THE EARLIEST FOR
COMPLETION OF STATUTORY CERTIFICATES.

• GET SURVEYORS APPROVAL FOR THE SCOPE OF REPAIRS


INVOLVING CLASS.
PRE DOCKING SURVEYS

• GET THE GAUGING REPORTS VERIFIED AND ESTABLISH


THE SCOPE OF STEEL REPAIRS.

• AGREE WITH SURVEYORS ACTION PLAN FOR CREDITING


OF CARGO /BALLAST TANKS FOR(INTERMEDIATE/SPECIAL)
SURVEYS

• AGREE ON TESTING PROCEDURES / REPAIR PROCEDURES


IF ANY AND PRESS TEST OF TANKS AS PER
REQUIREMENTS.

• IT IS ADVANTAGEOUS TO PLAN TO CREDIT ALL TANKS


PRIOR TO DOCKING ,THE TRADING PATTERN PERMITTING.

• TO CREDIT MAX POSSIBLE CSM ITEMS PRIOR TO DOCKING.


DRYDOCK WORK SCHEDULE
• SHIP STAFF AND YARD JOBS ARE CLEARLY UNDERSTOOD /
PLANNED AND CARRIED OUT WITHOUT INTERFERANCE

• YARD JOBS (INPROCESS AND COMPLETION AND TESTING)


ARE PROPERLY SUPERVISED

• SPARES SUPPLIED TO YARD BY VESSEL / ARRIVAL OF NEW


SPARES ETC ARE PROPERLY RECORDED AND MONITORED

• DECISION MAKINGS ARE PROPERLY DELEGATED

• ONBOARD TIMINGS ARE SUITABLY ALTERED TO GET MAX


PRODUCTIVITY.

• SHIPBOARD MEETINGS ARE PROPERLY TIMED TO CONTINOUSLY


MONITOR THE SITUATION.

• REPAIR TEAMS IF ANY ARE TO BE PROPERLY UTILISED AND


EFFECTIVELY MONITORED
DRY DOCKING SAFETY
• SAFETY MEETINGS INVOLVING YARD AND SHIP STAFF TO
BE PROPERLY TIMED AND WELL ATTENDED
• VIOLATION OF YARD GUIDELINES ARE TO BE STRICTLY
DISCOURAGED (HOTWORK IN ENGINE ROOM ETC.)
• TANK ENTRIES ETC. ARE TO BE DONE STRICTLY ACCORDING TO
PROCEDURES AND PERSONNEL TO BE DOUBLY CAREFUL WHILE
CLOSING OPENINGS
• IMPORTANCE TO BE GIVEN TO ATTIRE.
• EXTREME CARE TO BE EXERCISED WHILE TURNING ENGINES/OPERATING
STEERING GEAR/STARTING BLOWERS/SWITCHING ON ELECTRICAL
BREAKERS/PRIOR TRIALS ETC.
• SYSTEMS ARE TO BE PROPERLY DEACTIVATED AND RENDERED SAFE
(DEPRESSURISE HYDRAULIC LINES/EMPTY OIL LINES/DRAIN SEA WATER
LINES ETC)
• BOUNDARIES OF FUEL OIL TANKS ARE PROPERLY MARKED
• THE TANK DRAIN PLUGS ARE PROPERLY MARKEDIIDENTIFIED
AND PROTECTED FROM INADVERTANT OPENING.
• FRAME NOS ARE SUITABLY MARKED ON DECK/SIDES AND BOTTOM.
• VENT PIPES ARE SUITABLY MARKED/IDENTIFIED.
DRYDOCKING ECONOMY
THE FOLLOWING TO BE BORNE IN MIND
• REPAIRS DONE THROUGH AFLOAT WORKSHOPS ARE ALWAYS CHEAPER
• MOST OF THE SPECIALIZED JOBS ARE
DONE THRU SUBCONTRACTORS OR REPRESENTATIVES OF OEMS WITH A
SURCHARGE.
• A REPAIR TEAM WILL ALWAYS BE CHEAPER IF THE MATERIALS CAN
BE ORGANIZED CHEAPLY.
• YOU WILL LOOSE A FORTUNE IF YOU NEED TO DO TANK CLEANING
INSIDE A YARD.
• ALL ADDITIONAL WORK WILL BE CHARGED AT A VERY HIGH RATE.
• THE SMALLER THE FABRICATION JOBS/STEEL JOBS ON DECK--THE MORE
UNECONOMICAL IT BECOMES
• QUANTITIES OF STEEL WORK/PIPE WORK/HULL PAINTING ETC
ARE TO BE DETERMINED WITH RESPECT TO CONDITIONS IN TARIFF LIKE
• MINIMUM KGS PER LOCATION
• MINIMUM METERS PER LOCATION.
• CHARGES FOR INWAY AND ACCESS WORK
• MINIMUM SURFACE (BLASTING)
• MINIMUM NO OF POINTS PER LOCATION(GAUGING)
DRYDOCKING ECONOMY (CONTD)
• WATCH OUT FOR THESE DANGER AREAS
PIPE CLAMPS
TRANSPORT TO WORKSHOP
MACHINING/FABRICATION ITEMS
CLEANING
VENTILATIONS/BILGES/SERVICES.

•IT WOULD BE COST EFFECTIVE TO TAKE A QUOTE FOR THE FOLLOWING:-


- UNSHIPMENT OF RUDDER
- RENEWAL OF CARRIER BEARING WITH YARD MATERIAL
- RENEWAL OF PINTLE BEARING WITH YARD MATERIAL
- STANDARD TARIFF FOR O’HAUL OF MOTORS(KW BASIS) /
PUMPS(KW BASIS)/PIPES(METER BASIS)/ TESTING OF
PIPES(METER BASIS) /TESTING OF WELDS(METER BASIS) /
SUPPLY OF SKILLED AND UNSKILLED MANPOWER (HOURLY BASIS)/
MAGNAFLUX / RADIOGRAPHY AND OTHER TESTS / STAGING
(TOWER AND BLOCK/BUILDUP OF PITS/REWELD BOTTOM PLATES

• BEST ECONOMY IS AN OUTCOME OF A TIGHT SPECIFICATION


DRYDOCKING COMMERCIAL
THE FOLLOWING IMPORTANT ASPECTS ARE COVERED BY
THE CONTRACT DOCUMENT

• TIME OF COMPLETION
• DISCOUNT OFFERRED
•PENALTY CLAUSES
•REPAIR SPECIFICATIONS
• REPAIR SPECIFICATIONS
• PAYMENT SCHEDULE & REDELIVERY OF VESSEL
• OWNERS RIGHTS
• YARDS RESPONSIBILTY AND LIMITATIONS
• GUARANTEE -
• ENGAGEMENT OF SUBCONTRACTORS AND SURCHARGE.
• WORK DONE CERTIFICATES
• AUTHORITY AND OWNERS REPRESENTATIVE
• CANCELLATION CLAUSE / TERMS
- FACILITIES TO BE PROVIDED TO OWNERS REPRESENTATIVES
- CHANGE OF SCOPE OF REPAIRS
- SPARES AND STOWAGE
- PILOTAGE TUGS ETC FOR SHIFTING FOR YARDS CONVIENIENCE
DRYDOCKING COMMERCIAL (CONTD.)

• THE OWNERS ENQUIRY CONTAINS THE CONDITIONS


OF THE OWNERS

• THE YARDS OFFER CONTAINS THE YARDS


RULES AND CONDITIONS

• THE CONDITIONS IN THE YARDS OFFER STAND VALID


EVEN IF THEY ARE CONTRADICTORY TO OWNERS
REQUEST ONCE THE VESSEL HAS BEEN STEMMED

• THE AREAS OF CONTRADICTIONS ARE TO BE AGREED


UPON / THRASHED OUT PRIOR STEMMING THE VESSEL.
DRYDOCKING TECHNICAL
CORROSION PROTECTION

ANODES

- CHOICE OF THE CORRECT TYPE AND QUANTITY OF ANODES.

- REPLENISHING OF ELECTRODES FOR IMPRESSED CURRENT


SYSTEMS IF FITTED.

- PROTECTION OF ANODES WHILE PAINTING

- CORRECT PLACING OF ANODES UNDER GUIDANCE FROM SUPPLIER.

- REMOVAL OF OLD ANODES


CORROSION PROTECTION

• LIFE OF THE VESSEL AND FUTURE EXPENDITURE DEPEND ON THE


QUALITY OF WORK DONE IN EVERY DOCKING.

• GET PROPER ADVICE FROM LEADING PAINT MANUFACTURER


AND GET AN IDEAL SCHEME

• ADVISABLE TO GO FOR THE BEST SURFACE PREPARATION AND


CHOOSE REAL GOOD PAINT(TYPE COMPATABLE WITH PREVIOUS
PAINT)

• PROCESS INCLUDE--H.P WASHING /FLOGGING/GRIT BLASTING


(S.A 1/2/2.5) OR HYDRO BLASTING/GRIT
SWEEPING/PRIMER COAT(2 OR 3 TOUCH UP COATS FOLLOWED BY
1 OR 2 FULL COATS)AS PER RECOMMENDED MICRON THICKNESS
/ STRIPE COATS (ON DECK)

• IMPORTANT ASPECTS ARE--PROPER SURFACE PREPARATION AND


CONTROL ON HUMUDITY.
DRYDOCKING
TECHNICAL

• STEEL WORK

- INSPECTION OF WELD QUALITY / FITUPS

- KEEP TRACK OF THE DIMENSIONS AND LOCATIONS


(FOR COMMERCIAL REASONS)

• RUDDER-

- BUSH CLEARANCE
- DROP
- SEALING 0 RINGS FOR THE TAPER SURFACE OF THE PINTLES
- PROPER CEMENTING OF PALM BOLTS
- WATER BOX CLOSING PLATE WATER TIGHTNESS
- JUMPING BAR /CLEARANCE
- KEY WAYS
DRYDOCKING
TECHNICAL

• PROPELLER-

- PUSH UP AND PULL UP HYDRAULIC PRESSURES(PUSH UP CURVE)


- KEY WAYS
- POLISHING

• ANCHORS AND CHAIN-

- GAUGING AND REVERSAL IF REQD


- CLNG OF CHAIN LOCKER AND INSP

• HULL

- GAUGING OF STIKER PLATES


- BUILD UP OF PITS
- WEE OUT/GOUGE AND BUILD UP WELD SEAMS OF BOTTOM
PLATES
- INSPECTION OF DRAIN PLUGS
DRYDOCKING
TECHNICAL (MACHINERY)

• CLEANING OF COOLERS AND HEATERS

• O’HAUL OF LARGE ELECTRIC MOTORS

• BALANCING OF ROTATING EQUIPMENTS AS REQD.

• O’HAUL OF MACHINERY AS REQD

• RECHECK ALIGNMENTS OF MACHINERIES IF DISTURBED.

• REMOVE DEFICIENCIES IN AUTOMATION AND CONTROL EQUIPMENT


AS REQD.
DRYDOCKING
INSTRUMENTATION AND
NAVIGATING EQUIPMENTS

• CALLIBRATION OF ELECTRICAL SWITCHBOARD METERS/OTHER


ELECTRICAL AND MECHANICAL MEASURING DEVICES

• O’HAUL OF MAIN BREAKERS AND CALLIBRATING SAFETY TRIPS.

• RECTIFY DEFICIENCIES IN NAVIGATING INSTRUMENTS

• RECTIFY DEFICIENCIES IN SAFETY SYSTEMS IF ANY.


DRYDOCKING
PRIOR FLOODING

IMPORTANT ITEMS PRIOR FLOODING

-ALL TANK DRAIN PLUGS ARE INSPECTED AND VACUUM


TESTED AFTER FITMENT

- ALL ANODES ARE FUNCTIONAL

- SEA CHEST GRATINGS ETC ARE SECURED

- CORRECT BALLAST IS TAKEN.

-INSPECT RUDDER (WATER BOX) / PROPELLER /ROPE


GUARD
DRYDOCKING
PRIOR UNDOCKING

PRIOR UNDOCKING
-ALL CARGO/BALLAST TANKS ARE CLEAN FROM REMNANTS OF
STEEL WORK

- CARGO LINES ETC PRESSURE TESTED / PUMPS ARE TRIED OUT

- ALL TANK VALVES(IF REMOTE OPERATED) ARE TRIED OUT

- HATCH COVERS ETC AND OTHER TYPE OF CARGO GEAR ARE TRIED
OUT AND PROPERLY SECURED

- ALL SEA CHESTS ARE PROPERLY PURGED OF AIR

- ALL EQUIPMENT IN ENGINE ROOM ARE TRIED OUT

- MAIN ENGINES/BOILERS ARE PREHEATED AND READY FOR TRIALS


DRYDOCKING
SEA TRIALS

• SEA TRIALS

- ENGINES ARE RUN TO REQUIRED SPEED, MOVEMENTS ARE


CHECKED.

-STEERING IS CONFIRMED TO BE PERFORMING SATISFACTORY

- STERN TUBE OIL IS CHECKED FOR MAINTAINING LEVEL.

• THE VESSEL MAY PROCEED TO SEA ON


SATISFACTORY COMPLETION IN SOME
CASES