Deputy Director, B.E Civil, Mst Const. Law(Melb) CIArb PGD in International Commercial Arbitration, Oxford UK, PMP FIDIC Provides for a comprehensive mechanism of Notices to inform the Engineer or the Employer whenever the Contractor commences, continues or completes his obligations under the Contract.
From the Employers perspective, it forewarns
and saves the Employer from the Ambush of Contractual Claims by the Contractor at any convenient time. Clause 6.3, Notify Engineer reasonably in advance non-issuance of a drawing or Instruction that will result in disruption or delay
Clause 12.2, Notify Engineer reasonably in
advance on encountering on Site unforeseeable physical Obstruction or Conditions
Clause 27.1, Notify Engineer and seek
instructions of discovery of fossils, coins and archaeological articles Clause 44.2, Notify Engineer reasonably in advance of events giving rise to entitlement of Extension of Time for Completion of Works
Clause 65.5, Notify Engineer reasonably in
advance of the Cost incurred as a result of Special Risk to works
In some contracts, responsibility to Notify the
Engineer may cover other Express circumstances. Clause 52.2, Notify Engineer of its intention to Claim additional payment or a varied rate or price within 14 days of receiving an Engineers Variation Order. This Notice can also be given by the Engineer.
Clause 53.1, Notify Engineer reasonably in advance of
its intention to Claim Time or Cost or both within 28 days under relevant provisions.
Failure to give Notice, however will not deprive but
restrict the entitlement of the Contractor under Clause 53.4 to whatever he can prove on the basis of contemporary records. Notice to claim is an express requirement in FIDIC 1999 suite However under Clause 67.1, Notice of intention to refer a dispute for Engineer’s Decision is not required
Any dispute can be referred any time to the
Engineer
Notice of Intention to Arbitration be given
under Clause 67.1 when ◦ A) Engineer fails to give decision within 84 days Or Other party is dissatisfied with Engineer’s Decision Broadly, two types of Claim exist in any Construction Contract, a) Cost Claim b) time Claims
Clause 53 covers the Procedure of Cost
Claims Clause 44 covers the Procedure of Time Claims Both start generally with a ‘Notice of intention’. Broadly, two types of Claim exist in any Construction Contract, a) Cost Claim b) time Claims
Clause 53 covers the Procedure of Cost
Claims Clause 44 covers the Procedure of Time Claims Both start generally with a ‘Notice of intention’. Under Clause 8.2, Contractor is responsible for the following risks ◦ Method of Construction ◦ Site Operations ◦ Any part of Permanent works designed by the Contractor ◦ Any part of the Temporary Works designed by the Engineer but Contractor undertakes to take responsibility Under Clause 8.2, Engineer is responsible for the following risks ◦ Design of Permanent Works or Temporary Works ◦ Specifications of Permanent Works or Temporary Works
◦ Under Clause 20.4, The Risk of any loss or
damage by events as mentioned in this Clause, are exclusively on the Employer Indemnity is considered to be a contractual agreement between two parties whereby one party agrees to pay for potential losses or damages in certain circumstances Employer Indemnifies the Contractor Under clause 65.1, for any loss or damage to the permanent works due to events such as war, rebellion etc (special risks) Under clause 22.3, damage against any injury to any person at project site where negligence can be attributed to Employer’s personnel. Employer Indemnifies the Contractor Under clause 22.3, for any liability arising due to non compliance with local laws, permissions etc for which Contractor can not be held responsible. Under clause 30.1, any claim made by local road authority for damage to local roads when Contractor is not responsible. Under Clause 71.1, any damage due to restriction imposed by the State on transfer of currency restrictions Contractor Indemnifies the Contractor Under clause 22.1, loss of life or any injury to any person(third person) or property at project site where negligence can be attributed to Contractor’s personnel.
Under clause 24.1, claims, costs, charges,
compensation in case of death or injury to employees of the Contractor or subcontractor
Under clause 26.1, against all penalties and
liability of every kind imposed by local law regulations etc. Contractor Indemnifies the Contractor Under clause 28.1, all claims and damages due to infringement of Intellectual property or patent laws
Under clause 29.1, claims, costs, charges,
compensation in case improper interference with public convenience i.e blocking of roads etc
Under clause 30.2, against all claims of
damage to local roads caused by Contractor’s machinery Insurance:- A contract (an insurance contract) whereby one person, the insurer, promises and undertakes, in exchange for consideration of a set or assessed amount of money (called a "premium"), to make a payment to either the insured or a third-party if a specified event occurs, also known as "occurrences". Contractor Insures Under Clause 21.1, in joint name of Contractor & Employer against damage to Works or Loss of materials brought to site due to Special risks
Under Clause 23.1, in joint name of
Contractor & Employer against liability for death or injury to persons and damage to property as a result to performance of contract Contractor Insures Under Clause 24.2, Insurance against liability for all damages or compensation payable to any workman or other persons in the employment of Contractor.
In FIDIC Redbook 1987, Clause 24 & 25 relate
to insurances. Performance Security is the amount stated in the Contract which serves as a guarantee for Performance of the Contractor
Should remain valid and enforceable till the
issuance of the Defects Liability Certificate or as provided by the Contract Can be presented in the shape of guarantee or bond as provided in the Contract. In FIDIC Red Book 1987, relevant Clause are 10.1,10.2 & 10.3 Retention is a percentage (often 5%) of the amount certified as due to the contractor on an interim certificate, that is deducted from the amount due and retained by the client.
Under Clause 60.3, 50% of Retention Money is
released upon issue of TOC and remaining 50% on expiry of DLP Thank You