Infrastructure Development Works
Administrative Approval (Original) : Rs.607.129 Million
26.08.2012
Revised Administrative Approval : Rs.904.77.00 Million
20.12.2017
Overall Expenditure (Up to Dec, 2019) : Rs.722 Million
Agreement
Sr. Date of Amount Date of T.S Expenditure
Description of Work
No. Award (Rs. in Completion Estimate up date
Million)
Agreement
Sr.
Date of Date of T.S Amount Expenditure
No Description of Work
Award Completion Estimate (Rs. in up to date
.
Million)
5 Sub-Engineer SSS 1 1 0
8 Driver JSS 1 1 0
10 Chowkidar Attendent 2 0 2
11 Frash Attendant 1 1 0
Total 12 6 6
Detail of Maintenance Staff
Pay Scale
Sl. No. Name of Posts (Monthly/Daily Sectioned Working Vacant Remarks
Wages)
Hired a Private
Security Company
6 Security Staff JSS 16 12 4 for security of
PGSHF Scheme Dg
Khan
Total 37 24 13
USER CHARGES DETAIL
1 1 Kanal 664,840/-
2 10 Marla 846,735/-
3 07 Marla 756,285/-
4 05 Marla 37,100/-
Total = 2,304,960/-
PROGRESS OF SCHEME
LONGITUDINAL CRACKS IN
ROAD NETWORK:
Demand Notice amounting
Longitudinal Cracks started to appear
in the Road Network which was Rs. 136,320/- of Deep Testing
conveyed to M/S NESPAK in August- was received on 02-12-2019
2018 and requested was made to from Road Research and
depute his Team for site visit and Material Testing Institute
recommendations. M/S NESPAK had which was forwarded to E.D
made two (02) site visit and furnished (Engg) Office on 03-12-2019
3. their report along with remedial followed by reminders on
measures which were not as per actual 11-12-2019 & 23-12-2019. As
on-ground realities. In November 2019 per direction of E.D (Engg),
E.D (Engg) directed to perform deep
testing of road network of PGSHF on 31-12-2019 Director
Scheme which was performed on 26 & (RRMTI) was approached
27 November 2019. Now funds are for the concession of testing
awaited in this regard for the issuance rates if any which was
of Test Resport. refused by them
telephonically.
Sr. No. DESCRIPTION SUGGESTIONS
CONSTRUCTION OF FALLEN
BOUNDARY WALL:
Boundary wall of almost length of 180ft
was fallen in April-2018 which was
conveyed to Consultant. M/S NESPAK
visited the site and had changed the design
of Boundary Wall and recommend the
Strengthening of Boundary Wall.
This office prepared the Estimate
Decision for provision of
amounting to Rs. 4.54 (M) and submitted
funds for reconstruction
to E.D (Engg) office for arranging the
4. of Fallen Boundary Wall
Approval vide T/O Letter No.
has to be made by the
PGSHF/DGK/PD/E.D(Engg)/3786 Dated:
Competent Authority.
15-10-2018. As directed by E.D(Engg)
office, an Office Note according to the
Contractual Clauses of Stake Holders was
submitted to E.D (Engg) on T/O No.
PGSHF/DGK/PD/ED(Engg)/4008 Dated:
26-03-2019 so that the estimated amount
Rs. 4.54 (M) will be charged to both Stake
holders which is still awaited.
Sr. No. DESCRIPTION REMERKS/STATUS
5. INFRASTRUCTURE DEVELOPMENT
(Balance Work):
The Revised Detail Estimate for
Balance Work amounting to Rs. 94 (M)
was got approved from the Competent
Authority after completing codal
formalities. Pre-Qualification
Documents from the competitive
bidders for the Infrastructure
Development Works (Balance Work)
was received on 23-12-2019. Seven (07)
Bidders had submitted the Pre- Work in Progress.
Qualification Document out of Eleven
(11) and Pre-Qualification Documents
along with checklist Performa is
forwarded to Director (Planning) for
their evaluation and arranging
approval from Competent Authority.
Sr. No. DESCRIPTION REMERKS/STATUS
APPOINMENT OF CONSULTANT
M/S NESPAK furnished the revised
reduced rates i.e. Rs. 1,018,296/- against the
initially quoted rates i.e. Rs. . 1,218,296/-.
Deputy Director (TP) office was
replied with the remarks i.e. Quoted
Rates are relatively high and request
to Re-Negotiate the rates with M/S
NESPAK. General Manager NESPAK
was requested vide T/O Letter No.
5014 dated: 02-12-2019 to reduce their
rates and followed by a meeting in the Continuously pursue the
6. office of M/S NESPAK on Dated: 06- matter at own level
12-2019 and telephonic reminder on
dated: 13-12-2019 & 18-12-2019 & 28-
12-2019 and written reminder dated:
23-12-2019. Mr. Imran Ahmad
Principal Engineer NESPAK intimated
the case is with competent authority
and upon approval of competent
authority further reduced rate if
possible for supervision of balance
work will be provided at the earliest.
Sr. No. DESCRIPTION REMERKS/STATUS
FINALIZATION OF CONTRACTOR
ACCOUNT:
E.D (Engg.) may head
- Snag Lists have attended by
Contractors M/S Trend Scatter and M/S the meeting along with
Haji Pasham on 10-12-2019 which was the M/S NESPAK and
conveyed to M/S NESPAK to Schedule Contractors to resolve
the visit for Verification along with
7. Contractor and PGSHF. the pending issues. M/S
- Final Bills are with Consultants for NESPAK may also be
Verification advised to take keen
- Extension of Time of Contractors are interest in the issues of
Pending. subject Scheme.
- Agreement Enhancement of
Contractors are Pending.
8 DEMAND OF FUND amounting Rs. Funds may please be
136,320/- on account of Deep Testing released at the earliest so
was received on 02-12-2019 from Road
Research and Material Testing that requisite report may
Institute which was forwarded to E.D please be get from Road
(Engg) Office on 03-12-2019 followed Research and Material
by reminder dated 11-12-2019 and Testing Institute
recently reminded on 23-12-2019 for
arrangement of Funds.
Sr. No. DESCRIPTION REMERKS/STATUS
ON GROUND AREA
DEMARCATION OF SCHEME.
On-Ground Area Demarcation of
Scheme was started on 16-12-2019 with Work is in progress and
the available resources and man power
after the cleaning of Scheme area. On- will be completed within
Ground Area of Block-C has been Two to Three weeks.
9. completed and list has been prepared as
per Master Plan R-06. On-Ground Area
Demarcation of Block A & B is in
progress.
PICTURES
ENTRANCE GATE
CENTRAL PARK
BERM & MEDIAN
MAINTENANCE OF
BERM
CLEANING OF PLOT