Professional Documents
Culture Documents
1
The learning curve
4
Table 1 illustrates how an 90 percent learning curve works, as
units are doubled from 1 to 2, to 4, to 8.
In constructing Table 1 , it was assumed that we already
knew the learning rate that applied to this particular situation.
However, it must be appreciated that, in the real world, this rate
can only be established by observation. Records must be kept of
the number of units/batches produced and the associated time
taken, in order to construct the table.
5
Cumulative average time learning rate: 0.90
Cumulative average
Cumulative total
Batches time per batch
(hours)
(hours)
1 100.00 100
2 90.00 180
4 81.00 324
8 72.90 583
16 65.61 1,050
32 59.05 1,890
64 53.14 3,401
128 47.8. 6,122
256 43.05 11,021
512 38.74 19,835
6
Uses of the learning curve
(i) In circumstances where the learning curve is likely to
operate, that is, in complex assembly operations, knowledge
of the rate of learning can help in price setting.
(ii) When setting budgets, the effects of the learning curve
should be taken into account. Standard cost should reflect the
point that has been reached on the learning curve, so that
those set on the basis of the ‘steady state’.
(iii) The learning curve has been found to be particularly useful
in determining the likely costs to be incurred in fulfilling
government contracts. This provides a rational basis for price
negotiation and cost control.
7
1
0.9
0.8
0.7
Time per unit
0.6
0.5
0.4
0.3
0.2
0.1
0 20 40 60 80 100
Cumulative repetitions
8
Learning Curve Formula
Y = axb
Y = Cumulative Average Time Taken Per Unit
a = Time Taken for the First Unit
x = Trial Number of Units
b = Index for Learning
11
Question
• Amir ltd. finds that new production is affected
by an 80% learning curve. The company has
just completed 5,000 units at 10,000 hours,
per unit hours required 2.
• The cost of producing 5,000 units were as:
• Direct material 5,000 units @ RS.20 per unit,
Direct labour 10,000hours @ Rs. 8 per unit
variable overheads 10,000 hours @ Rs 2 per unit
12
Question
• The company has just received an order for
another 5,000 units. Management wants to
add a 50% markup to the cost of material,
labour and overheads.
• Required:
• Compute the price to be charged to the order.
13
Answer
• Under 80% learning curve, if the output is
doubled the time required to produced one
unit will reduce to 80%. Therefore for each
unit will require 2 hours X 80% =1.6 hours.
• The total hours for 10,000 units will be
10,000 units X1.6 hour =16,000 hours
therefore for the order of 5,000 units will be
the difference of 16,000- 10,000 =6,000 hours.
14
Answer
• Cost of order:
Material 5000 units X Rs. 20 Rs.100,000
Labour 6000 hours X Rs. 8 Rs. 48,000
Variable overheads 6000 hoursXRS.2Rs.12,000
Total cost Rs.160,000
Markup 50% of total cost Rs. 80,000
15
16
12th unit require 5.58 hours and total 12 units will require 82.44
hours.
using equation=b=ln(.85)/ln(2)=-.234
T12=10(12)-0234=5.58 hours
17
Life Cycle Costing & Target Costing
18
TARGET COSTING
• TARGET COSTING is actually working back
wards to find out the target cost, which a firm
should be able to achieve.
• First stage is to determine the target price.
• Second stage is determine profit margin.
• Final stage the target profit margin is
deducted from target selling price to
determine the target cost.
19
Target costing
• If the estimated actual cost exceeds the target
cost, investigate the ways and means of cost
reduction.
• Target costing is used where the prices are
controlled by the government , in consumer
goods manufacturing where competition is
severe.
• The major advantage of target costing is that it is
deployed during a product’s design and planning
stage. Value engineering techniques are highly
useful in implementing target costing.
20
Question:# 1
a) Costing systems attempt to explain how products consume
resources but do not indicate the joint benefits of having
multiple products.
Requirements:
Explain the statement above and discuss:
i. How the addition of a new product to the product range may
affect the ‘cost’ of existing products’.
ii. The consequences, in terms of total profitability, of decisions
to increase / decrease the product range.
21
The total cost of some types of activity/resource depends on the number of
batches put through production.
Such activities include, for example, machine set up. If long production runs
are used, set-up costs will be less than if many short production runs are used.
The same applies to the number of different products manufactured. If only
one product is made set-up costs will not be incurred.
Two products create the cost and three increase it, and so on. Thus, some
resource costs will increase if a company manufactures multiple products.
On the other hand, there are a number of benefits from manufacturing a
number of products that need to be considered. They are:
An additional product may help smooth out production peaks and trough
caused by economic or seasonal fluctuations.
Distribution and marketing channels can be used more fully bringing down
the cost per unit.
If a company making a range of products creates a brand name, it can be
used to launch a new product more cheaply than if the new product more
cheaply than if the new product was made by a single product company set up
for the purpose.
22
ii. The effect on total profit if the product range is increased /
decreased.
All costs (production, distribution, research, marketing and so on) must
be considered when making decisions on whether or not to expand the
product range.
Some companies focus on production costs and so, as a consequence,
could over look cost education benefits gained on the marketing side if
another product is added.
A full product range is almost always an advantage on the marketing
side. For example, a brand name for a range of products creates joint
benefits for that range of products.
The effect of brand names is difficult to measure and could be ignored
if only 'hard' costs and benefits are included when making a decision.
Sometimes a full product range is necessary to attract customers - such
as a company supplying plumbing pipes and joints, and so on.
If one product is withdrawn, because the costing system shows it to be
unprofitable, customers may switch to another supplier and the
organization's overall profit may go down as a result. 23
b. The modern business environment tends to be an unstable one
and is rapidly changing in terms of customer requirements,
economic factors, technology, and so on. Telmat is in a
particularly unstable business because technology is changing
rapidly as digital telephones take over and text messaging
develops. Both target costing and life cycle costing are
systems which should help the company cope with this. These
systems should help Telmat to compete in terms of cost and
product development in the competitive
telecommunications market.
Their specific advantages are as follows:
i. Target Costing
Target costing may replace, and is often compared with,
traditional standard costing / variance analysis which has long
been in place in the West. Telmat may wish to replace standard
costing/variance analysis with target costing for cost control and
reduction for the following reasons: 24
• It puts pressure on cost- it can be used as a cost reduction
technique unlike standard costing and can incorporate a
learning effect. This is likely to be important in the
manufacture of phones.
• Traditional standards may be too rigid for cost control and
reduction purposes for a company such as Telmat as they
usually need to be set for a year at a time. Target costing is
more flexible and targets can change/reduce from month to
month.
• It considers the market and the price customers are prepared
to pay'- so it forces an organisation to be outward rather than
inward looking. Telmat needs to consider the final customer
as well as the system supplier. (Standard costing tends to
focus on internal costs.)
25
• It should motivate staff if used correctly and help break down
any artificial functional barriers as it involves staff at all
levels and in most functions and forces them to communicate
• It leads towards the use of other techniques, such as value
analysis and value engineering, which should simplify
production methods and reduce cost. This is particularly
important in an industry with short product life cycles.
26
• Many Telmat's costs are likely to be 'locked in' during the
design stage, say 80-90 per cent, so it is important to control
costs initially in order to maximize the profit over the
product's life.
• It focuses on the time as well as money. Time to market is
often a key factor in generating profit. It is often more
important to measure time than money/cost. It may be vital
for Telmat to bring new products to market quickly and on
time in order to achieve a profit.
• Monitoring of costs and benefits over the life cycle helps to
stop a project early if events have changed or not turned out
as planned.
• It presents a different perspective that could be advantageous
to Telmat as it is not tied to periodic reporting.
Because of the above it would be advantageous for the company
to adopt both of these techniques.
27
28
TARGET COSTING
• Target costing originated in Japan in the 1960.
• Target costing is an activity which aimed at
reducing the life-cycle costs of a new products,
while ensuring quality, reliability, and other
customer requirements, by examining all possible
ideas for cost reduction at the product planning,
research and development, and the prototyping
phases of production.
• It is a part of a comprehensive strategic profit
management system.
29
Throughput Accounting
30
Question
MN Ltd manufactures automated industrial trolleys, known as
TRLs. Each TRL sells for £2,000 and the material cost per unit is
£600.
Labour and variable overhead are £5,500 and £8,000 per week
respectively. Fixed production costs are £450,000 per annum and
marketing and administrative costs are £265,000 per annum.
The trolleys are made on three different machines. Machine
X makes the four frame panels required for each TRL.
Its maximum output is 180 frame panels per week. Machine X is
old and unreliable and it breaks down from time to time – it is
estimated that , on average, between 15 and 20 hours of
31
production are lost per month.
Machine Y can manufacture parts for 52 TRLs per week and
machine Z, which is old but reasonably, can process and assemble
30 TRLs per week.
The company has recently introduced a just-in-time (JIT)
system and it is company policy to hold little work-in-progress and
no finished goods stock from week to week.
The company operates a 40-hour week, 48 weeks a year (12
months x 4 weeks) but cannot meet demand. The demand for the
next year is predicted to be as follows – this is expected to be
typical of the demand for the next 4 years:
32
Units per week Units per week
January 30 July 48
February 30 August 45
March 33 September 42
April 36 October 40
May 39 November 33
June 44 December 30
36
(b) The reliability of machine X is {(160 – 17.5) x 100} / 160 = 89%
The existing output capacities per week are:
37
Production
Month Present Machine G and
Machine F Machine G
Machinery overhaul
Jan 120 120 120 120
Feb 120 120 120 120
Mar 120 132 132 132
Apr 120 144 144 144
May 120 144 156 156
Jun 120 144 160 176
Jul 120 144 160 180
Aug 120 144 160 180
Sep 120 144 160 168
Oct 120 144 160 160
Nov 120 132 132 132
Dec 120 12 120 120
1,440 1,632 1,724 1,788
Additional units each year 192 284 348
38
Value added per unit £
Machine G and
Machine F Machine G
overhaul
£000 £000 £000
Additional value added 268.8 397.6 487.2
Less: Additional costs 120.0 216.0 216.0
Net gain each year 148.8 181.6 271.2
39
Machine G
Cab Discount
Machine F Machine G and
flows factor
overhaul
Year 0 £ £ £
Machine 1 (330,000) (550,000) (550,000)
Cost
Overhaul 1 (100,000)
Years 1-4
£148,800 3.170 471,696
£181,600 3.170 575,672
£271,200 3.170 859,704
NPV 141,696 25,672 209,704
40
The combination of machine G and overhauling machine X has
the great NPV and should be undertaken. The lowest cost
option to overhaul machine X is not worth while on its own, as
machine X is not presently limiting output.
If the overhaul is not possible for any reason then machine F
should be purchased.
41
Extra units 276.5
Extra added value £387,100
Net gain each year £171,100
NPV 171,100 x 3.170 - £650,000 = (£107,600)
42