Professional Documents
Culture Documents
1
Problem
Direct materials: Rs.
Bricks 200,000 @ Rs. 100 per thousand 20,000 note 1
200,000 @ Rs. 120 per thousand 24000
Direct labor:
Skilled 3200 hours @ Rs. 12 per hour 38400 note 3
Unskilled 2000 hours @ Rs. 6 per hour 12000 note 4
Other costs:
Scaffolding hire 3500 note 5
Depreciation of general purpose machinery 2000 note 6
General overheads 5,200 hours @ Re. 1 per hour 5200 note 7
plans 2000 note 8
3
Problem
4. John employs four unskilled workers on contracts guaranteeing them a
40 hour week at £6 per hour. These unskilled laborers are currently idle
and would have sufficient spare time to complete the proposal under
consideration.
5. This is the estimated cost of hiring scaffolding.
6. John estimates that the project will take 20 weeks to complete. This
represents 20 weeks’ straight line depreciation on equipment used. If
the equipment is not used on this job it will stand idle for the 20 week
period.
In either case its value at the end of the 20 week period will be identical.
7. This represents the rental cost of John’s storage yard. If he does not
undertake the above job he can rent his yard out to a competitor who
will pay him rent of £500 per week for the 20 week period.
8. This is the cost of the plans that John has already had drawn for the
project.
9. John attempts to earn a mark up of 20% on cost on all work undertaken.
John is surprised at the suggested price and considers it rather high. He
knows that there will be a lot of competition for the work.
4
Problem
Required:
• Using relevant costing principles, calculate the
lowest price that John could quote for the
customer’s building work. Explain your
treatment of each item in the accountant’s
estimate.
5
6
Problem
• Krol plc uses a standard costing system to control its costs. In the
most recent month its cost accountant has reported a large adverse
direct material usage variance. An initial investigation has shown
that the variance is caused by a faulty machine.
7
Problem
• Two maintenance engineers would be required to carry out the
emergency maintenance work. Maintenance engineers are paid £25,000
per annum and each engineer works for 250 days each year.
• There is currently surplus capacity in the maintenance department. The
emergency maintenance would use parts costing £10,000. These parts
would have to be replaced again during the scheduled annual
maintenance.
• Emergency maintenance would involve stopping production for a day
resulting in lost production with an estimated sales value of £160,000,
direct material cost of £45,000 and direct labor cost of £90,000.
• Direct labor would continue to be paid during the one-day stoppage. In
this time the otherwise idle labor would be used to repaint the factory,
saving £7,000 in outside painting contractor costs.
• Krol carries no finished goods stocks and is currently unable to satisfy
demand for its product.
8
Problem
1. Using relevant cost principles, calculate
whether the emergency maintenance should
be performed.
2. Suggest three potential causes of direct
material usage variances.
9
10
Problem
• Karachi Electrics (K.E) Ltd., a local company
produces electrical household equipment
including 50,000 electric irons per annum. For
each iron, they use a specialized component
which they import at a cost of Rs.115.
11
Problem
The Chief Accountant after consulting various departmental managers made
calculation based on the following information:
– Direct materials to produce 50,000 components would cost Rs.3,000,000
– Direct labor at the standard hourly rate of Rs.50 would cost Rs.2,000,000
– The company’s overheads excluding depreciation and supervision costs
would increase from Rs.2,100,000 to Rs.2,400,000.
– With the level of overheads Rs.2,400,000 the overhead recovery rate
would be Rs.6 per direct labor hour.
– For the components to be produced locally, the K. E Ltd., would have to
buy a new machine worth Rs.1,000,000. The expected useful life of this
machine is 5 years.
– Production of these components would also utilize 10% capacity of an
existing machine which was bought in the previous year at a cost of
Rs.40,000,000. The expected useful life of this machine is 8 years.
Currently, only 70% of the machine.s capacity is being utilized.
– The supervision of production will fall on Mr. Ubaydullah who earns a
salary of Rs.500,000 per annum. Management thinks that Mr. Ubaydullah
is only half utilized.
– The company uses straight line method of depreciation, which reduces
salvage value of the machines to zero.
12
Problem
• After making all the calculations be deemed
necessary, the Chief Accountant concluded
that the standard cost of manufacturing the
components was Rs.125 per unit.
• On the basis of this information the
management decided to continue importing
the components as this would save the
company Rs.500,000 per annum.
13
Problem
Required:
• Prepare a comprehensive statement, showing how the
Chief Accountant worked out the standard cost of
Rs.125 per component.
• State whether the management made use of relevant
costs in arriving at their decision. If you think that
management did not use relevant costs, then prepare a
statement and apply the criteria of relevant costs.
• Assuming that the costs of producing or importing the
components were equal, give six major advantages of
manufacturing the components.
14
Solution
(a). The standard cost of manufacturing 50,000 components:
Per unit
Rs.
Material 60
Direct labor 40
Variable overhead 6
Depreciation of new machine 4
Depreciation of existing machine -
Supervision -
Total 110
(ii). Cost per unit reduces, due fixed cost remaining the same.
17
Problem
The Businet newspaper group is to commence
publication of a weekly supplement called
Bizcom. They have estimated that printing
cost will be as follows:
No. of 5,000 6,000 7,000 8,000 9,000
copies
Cost (Rs.) 6,250 7,200 8,310 9,200 9,500
18
Problem
Additional cost will be Re. 0.50 as delivery cost for each copy
ordered and a 15% commission payable on each copy sold. Any
unsold copies are considered worthless.
The management has as yet not decided on a selling price for the
supplement and has evaluated that the demand will be as follows
at the following prices:
Prices Demand
(Rs.) (copies)
2.75 9,000
3.00 8,000
3.25 7,000
3.50 6,000
3.75 5,000
19
Problem
Required:
1. Calculate the number of copies that the
management should order and the selling price
that it should set.
2. Assuming that 9,000 copies had been ordered
and the selling price set at Rs. 3.25, advise the
management whether to accept an upcountry
order at Rs. 1.25 a copy for 2,000 copies
(demand is expected to fall by 10% as a result of
accepting the offer). Show your working notes.
20
Solution
(a)- col.1 col.2 col.3 col.4 col.5 col.6 col.3 -
(col.1*co (15%*col.3) (0.50*col.2) sum(col.4,5,6)
l.2)
Decision: The management should order 6,000 copies at a selling price of 3.50 Rs.
per copy, in order to maximize the profit
21
Solution
(b) The relevant costs and revenues to be considered for this analysis are those
- that may be affected, if the company accepts the upcoming offer. The
additional revenue and the costs in case of acceptance have been worked out
as below:
Additional 2,500
revenue
(2,000*1.25)
Loss of revenue 1,934
- (net of
commission)
(10%*22750*0.
85)
Gain 566
The offer should be accepted, because out of 9,000 copies, 7,000 copies will
be sold at Rs. 3.25, and the additional revenue of 2,000 copies will be Rs.
2,500 (at Rs. 1.25 each), which is more than the revenue loss (1,934) that will
be incurred by the company by accepting the offer.
22
Problem
• Allied PLC wishes to decide whether or not to
supply a contract to a large retail store for a
one year contract period. The management
accountant prepares an initial summary as
follows:
23
Problem
Material Rs.
X: in stock at original cost 8,000
Y: on order (contract price) 2,000
Labor
Skilled men 25,000
Foreman 9,000
Overhead
Production 40,000
Administration 6,000
Distribution 2,000
Total Cost 92,000
25
Problem
The additional information is as follows:
26
Problem
3. If the skilled men are not used on the contract, they will
be made redundant at a cost of Rs. 3,000 in one
year’s time, so that redundancy pay would then be Rs.
1,600
4. The foreman will be retained at his present salary of Rs.
9,000 whether or not the contract is accepted. If not
required for the contract, however, he will be used to fill a
clerical post for which a salary of Rs. 5,000 is payable.
5. Production Overhead includes depreciation of machinery
of Rs. 10,000. This machinery is old and will be sold for Rs.
5,000 if not used on the contract. If it is used on the
contract, it is estimated that it will be sold in one year’s
time for Rs. 3,000. All other production overheads is fixed
and will remain unchanged by the contract.
27
Problem
6. Administrative overhead includes Rs. 2,000 appointment
of company rates for an office to be used to coordinate
work on the contract. If not used for the contract this
office space will be sub-let for the year for Rs. 4,000. All
other administrative overhead is fixed and will remain
unchanged by the contract.
7. Distribution overhead represents the amount which will
be paid to an outside haulage firm should the contract be
accepted.
Required:
• Advise Management of Allied PLC regarding acceptance of
contract.
28
Solution
ALLIED PLC
ACCEPTANCE OF THE CONTRACT
Rs.
Benefits:
Contract price 70,000
Reduction in redundancy pay 1,600
Total benefits 71,600
Costs:
Loss in sale value of machinery (5,000-3,000) 2,000
Sublet income forgone 4,000
Material X (5,000-1,000) 4,000
Material Y (2,000-400) 1,600
Skilled men's wages 25,000
Clerical salary 5,000
Distribution expense 2,000
Total cost 43,600
Net benefits 28,000
29
Solution
Using Cash Flow Approach:
Accept contract Reject contract
Rs.
Cash inflows:
of machinery 3,000 5,000
Sublet income - 4,000
Contract price 70,000 -
Total cash inflows 73,000 9,000
Cash outflows:
Material X (purchase of K) 5,000 -
Material X (adoption) - 1,000
Material Y 2,000 -
Material Y (penalty) - 400
Skilled men's wages 25,000 -
Skilled men's redundancy pay 1,400 3,000
Foreman (clerical vacancy) 5,000 -
Distribution costs 2,000 -
Total cash outflows 40,400 4,400
Net cash flow 32,600 4,600