You are on page 1of 17

PROJECT-2

SCHEDULING FOR CONSTRUCTION


PROJECT DETAILS:
PROJECT: NEW INPATIENT BLOCK (CONVERSION OF THE EXISTING SNH BUILDING
. INTO OPERATION THEATERS AND CLINICAL FACILITY IN TOWN CAMPUS)
TYPOLOGY: HOSPITAL BUILDING
CLIENT: CHRISTIAN MEDICAL COLLEGE AND HOSPITAL AT VELLORE
LOCATION: VELLORE, TAMILNADU
TOTAL BUILTUP AREA: 14,153.7 SQ M
NO. OF FLOORS: BASEMENT+GROUND+9 TYPICAL FLOORS
FIRST FLOOR LAYOUT
SECOND FLOOR LAYOUT
WORK BREAK DOWN STRUCTURE
WORK BREAK DOWN STRUCTURE
MOBILIZATION
MOBILIZATION REFERS TO THE ACT OF PHYSICALLY MOVING ON SITE AND BRINGING IN TEMPORARY FACILITIES,
E.G.; STORAGE CONTAINERS, OFFICE TRAILERS AND TEMPORARY POWER SUPPLIES, ERECTING TEMPORARY
FENCING, AND OTHER SUCH PRE-CONSTRUCTION NECESSITIES AS MAY BE APPROPRIATE FOR THE PROJECT. IT ALSO
REFERS TO MOVING THE EQUIPMENT NECESSARY FOR THE CONSTRUCTION ONTO THE SITE.
DEMOLITION WORK IN OT BLOCK:

DEMOLITION WORK IN 9TH FLOOR:

CHIP EXISTING FLOORS IN 9TH FLOOR AND DEMOLISH CONCRETE IN 9TH FLOOR AND REMOVE
REMOVE DEBRIS: DEBRIS FROM SITE (STAIRCASE AREA)
TOTAL AREA= 590 SQ.M TOTAL AREA= 10 CU.M
UNIT OF QUANTITY= 100 CU.M UNIT OF QUANTITY= 100 CU.M
LABOUR INVOLVED = MAZDOOR (235 RS/DAY) LABOUR INVOLVED = SKILLED MAZDOOR (245 RS/DAY)
NO.OF LABOUR = 10 NO.OF LABOUR = 20

NO OF DAYS=3 NO OF DAYS=2
NO OF LABOUR PER DAY = 19.5 NO OF LABOUR PER DAY = 1
LABOUR COST = 4,582 RS/ DAY LABOUR COST = 245 RS/ DAY
TOTAL LABOUR COST = 13,747.5 RS TOTAL LABOUR COST = 490 RS
DEMOLISH INTERNAL BLOCK WORK IN 9TH FLOOR AND REMOVE EXISTING WINDOWS IN 9TH FLOOR
REMOVE DEBRIS FROM SITE NO OF WINDOWS = 36
LABOURS= MASON AND MAZDOOR
UNIT OF QUANTITY= 100 CU.M NO OF DAYS= 6
LABOUR INVOLVED = MAZDOOR (235 RS/DAY) TOTAL LABOUR COST= 4,170 RS
NO.OF LABOUR = 10

NO OF DAYS=4 REMOVE WOODEN CUPBOARDS IN 9TH FLOOR


NO OF LABOUR PER DAY = 8
LABOUR COST = 1880 RS/ DAY LABOUR INVOLVED = MASON -1 ( 460 RS/DAY)
TOTAL LABOUR COST = 7,520 RS MAZDOOR - 1 ( 235 RS/DAY)
NO OF DAYS=1
REMOVE EXISTING DOORS IN 9TH FLOOR NO OF LABOUR PER DAY = 1
LABOUR COST = 695 RS/ DAY
TOTAL NUMBER = 5 TOTAL LABOUR COST = 695 RS
LABOUR INVOLVED = MASON -1 ( 460 RS/DAY)
MAZDOOR - 1 ( 235 RS/DAY) TOTAL LABOUR COST FOR DEMOLITION IN 9TH FLOOR
NO OF DAYS=1 =27,317.5 RS
NO OF LABOUR PER DAY = 1
LABOUR COST = 695 RS/ DAY TOTAL LABOUR COST FOR DEMOLITION OF
TOTAL LABOUR COST = 695 RS GROUND +9 FLOOR = 2,73,175
BRICK WORK / PARTITION WALL IN EXISTING BUILDING FOR 4.5” THK.WALL,
TOTAL AREA = 708.78 SQ.M (7630 SQ.FT) NO OF BRICK WITHOUT WASTAGE = 47.5 NOS/ SQ.M
LABOUR INVOLVED = MASON- 1 (460 RS) NO OF BRICK WITH WASTAGE = 52.25 NOS/ SQ.M
LABOUR -0.5 (280 RS)
HELPER – 0.5 (235 RS) TOTAL NO OF BRICK REQ. FOR 708.78 SQ.M
10 SQ.M CAN BE CONSTRUCTED BY A MASON PER DAY = 33,667 NOS WITHOUT WASTAGE
NO OF DAYS ALLOCATED = 7 TOTAL NO. OF BRICK WITH WASTAGE = 37,033.75 NOS.
NO.OF LABOUR = 10 MASON, 5 LABOUR, 5 HELPER COST PER BRICK = 5.50 RS
LABOUR COST = 7,175 RS/ DAY TOTAL COST FOR BRICK = 2,03,658.6 RS.
TOTAL LABOUR COST = 50,225 RS
Brick calculation MORTAR = CEMENT + SAND = 1:6
SIZE= 19X 9X 9 CM QUANTITY OF MORTAR TO CONSTRUCT HALF BRICK WALL
MORTAR THICKNESS= 10MM =3.20 CU.M FOR 100 SQ.M
FOR 9” WALL TOTAL MORTAR REQ. = 7.0878 X 3.20 = 22.6809 CU.M
NO. OF BRICK = VOL. OF BRICKWORK/ VOL. OF 1 BRICK FOR 1 CU.M MORTAR:
WITH MORTOR CEMENT= 5.472 BAG (1915.2 RS)
VOLUME OF 1 BRICK WITH MORTOR = 0.20 X 0.10 X 0.10 = SAND = 1.14 CU.M (1539 RS)
0.002 CU.M COST OF MORTAR FOR 1 CU.M = 3454.2 RS
VOLUME OF BRICKWORK = THK’ OF WALL X AREA OF TOTAL COST FOR MORTAR= 78,344.36 RS
BRICKWORK
VOLUME OF BRICKWORK = 0.19M X 1 SQ.M = 0.19 CU.M TOTAL COST FOR CONSTRUCTING A PARTITION WALL
NO. OF BRICKS = 0.19 / 0.002 = 95 NOS ( WITHOUT = 3,32,227.96 RS/ FLOOR
WASTAGE)
CONSIDER WASTAGE 10%
THEN, NO OF BRICK WITH WASTAGE = 95 + 9.5 = 104.5 NOS
FINISHING WORK IN EXISTING BUILDING INCLUDES,
WATER PROOFING AND FLOORING IN TOILET AREAS
WALL CHASING FOR ELECTRICAL CONDUITS
WALL PASTERING INTERNAL AND EXTERNAL
WALL PUTTY WORK
FALSE CEILING WORK
FLOORING WORK
SKIRTING WORK
WALL PAAINTING INTERNAL AND EXTERNAL.
ROOM 1- WARD 13 BEDS: PLASTERING MATERIAL:
TOTAL FLOOR AREA: 16260X5700MM CEMENT BAG REQ. FOR 100 SQ.M- 8
HEIGHT: 3000MM SAND FOR 100 SQ.M- 1.646 CU.M
COST:
TOTAL NO OF WINDOWS: 8( 1000X1000MM) CEMENT- 8X 2.65= 21 BAGS X 350 RS/BAG= 7350 RS.
TOTAL AREA: 8 SQ.M SAND- 1.646X 2.65= 4.3619 CU.M X1000 RS= 4361 RS.

DOOR: 1 (2000X2100) TOTAL COST FOR LABOUR=19,146 RS


TOTAL AREA: 4.2 SQ.M TOTAL COST FOR MATERIAL= 11,711 RS
TOTAL COST= 30,857 RS
TOTAL AREA FOR PLASTERING: 265.846 SQ.M
LABOURS REQUIRED AND THEIR COST PER DAY:
HEAD MASON-1/2 = 175 RS/D
MASON- 10 = 325 RS/D = 3250 RS
MALE MAZDOOR- 8 = 300 RS/D = 2400 RS
FEMALE MAZDOOR- 4 = 275 RS/D = 1100RS
BHISTI (WATER CARRIER)-1= 300 RS/D
TOTAL COST= 7225 RS/DAY

AREA COVERED PER DAY: 100 SQ.M


THICKNESS OF PLASTERING: 12MM

RESOURCE ALLOCATION
1 st FLOOR PLASTERING WORK: 1 st FLOOR PLASTERING WORK:
TOTAL AREA REQUIRED TO DO PLASTERING= 1189.97 SQ M NO. OF DAYS = 5

LABOURS REQUIRED AND THEIR COST PER DAY: NO. OF LABOURS REQ. PER DAY
HEAD MASON-1/2 = 175 RS/D
MASON- 10 = 325 RS/D = 3250 RS HEAD MASON= 1 1/2
MALE MAZDOOR- 8 = 300 RS/D = 2400 RS MASON= 30
FEMALE MAZDOOR- 4 = 275 RS/D = 1100RS MALE MAZDOOR= 24
BHISTI (WATER CARRIER)-1= 300 RS/D FEMALE MAZDOOR= 12
TOTAL COST= 7225 RS/DAY BHISTI (WATER CARRIER)= 3

AREA COVERED PER DAY: 100 SQ.M


THICKNESS OF PLASTERING: 12MM
MATERIAL:
CEMENT BAG REQ. FOR 100 SQ.M- 8
SAND FOR 100 SQ.M- 1.646 CU.M
COST:
CEMENT- 8X 11.9= 95 BAGS X 350 RS/BAG= 33,250 RS.
SAND- 1.646X 11.9= 19.5874 CU.M X1000 RS= 19587.4 RS.

TOTAL COST FOR LABOUR =85,977 RS + 19146 RS = 1,05,123 RS


TOTAL COST FOR MATERIAL = 52,837 RS + 11711 RS = 64,548 RS
TOTAL COST = 1,38,814 RS + 30857RS = 1,69,671 RS

RESOURCE ALLOCATION
EXTERIOR WALL PLASTERING WORK: NO. OF DAYS = 5
TOTAL AREA REQUIRED TO DO PLASTERING:
NORTH – 1756.5 SQ.M NO. OF LABOURS REQ. PER DAY
SOUTH – 1696.5 SQ.M EAST / WEST
EAST – 750 SQ.M HEAD MASON= 3/4
WEST- 750 SQ.M MASON= 15
MALE MAZDOOR= 12
AREA COVERED PER DAY: 100 SQ.M FEMALE MAZDOOR= 6
THICKNESS OF PLASTERING: 12MM BHISTI (WATER CARRIER)= 1.5
MATERIALS: NORTH
CEMENT BAG REQ. FOR 100 SQ.M- 8 HEAD MASON= 1 3/4
SAND FOR 100 SQ.M- 1.646 CU.M MASON= 35
COST: MALE MAZDOOR= 28
(NORTH) FEMALE MAZDOOR=14
CEMENT- 8 X 17.5 = 140 BAGS X 350 RS/BAG= 49,000 RS. BHISTI (WATER CARRIER)= 3.5
SAND- 1.646X 17.5 = 28.805 CU.M X1000 RS= 28,805 RS. SOUTH
LABOUR COST= 54187 X 2 = 126,907 RS. HEAD MASON= 1 3/4
(SOUTH) MASON= 33
CEMENT- 8 X 16.9 = 135 BAGS X 350 RS/BAG= 47,250 RS. MALE MAZDOOR= 27
SAND- 1.646X 16.9 = 27.817 CU.M X1000 RS= 27817 RS. FEMALE MAZDOOR=13
LABOUR COST= 54187 X 2 = 119,212 RS. BHISTI (WATER CARRIER)= 3.5
(EAST AND WEST)
CEMENT- 8 X 15 = 120 BAGS X 350 RS/BAG= 42,000 RS.
TOTAL COST FOR LABOUR =3,54,494 RS
SAND- 1.646X 15 = 24.69 CU.M X1000 RS= 24690 RS. TOTAL COST FOR MATERIAL = 2,19,562 RS
LABOUR COST= 54187 X 2 = 108,375 RS. TOTAL COST = 5,74,056 RS

RESOURCE ALLOCATION
1 st FLOOR WALL PUTTY WORK:
1 ST FLOOR FLOORING WORK:
TOTAL AREA REQUIRED TO DO PUTTY = 1455.816 SQ M

LABOURS REQUIRED AND THEIR COST PER DAY: TOTAL AREA REQUIRED TO DO FLOORING = 538.8 SQ M
SKIRTING = 51.8 SQ.M
PAINTER =22 RS PER SQ.M
LABOURS REQUIRED AND THEIR COST PER DAY:
AREA COVERED PER DAY: 100 SQ.M
SKILLED LABOUR = RS.700/DAY
MATERIAL: SUPERVISOR=RS.800/DAY
PUTTY COST- 30 RS/KG GENERAL LABAOUR=RS.600/DAY
1 KG COVERS 2 SQ.M ( ½ KG/ SQ.M)
COST: AREA COVERED PER DAY: 20 SQ.M
PUTTY POWDER- .1455.816 X ½ = 2912 KG NO. OF DAYS = 15
COST – 2912 X 30 RS = 87,360 RS AREA COVERED PER DAY = 40 SQ.M
LABOUR COST PER DAY = 4,200 RS
TOTAL COST FOR LABOUR = 32,032 RS TOTAL LABOUR COST = 61,950 RS
TOTAL COST FOR MATERIAL = 87,360 RS
TOTAL COST = 32,032 RS + 87,360RS = 119,392 RS MATERIAL
APPROX. 1 SQ.FT TILE COST 60/-
NO. OF DAYS = 5 590 SQ.M COST- 3,81,000 RS

NO. OF LABOURS REQ. = 3 TOTAL COST= 4,42,950 RS. APPROX.

RESOURCE ALLOCATION
INTERNAL WALL PAINTING WORK: EXTERNAL WALL PAINTING WORK:
TOTAL AREA REQUIRED TO PAINTING :
TOTAL AREA REQUIRED TO PAINTING = 1455.816 SQ M NORTH – 1756.5 SQ.M
SOUTH – 1696.5 SQ.M
LABOURS REQUIRED AND THEIR COST PER DAY: EAST – 750 SQ.M
WEST- 750 SQ.M
PAINTER = 325 RS/ D
HELPER = 240 RS/D AREA COVERED PER DAY: 100 SQ.M
AREA COVERED PER DAY: 100 SQ.M LABOURS REQUIRED AND THEIR COST PER DAY:
PAINTER ½ NOS. – 100 SQ.M
HELPER 2- NOS – 100 SQ.M PAINTER 3 ½ NOS. EACH DAY
HELPER 14 NOS . EACH DAY
LABOUR TOTAL COST = 9,637.5 RS
MATERIAL NO OF DAYS= 7

10 LITRES CAN BE USED FOR 100 SQ.M LABOUR TOTAL COST = 31,482.5 RS
145.5 LITRES REQ. TO PAINT 1455.816 SQ.M

NO OF DAYS= 5

RESOURCE ALLOCATION
THANK YOU

You might also like