Professional Documents
Culture Documents
Session 2 - Project Scope and Schedule Planning
Session 2 - Project Scope and Schedule Planning
ADM 6260-E00
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
2
Monitoring &
Initiating Planning Executing Closing
Controlling
Integration
Scope Scope
Schedule Schedule
Cost Cost
Quality
Resources
Communications
Risk
Procurement
Stakeholders
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
3
Project
Planning
Process
Group
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
4
Integration: Project Management Plan
• Scope, Requirements, Schedule, Cost, Quality,
resource, communications, risk, procurement, and
stakeholder management plans.
• Scope, schedule, and cost baselines.
– PM reports project performance based on them.
– Scope baseline: project scope statement + WBS
– Schedule and Cost baselines: The agreed-upon
schedule and cost budget.
• Change management plan.
• …
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
5
Planning: Project Scope
Management
Monitoring &
Initiating Planning Executing Closing
Controlling
Integration
Scope Scope
Schedule Schedule
Cost Cost
Quality
Resources
Communications
Risk
Procurement
Stakeholders
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
7
Scope
• Product Scope: features/functions that characterize a
product, service, result, or deliverables.
– Project: Build a new train terminal
– Product Scope: A new train terminal with such and
such specifications.
• Project Scope: The work performed to deliver the
product, service, result, or deliverables.
– Project Scope: includes the planning, coordination,
and management activities on top of product
scope.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
8
Scope Management Planning
Create WBS
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
9
Plan Scope Management
Scope management plan: documents how project and product
scope will be defined, validated, and controlled
– Process for preparing a project scope statement
– Process for creating WBS
– Establishing how the scope baseline will be approved and maintained.
– Specifying how formal acceptance of project deliverables will be obtained.
Requirements management plan: describes how project and
product requirements will be analyzed, documented, & managed.
– How requirements activities will be planned, tracked, and reported.
– Configuration/change management activities
Plan Scope
Collect
– Metrics that will be used and the rationale for using them Requirements
–… Define Scope
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
10
Collect Requirements and Define Scope
Define Scope
Create WBS
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
11
Create Work Breakdown Structure
• Subdividing project deliverables and project work into smaller,
more manageable components. The output is the Scope
Baseline.
– Every single thing that anyone on the project team—including PM- will
do is written down in the WBS.
– The WBS doesn’t show the order of work packages or any
dependencies between them. Its only goal is to show the work
involved in creating the product.
– Breakdown the work by deliverables or by project phase.
– Take deliverables and coming up with work packages that will create
them (Decomposition) Plan Scope
Management
Collect
Requirements
Define Scope
Create WBS
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
12
PMBOK, 6th Edition (2017)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
13
Work Breakdown Structure
Building a
Complex
Project
Engineering Procurement Construction Safety …
Management
Communications …
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
14
Scope Baseline
+
• WBS
Plan Scope
Management
Collect
Requirements
Define Scope
Create WBS
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
15
Responsibility Matrix (RACI)
• RACI Matrix is a table
• Responsible-Accountable-Consulted-Informed
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
16
Sample RACI
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
17
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
18
Planning: Project
Schedule Management
Monitoring &
Initiating Planning Executing Closing
Controlling
Integration
Scope Scope
Schedule Schedule
Cost Cost
Quality
Resources
Communications
Risk
Procurement
Stakeholders
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
20
PMBOK, 6th Edition (2017)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
21
Schedule Management Process
Define Activities
Outputs:
1. Schedule Management Plan
Sequence Activities 2. Project Schedule
3. Milestone List
4. Schedule Baseline
Develop Schedule
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
22
Plan Schedule Management
Plan Schedule
Management
Define Activities
Sequence Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
23
Define Activities
Estimate Activity
Resources
dates, checkpoints, etc.) Estimate Activity
Durations
Develop Schedule
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
24
Define Activities- Example
• Project: Wedding
• Project manager- the wedding planner: Rose
• Part of the WBS: Wedding
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
27
Sequence Activities
No
• Network Diagrams Loops
Allowed
– Activity-on-Node (AON)
Activity Activity
A B
Define Activities
A B Sequence Activities
0 1 2 Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
28
AON vs. AOA
Predecessors
– AON Activity
B Successors
Activity
A
Activity
C
– AOA
B 2
A
0 1
C 3
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
29
Drawing a Network Diagram
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
30
Sequence Activities- Example
Finish
Start Design Print
invitations invitations
Pick
menus
printer
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
31
Predecessors (1)
Give toasts
• Start to Start (SS):
Serve cake
Play “here comes
the bride”
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
32
Predecessors (2)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
33
Estimate Activity Resources and Duration
• Resources:
– Human resources
– Equipment and material
–… Plan Schedule
Management
Define Activities
Sequence Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
• Expert Judgement
• One-Point Top-Down Estimating (Analogous)
• Parametric Estimating
• Three-Point Estimating
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
35
Three-Point Estimation
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
37
Exercise
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
38
Answer
• Optimistic Duration = 30 d
• Pessimistic Duration = 90 d
• Most Likely Duration = 45 d
• Expected Duration = 50 d
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
39
Develop Schedule
Define Activities
Sequence Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
40
Critical Path Method
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
41
Example
C, 2
A, 4
Start B, 7 Finish
D, 3 E, 5
• Start-A-C-Finish: 4+2=6
• Start-A-B-Finish:4+7=11
• Start-D-E-Finish:3+5=8
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
42
Exercise
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
43
Answer
Start-D-E-F-G-End
17
3
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
44
Critical Path Method (cont’d)
Activity A
The latest time an
Late Start Late Finish
activity can start
(LS) (LF)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
45
Critical Path Method (cont’d)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
46
Example
3 8
3 6 6 14
B D
14
3
0 3
Start A 4
6 14 18
E Finish
3 9
C
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
47
Critical Path Method (cont’d)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
48
Example
3 8
3 6 6 14
B D
3 6 6 14
3
0 3
Start A 4
0 3 14 18
6
E Finish
3 9 14 18
C
8 14
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
49
Critical Path Method- Float
• Float (Slack)
– Activity Float: Amount of time an activity can be
delayed without delaying the project end date or a
milestone.
– Project Float: Amount of time a project can be
delayed without delaying the end date specified
by customer.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
50
Critical Path Method (cont’d)
• Floats
– Activities on critical path have zero float
– Float = Late Start (LS) – Early Start (ES)
– Float = Late Finish (LF) – Early Finish (EF)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
51
Example
3 8
3 B 6 6 D 14
3 0 6 6 0 14
3
0 A 3
Start 4
0 0 3
6 14 E 18
Finish
3 C 9 14 0 18
8 5 14
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
52
Exercise
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
53
Answer
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
54
Exercise
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
55
Answer
Critical Path: 17
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
57
Milestone Chart
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
58
Gantt Chart
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
59
ACTIVITY DEFINITION AND SEQUENCING
WORK BREAKDOWN STRUCTURE
OBJECTIVES
PROJECT HOW
CHARTER
WHAT
ESTIMATION
RESPONSIBILITIES ASSIGNMENT
PARTICIPANTS
WP
WHO
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
60
Develop Schedule (cont’d)
Define Activities
Sequence Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
61
Schedule Compression
• Why?
– A completion date required by customer that
cannot be met, Bring the delayed project back in
line, Adjust the project for changes.
• Objective?
– To compress the schedule without changing the
project scope.
• How?
– Fast tracking
– Crashing
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
62
Fast Tracking
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
63
Example
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
64
Example
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
65
Crashing
• Adding or adjusting resources in order to compress
the schedule while maintaining the original project
scope (Trade time for money).
• Downside?
– Increased costs, increased risk.
• Examples: Hire contract resources to supplement the
internal resources on the critical path activities, Buy
a software application.
𝐶𝑟𝑎𝑠ℎ 𝐶𝑜𝑠𝑡 − 𝑁𝑜𝑟𝑚𝑎𝑙 𝐶𝑜𝑠𝑡
𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑆𝑙𝑜𝑝𝑒 $ 𝑝𝑒𝑟 𝑑𝑎𝑦 =
𝐶𝑟𝑎𝑠ℎ 𝑇𝑖𝑚𝑒 − 𝑁𝑜𝑟𝑚𝑎𝑙 𝑇𝑖𝑚𝑒
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
66
Crashing Example
B,2 E,3
A,3 C,2
D,4
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
67
Crashing Example (cont’d)
Duration Cost Activity
Activity Prec.
(Norm/Crash) (Norm/Crash) Slope
A - 3,2 40 , 80 -40
B A 2,1 20 , 80 -60
C A 2,2 20 , 20 -
D* A 4,1 30 , 120 -30
E** B 3,1 10 , 80 -70 (2 d)
*Partial crashing allowed: it can be crashed one day at a time.
** Partial crashing not allowed: it cannot be broken to one-day
segments.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
68
Crashing Example (Cont’d)
Reduce the duration by one day:
Critical Time= 8 days
B,2 E,3
Total Cost=$120
A,2 C,2
D,4
A,3 A,2
Project Time= 7 days
Total Cost=$160
• Least expensive way, critical path: Crash A
• Is there a change in critical path? No
• Project becomes one day shorter!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
69
Crashing Example (cont’d)
Duration Cost Activity
Activity Prec.
(Norm/Crash) (Norm/Crash) Slope
A - 3,2 40 , 80 -40
B A 2,1 20 , 80 -60
C A 2,2 20 , 20 -
D* A 4,1 30 , 120 -30
E** B 3,1 10 , 80 -70 (2 d)
*Partial crashing allowed: it can be crashed one day at a time.
** Partial crashing not allowed: it cannot be broken to one-day
segments.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
70
Crashing Example (Cont’d)
Reduce the duration by two days:
Critical Time= 8 days
B,1 E,3
Total Cost=$120
A,2 C,2
D,4
A,3 A,2 + B,2 B,1
Project Time= 6 days
Total Cost=$220
• Least expensive way, critical path: Crash A + B
• Is there a change in critical path? Yes
• Project becomes two days shorter!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
71
Crashing Example (Cont’d)
Reduce the duration by three days:
Critical Time= 8 days
B,2 E,1
Total Cost=$120
A,2 C,2
D,4
E,3 E,1 + A,3 A,2 Not
enough!
Project Time= 6 days
Total Cost=$230
• Least expensive way, critical path: Crash E + A
• Is there a change in critical path? Yes
• Project becomes two days shorter!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
72
Crashing Example (cont’d)
Duration Cost Activity
Activity Prec.
(Norm/Crash) (Norm/Crash) Slope
A - 3,2 40 , 80 -40
B A 2,1 20 , 80 -60
C A 2,2 20 , 20 -
D* A 4,1 30 , 120 -30
E** B 3,1 10 , 80 -70 (2 d)
*Partial crashing allowed: it can be crashed one day at a time.
** Partial crashing not allowed: it cannot be broken to one-day
segments.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
73
Crashing Example (Cont’d)
Reduce the duration by three days:
Critical Time= 8 days
B,2 E,1
Total Cost=$120
A,2 C,2
D,3
E,3 E,1 + A,3 A,2+ D,4 D,3
Project Time= 5 days
Total Cost=$260
• Least expensive way, critical path: Crash E + A + D
• Is there a change in critical path? Yes
• Project becomes three days shorter!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
74
Crashing Flowchart
Find The Critical Note: Expedite Project Duration
Path (One time unit at a time)
Expedite Cheapest
Check if the Critical Path
Task(s)
Changed!
(on the critical path)
No
Reached the Goal or
Expediting-Cost>Benefit
Yes
End
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
75
Fast Tracking, Crashing, or both?
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
76