You are on page 1of 76

Project Management I

ADM 6260-E00

Sara Hajmohammad, PhD, PMP


Winter 2020
Session 2
Project Planning
Integration, Scope, and Schedule

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
2
Monitoring &
Initiating Planning Executing Closing
Controlling

Integration

Scope Scope

Schedule Schedule

Cost Cost

Quality

Resources

Communications

Risk

Procurement

Stakeholders

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
3
Project
Planning
Process
Group

PMBOK, 6th Edition (2017)

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
4
Integration: Project Management Plan
• Scope, Requirements, Schedule, Cost, Quality,
resource, communications, risk, procurement, and
stakeholder management plans.
• Scope, schedule, and cost baselines.
– PM reports project performance based on them.
– Scope baseline: project scope statement + WBS
– Schedule and Cost baselines: The agreed-upon
schedule and cost budget.
• Change management plan.
• …
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
5
Planning: Project Scope
Management
Monitoring &
Initiating Planning Executing Closing
Controlling

Integration

Scope Scope

Schedule Schedule

Cost Cost

Quality

Resources

Communications

Risk

Procurement

Stakeholders

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
7
Scope
• Product Scope: features/functions that characterize a
product, service, result, or deliverables.
– Project: Build a new train terminal
– Product Scope: A new train terminal with such and
such specifications.
• Project Scope: The work performed to deliver the
product, service, result, or deliverables.
– Project Scope: includes the planning, coordination,
and management activities on top of product
scope.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
8
Scope Management Planning

Plan Scope Management

Collect Requirements Outputs:


1. Scope Management Plan
2. Requirements Management Plan
3. Project Scope Statement
4. WBS
5. Scope Baseline
Define Scope

Create WBS

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
9
Plan Scope Management
Scope management plan: documents how project and product
scope will be defined, validated, and controlled
– Process for preparing a project scope statement
– Process for creating WBS
– Establishing how the scope baseline will be approved and maintained.
– Specifying how formal acceptance of project deliverables will be obtained.
Requirements management plan: describes how project and
product requirements will be analyzed, documented, & managed.
– How requirements activities will be planned, tracked, and reported.
– Configuration/change management activities
Plan Scope

– Requirements prioritization process Management

Collect
– Metrics that will be used and the rationale for using them Requirements

–… Define Scope

PMBOK, 6th Edition (2017)


Create WBS

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
10
Collect Requirements and Define Scope

The output is Project Scope Statement that Includes:


• Product Scope
• Project Scope
• Deliverables
• Acceptance Criteria
• Exclusions
PMBOK, 6th Edition (2017)
Plan Scope
Management

Developed mainly based on Project Charter


Collect
Requirements

Define Scope

Create WBS

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
11
Create Work Breakdown Structure
• Subdividing project deliverables and project work into smaller,
more manageable components. The output is the Scope
Baseline.
– Every single thing that anyone on the project team—including PM- will
do is written down in the WBS.
– The WBS doesn’t show the order of work packages or any
dependencies between them. Its only goal is to show the work
involved in creating the product.
– Breakdown the work by deliverables or by project phase.
– Take deliverables and coming up with work packages that will create
them (Decomposition) Plan Scope
Management

Collect
Requirements

Define Scope

Create WBS

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
12
PMBOK, 6th Edition (2017)

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
13
Work Breakdown Structure
Building a
Complex

Project
Engineering Procurement Construction Safety …
Management

Schedule Electrical Foundation

Cost Architecture External

Quality Mechanical Internal

Communications …

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
14
Scope Baseline

• Project Scope Statement

+
• WBS
Plan Scope
Management

Collect
Requirements

Define Scope

Create WBS

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
15
Responsibility Matrix (RACI)
• RACI Matrix is a table

• Responsible-Accountable-Consulted-Informed

• Project tasks derived from the WBS listed in rows and


departments and individuals in the columns

• Helps organize the project team

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
16
Sample RACI

Responsible: performs the work.


Accountable: ultimately
accountable and has Yes/No/Veto.
Consulted: needs to feedback and
contribute to the work.
Informed: needs to know of the
decision or action.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
17
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
18
Planning: Project
Schedule Management
Monitoring &
Initiating Planning Executing Closing
Controlling

Integration

Scope Scope

Schedule Schedule

Cost Cost

Quality

Resources

Communications

Risk

Procurement

Stakeholders

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
20
PMBOK, 6th Edition (2017)

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
21
Schedule Management Process

Plan Schedule Management

Define Activities
Outputs:
1. Schedule Management Plan
Sequence Activities 2. Project Schedule
3. Milestone List
4. Schedule Baseline

Estimate Activity Resources

Estimate Activity Durations

Develop Schedule

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
22
Plan Schedule Management

• The process of establishing the policies, procedure,


and documentation for planning, developing,
managing, executing, and controlling the project
schedule.

Plan Schedule
Management

Define Activities

Sequence Activities

Estimate Activity
Resources

Estimate Activity
Durations

Develop Schedule

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
23
Define Activities

• Decompose work packages in WBS into activities


required to produce them (activities consume time
and resources).
– Rolling Wave Planning: Plan the higher level, wait
until the work is clearer to plan the lower levels
(Progressive Elaboration) Plan Schedule
Management

– Milestones: Significant events within Define Activities

project schedule (important delivery Sequence Activities

Estimate Activity
Resources
dates, checkpoints, etc.) Estimate Activity
Durations

Develop Schedule

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
24
Define Activities- Example
• Project: Wedding
• Project manager- the wedding planner: Rose
• Part of the WBS: Wedding

Food Invitation Bridal

• Milestones: Invitations sent; Menu finalized; Church


booked; Dresses fitted. The invitations be printed at
least 3 months in advance to be sure everyone had
time to RSVP (client requirement).
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
25
Wedding

Food Invitation Bridal

• Find caterer • Create guest list • Shop for dress


• Finalize the menu • Pick calligrapher • Shop for shoes
• Cater the wedding • Pick printer • Choose bouquet
Break down the • Design invitations • Tailoring & fitting
activities to the • Print invitations
level at which they • Address invitations
can be estimated • Mail invitations
accurately.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
26
Define Activities (summary)

Scope Baseline Activity List


WBS
Define
Activity Attributes
Project Scope Statement Activities Milestone List

• Activity list: a lower level of WBS.


• Activity attributes: description of each activity like
predecessor, successor, or constraints, resources, etc.
• Milestones: all of important checkpoints of your project.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
27
Sequence Activities
No
• Network Diagrams Loops
Allowed
– Activity-on-Node (AON)

Activity Activity
A B

– Activity-on-Arrow (AOA) Plan Schedule


Management

Define Activities

A B Sequence Activities

0 1 2 Estimate Activity
Resources

Estimate Activity
Durations

Develop Schedule

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
28
AON vs. AOA
Predecessors
– AON Activity
B Successors
Activity
A
Activity
C
– AOA
B 2
A
0 1

C 3

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
29
Drawing a Network Diagram

Think about activity precedence. For each activity:


• Which activities must be finished before this activity
can be started?
• Which activities can be done concurrently with this
one?
• Which activities cannot be started until this activity is
finished?

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
30
Sequence Activities- Example

Pick Address Send


calligrapher invitations invitations

Finish
Start Design Print
invitations invitations

Pick
menus
printer

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
31
Predecessors (1)

• Finish to Start (FS): Print Address


invitations invitations

Give toasts
• Start to Start (SS):

Serve cake
Play “here comes
the bride”

• Finish to Finish (FF): Bride walks down


the aisle

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
32
Predecessors (2)

• External predecessors: something outside the project


work

• Discretionary predecessors: no necessity, a matter of


preference!

• Mandatory predecessors: nature of the work

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
33
Estimate Activity Resources and Duration
• Resources:
– Human resources
– Equipment and material
–… Plan Schedule
Management

Define Activities

Sequence Activities

Estimate Activity
Resources

Estimate Activity
Durations

Develop Schedule

• Padding is not allowed: we need a realistic schedule


and budget
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
34
Estimation Techniques

• Expert Judgement
• One-Point Top-Down Estimating (Analogous)
• Parametric Estimating
• Three-Point Estimating

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
35
Three-Point Estimation

Risk-based expected duration estimate (with


assumptions)
Optimistic (O), Pessimistic (P), Most Likely (M)

• Simple Average Method (straight, equal weights)


– Expected Activity Duration = (P+M+O) /3

• Beta Distribution (PERT or weighted average)


– Expected Activity Duration = (P+4M+O)/6
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
36
Example- Venue Selection

• Optimistic: the couple settles on the first venue they


visit (9 days)
• Most Likely: they will visit four to five venues and
spend sometime negotiating with the venue
operators (15 days)
• Pessimistic: They’ll comb the neighborhood and visit
every place for weeks (30 days)

Estimated Duration=(9+4(15)+30)/6=16.5 days

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
37
Exercise

• A software team gathered estimates for all of the


work they’d have to do to build the next major
release of their product. Last time it took them
around 45 days, but they’re hoping that the lessons
learned from the past release could bring the time
down to 30 days. However, the infrastructure team
needs to upgrade their servers, and they are
concerned that procurement delays could potentially
extend the project to 90 days. What is the expected
duration of project (assuming a beta distribution)?

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
38
Answer

• Optimistic Duration = 30 d
• Pessimistic Duration = 90 d
• Most Likely Duration = 45 d

• Expected Duration = 50 d

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
39
Develop Schedule

• What should you do to create a finalized schedule?


– Schedule Network Analysis
• Critical Path Method
• Schedule Compression
• Resource Optimization
Plan Schedule
Management

Define Activities

Sequence Activities

Estimate Activity
Resources

Estimate Activity
Durations

Develop Schedule

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
40
Critical Path Method

• Critical Path: Longest duration path through a


network diagram; determines the shortest time it
could take to complete the project. Delay in one
activity on this path will cause the entire project to
be delayed!
• Near-Critical Path: The path close in duration to the
critical path.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
41
Example
C, 2
A, 4

Start B, 7 Finish

D, 3 E, 5

• Start-A-C-Finish: 4+2=6
• Start-A-B-Finish:4+7=11
• Start-D-E-Finish:3+5=8

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
42
Exercise

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
43
Answer

Start-D-E-F-G-End
17
3

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
44
Critical Path Method (cont’d)

• To see exactly how much freedom you have in your


The earliest time
schedule: an activity can
The earliest time Activity Duration finish
an activity can
start Early Start Early Finish
(ES) (EF)

Activity A
The latest time an
Late Start Late Finish
activity can start
(LS) (LF)

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
45
Critical Path Method (cont’d)

• Forward Pass Method (Add ES and EF to Precedence


Network).
• ES for first activity = 0
• EF for first activity = 0 + Duration
• ES for each activity = EF for its predecessor
– If two or more predecessors: ES = The latest EF

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
46
Example
3 8
3 6 6 14
B D
14
3
0 3
Start A 4
6 14 18
E Finish
3 9
C

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
47
Critical Path Method (cont’d)

• Backward Pass Method (Add LS and LF to Precedence


Network).
• LF for last activity = its EF
• LS for last activity = its LF - Duration
• LF for each activity = LS for its successor
– If two or more successors: LF = The earliest LS

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
48
Example
3 8
3 6 6 14
B D
3 6 6 14
3
0 3
Start A 4
0 3 14 18
6
E Finish
3 9 14 18
C
8 14

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
49
Critical Path Method- Float

• Float (Slack)
– Activity Float: Amount of time an activity can be
delayed without delaying the project end date or a
milestone.
– Project Float: Amount of time a project can be
delayed without delaying the end date specified
by customer.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
50
Critical Path Method (cont’d)

• Floats
– Activities on critical path have zero float
– Float = Late Start (LS) – Early Start (ES)
– Float = Late Finish (LF) – Early Finish (EF)

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
51
Example
3 8
3 B 6 6 D 14
3 0 6 6 0 14
3
0 A 3
Start 4
0 0 3
6 14 E 18
Finish
3 C 9 14 0 18
8 5 14

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
52
Exercise

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
53
Answer

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
54
Exercise

What is the float for each activity?

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
55
Answer

Critical Path: 17

A=2, B=2, C=7, D=0, E=0, F=0, G=0, H=6, I=6


From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
56
Project Schedule Format

• Network Diagram: Show interdependencies and


manage the schedule.
• Milestone Chart: Report to customer or senior
management
• Gantt Chart (Bar Chart): Track progress or report to
the project team.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
57
Milestone Chart

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
58
Gantt Chart

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
59
ACTIVITY DEFINITION AND SEQUENCING
WORK BREAKDOWN STRUCTURE
OBJECTIVES

PROJECT HOW
CHARTER
WHAT

ESTIMATION

ORGANIZATIONAL STRUCTURE WHEN HOW MUCH


WORK
PACKAGE
(WP) WP SCHEDULE BUDGET
WP $

RESPONSIBILITIES ASSIGNMENT
PARTICIPANTS
WP

WHO

Source: Pierre Ménard, UQAM

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
60
Develop Schedule (cont’d)

• What should you do to create a finalized schedule?


– Schedule Network Analysis
• Critical Path Method (Normal/Standard Resource
Loading)
• Schedule Compression
• Resource Optimization
Plan Schedule
Management

Define Activities

Sequence Activities

Estimate Activity
Resources

Estimate Activity
Durations

Develop Schedule

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
61
Schedule Compression
• Why?
– A completion date required by customer that
cannot be met, Bring the delayed project back in
line, Adjust the project for changes.
• Objective?
– To compress the schedule without changing the
project scope.
• How?
– Fast tracking
– Crashing
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
62
Fast Tracking

• Taking the critical path activities that were originally


planned in series and doing them in parallel for some
or all of their duration; Overlapping Activities
• Downside?
– Reworks, increased risk, more attention to
communication.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
63
Example

• You guess that 70% of the invitees will RSVP. Instead


of waiting for all of them to come in, you go ahead
and reserve the tables and chairs now.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
64
Example

• Which activity would you fast track to shorten the


project length?

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
65
Crashing
• Adding or adjusting resources in order to compress
the schedule while maintaining the original project
scope (Trade time for money).
• Downside?
– Increased costs, increased risk.
• Examples: Hire contract resources to supplement the
internal resources on the critical path activities, Buy
a software application.
𝐶𝑟𝑎𝑠ℎ 𝐶𝑜𝑠𝑡 − 𝑁𝑜𝑟𝑚𝑎𝑙 𝐶𝑜𝑠𝑡
𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑆𝑙𝑜𝑝𝑒 $ 𝑝𝑒𝑟 𝑑𝑎𝑦 =
𝐶𝑟𝑎𝑠ℎ 𝑇𝑖𝑚𝑒 − 𝑁𝑜𝑟𝑚𝑎𝑙 𝑇𝑖𝑚𝑒

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
66
Crashing Example

B,2 E,3

A,3 C,2

D,4

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
67
Crashing Example (cont’d)
Duration Cost Activity
Activity Prec.
(Norm/Crash) (Norm/Crash) Slope
A - 3,2 40 , 80 -40
B A 2,1 20 , 80 -60
C A 2,2 20 , 20 -
D* A 4,1 30 , 120 -30
E** B 3,1 10 , 80 -70 (2 d)
*Partial crashing allowed: it can be crashed one day at a time.
** Partial crashing not allowed: it cannot be broken to one-day
segments.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
68
Crashing Example (Cont’d)
Reduce the duration by one day:
Critical Time= 8 days
B,2 E,3
Total Cost=$120
A,2 C,2

D,4
A,3  A,2
Project Time= 7 days
Total Cost=$160
• Least expensive way, critical path: Crash A
• Is there a change in critical path? No
• Project becomes one day shorter!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
69
Crashing Example (cont’d)
Duration Cost Activity
Activity Prec.
(Norm/Crash) (Norm/Crash) Slope
A - 3,2 40 , 80 -40
B A 2,1 20 , 80 -60
C A 2,2 20 , 20 -
D* A 4,1 30 , 120 -30
E** B 3,1 10 , 80 -70 (2 d)
*Partial crashing allowed: it can be crashed one day at a time.
** Partial crashing not allowed: it cannot be broken to one-day
segments.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
70
Crashing Example (Cont’d)
Reduce the duration by two days:
Critical Time= 8 days
B,1 E,3
Total Cost=$120
A,2 C,2

D,4
A,3  A,2 + B,2 B,1
Project Time= 6 days
Total Cost=$220
• Least expensive way, critical path: Crash A + B
• Is there a change in critical path? Yes
• Project becomes two days shorter!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
71
Crashing Example (Cont’d)
Reduce the duration by three days:
Critical Time= 8 days
B,2 E,1
Total Cost=$120
A,2 C,2

D,4
E,3  E,1 + A,3 A,2 Not
enough!
Project Time= 6 days
Total Cost=$230
• Least expensive way, critical path: Crash E + A
• Is there a change in critical path? Yes
• Project becomes two days shorter!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
72
Crashing Example (cont’d)
Duration Cost Activity
Activity Prec.
(Norm/Crash) (Norm/Crash) Slope
A - 3,2 40 , 80 -40
B A 2,1 20 , 80 -60
C A 2,2 20 , 20 -
D* A 4,1 30 , 120 -30
E** B 3,1 10 , 80 -70 (2 d)
*Partial crashing allowed: it can be crashed one day at a time.
** Partial crashing not allowed: it cannot be broken to one-day
segments.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
73
Crashing Example (Cont’d)
Reduce the duration by three days:
Critical Time= 8 days
B,2 E,1
Total Cost=$120
A,2 C,2

D,3
E,3  E,1 + A,3 A,2+ D,4 D,3
Project Time= 5 days
Total Cost=$260
• Least expensive way, critical path: Crash E + A + D
• Is there a change in critical path? Yes
• Project becomes three days shorter!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
74
Crashing Flowchart
Find The Critical Note: Expedite Project Duration
Path (One time unit at a time)

Expedite Cheapest
Check if the Critical Path
Task(s)
Changed!
(on the critical path)

No
Reached the Goal or
Expediting-Cost>Benefit

Yes
End
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
75
Fast Tracking, Crashing, or both?

• Always see all the potential options and then select


the one(s) or a combination of them that has the
least negative impact on the project.

From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved
76

You might also like