STABILIZATION OF THE POWER GENERATED BY THE

TURBINE
INTEGRATING PROJECT
Robin Jaimes, Melitza Medina, Nino Toloza, Hermes Duran, Ivan Duarte

PRODUCTION & USE OF FUELS


ENERGY ENGINEERING

INTRODUCTION RESULTS
In this laboratory report we will show the behavior of the
turbine we have in the pilot plant, we will show data and Graphical analysis : It can be seen that as we improve
graphs of the input and output behavior; Three proposals the turbine stability behaviour, fluctuations are reduced,
for energy optimization will be shown. but the generated power decreases.
We will work only with the boiler and the turbine, without
opening the way to the other elements.
Our main objective is to stabilize the power released by
the turbine

PROPOSAL

First proposal for regulation and


consumption of generated power.
The proposal is based on the installation of a
charge regulator connected to the DC direct
current generator located in the pilot plant CONCLUSION
ngineering laboratory.
Second proposal for the regulation and
consumption of generated power.
This proposal is composed of two possible According to the data analyzed in the pilot plant
configurations identified by the range in test and thanks to the knowledge provided by
power generated by the turbine operating at some teachers, we conclude that the best proposal
conditions of regulation and restriction of for the stabilization of the power generated by the
steam flow. turbine and the use of the energy generated by it, is
the following:A charge regulator will be
a. First regulation proposal with implemented at the exit of the turbine, since
implementation of existing physical plant. although much more stabilization has been
The operating conditions of the steam
achieved, there are still small oscillations that with
production cycle are restricted in the
the charge regulator (battery) it will be possible to
pressure delta with which the boiler
operates, decreasing a pre-established maintain constants. Once our values are constant
delta from 12 psi to 8 psi, with a maximum over time we adapt it to an inverter which is a
pressure of 125 psi device that changes or transforms a direct current
a)Second regulation proposal with input voltage to a symmetrical alternating current
implementation of a pilot pressure output voltage, with the magnitude and frequency
reducing desired by the user. Once our alternating current
This implementation is based on proposal voltage is obtained, we will use it to charge a
b. (In order to generate higher power battery, which once charged, can be used for
values in the generator) Maintaining multiple applications.
operating conditions in the boiler, but
adding a pilot pressure regulating valve that
allows the regulation of higher steam flow
in order to operate at higher percentages of
openings in the electrovalve of the main
distribution line.