Professional Documents
Culture Documents
Definition
Tunnels are artificial underground
passages opened at both ends constructed
for different purposes.
Required for highways, railways,
sewerage, water supply, public utilities
and canals.
Necessitated when open excavation of
strata becomes uneconomical, not only
construction cost but for maintenance as
well. ed
n u
nti
o
History
The oldest tunnel was constructed 4000 years
ago in ancient Babylon to underpass the bed of
river Euphrates and to establish an
underground connection between the royal
palace and Temple of Jove.
The length of the tunnel was 1 km and it was
built with the considerable cross-section
dimensions of 3.6 m by 4.5 m.
In the second half of the 20th century, with the
progress in development of both explosives and
equipment, underground construction became
feasible.
u ed
ti n
o n
Geological Considerations or ground
properties before constructing any tunnel
project:
Wall
Invert Bottom
u ed
ti n
o n
Tunnelling Methods
Rough classification of methods
Excavation: An excavation process without
removing the overlying rock or soil
• Steps: excavating-remove muck-supporting-
lining-ventilation-draining
• Drill & Blast, hammer, roadheader, ....
Cut and cover: trenching to excavate and construct a
tunnel, and then backfilling earth over it.
Immersed tunnel: lowering prefabricated tunnel
elements into a dredged channel and joining them
up under water
• Concrete
u ed
• Steel ti n
o n
Bottom-up method: The main site is excavated,
with ground support as necessary, and the tunnel
is constructed within. The tunnel may be of in situ
concrete, precast concrete, precast arches, or
corrugated steel arches. The trench is then
carefully back-filled above the tunnel roof and the
surface is restored.
Coffer Dam and
hydroelectric Tunnel
Top-down method: Here side support walls and
cap beams are constructed from ground level
typically with slurry walls, or secant piling. Then a
shallow excavation allows making the tunnel roof
of precast beams or in situ concrete. The surface is
then restored except for access openings. This
allows early reinstatement of roadways, services
and other surface features. Excavation then takes
place under the permanent tunnel roof, and the
base slab is constructed.
Tunnelling in Firm ground
Traditional methods. Involving drilling and blasting
u ed
ti n
o n
Because stand-up time is generally short when
tunneling through soft ground, cave-ins are a
constant threat. To prevent this from happening,
engineers use a special piece of equipment called a
shield.
A shield is an iron or steel cylinder literally pushed
into the soft soil. It carves a perfectly round hole and
supports the surrounding earth while workers remove
debris and install a permanent lining made of cast
iron or precast concrete.
When the workers complete a section, jacks push the
shield forward and they repeat the process.
Tunnelling in Running Ground
Many methods
Principle is, Linear plates are pushed in starting
from crown
Cavity is excavated
Additional linear plates are pushed one by one and
bolted
Arch section gradually widened down to springing
line.
u ed
ti n
o n
Tunnelling in Rocks
Tunnels are driven in rocks by drilling holes in the rock
face, loading the holes with explosives, blasting and
removing the broken rock
Each sequence full cross section of the tunnel may be
excavated, or one or more drifts may be there.
Drilling pattern for holes of explosives may differ
depending upon rock type, cross section, experience
expertise and type of explosive suggested.
Methods are similar in principle like
Full Face Method
Top Heading and benching
Drift Method
u ed
ti n
o n
Tunneling through hard rock almost always involves
blasting. Workers use a scaffold, called a jumbo, to place
explosives quickly and safely.
The jumbo moves to the face of the tunnel, and drills
mounted to the jumbo make several holes in the rock. The
depth of the holes can vary depending on the type of rock,
but a typical hole is about 10 feet deep and only a few
inches in diameter.
Next, workers pack explosives into the holes, evacuate the
tunnel and detonate the charges. After vacuuming out the
noxious fumes created during the explosion, workers can
enter and begin carrying out the debris, known as muck,
using carts.
Then they repeat the process, which advances the tunnel
slowly through the rock.
Fire-setting is an alternative to blasting. In this
technique, the tunnel wall is heated with fire, and then
cooled with water. The rapid expansion and contraction
caused by the sudden temperature change causes large
chunks of rock to break off. The Cloaca Maxima, one of
Rome's oldest sewer tunnels, was built using this
technique.
The stand-up time for solid, very hard rock may measure
in centuries. In this environment, extra support for the
tunnel roof and walls may not be required. However, most
tunnels pass through rock that contains breaks or pockets
of fractured rock, so engineers must add additional
support in the form of bolts, sprayed concrete or rings of
steel beams. In most cases, they add a permanent concrete
lining
Sequence of operation in Rocky
Strata (Drill and Blast)
Marking tunnel profile.
Setting up and drilling
Loading explosive and blasting
Removing the foul gases
Checking
Scaling
Mucking
Rock bolting and lining
u ed
ti n
o n
Modern Tunnel Construction Methods:
Drill and blast
Mechanical drilling/cutting
Cut-and-cover
Immersed tunnels
Tunnel boring machines (TBMs)
New Austrian Tunnelling Method
(NATM)
u ed
ti n
o n
Road headers